Framework Agreements for Project and Programme Management and Technical and Design Services; and Estates Development Advisor Services (Notice of Decisions Ref. 497)
NotedExecutive1 paper
Cabinet noted this item on Thursday 13 February 2014. Below is the council's own wording, with the papers it was decided on.
That Cabinet note the update to the earlier report of June 2013 and endorse the actions taken since then, as set out in this report. 2. That delegated authority to award the Framework Agreements is given to the Director of City Renewal in consultation with the relevant Cabinet Member. 3. That delegated authority to award individual pieces of work under the Framework Agreements is given to the Director of City Renewal and relevant Assistant Directors, in consultation with the relevant Cabinet Member.
Word for word from the decision Stoke-on-Trent published for this meeting.Source: moderngov.stoke.gov.uk
1.1The purpose of the report is to provide an update and further detail to an earlier Cabinet Report (June 2013) which gave authority to commence procurement processes to establish Framework Agreements for Construction Related Professional Services and Estates Development Advisor Services. The update is summarised below. • The first Framework has been re-titled Project and Programme Management and Technical and Design Services to more accurately reflect the scope of services required. The Technical and Design Service elements were not included in the scope of the original report. • The scope and title of the second Framework remains as Estates Development Advisor Services. • Each Framework will run for a three year duration. • The Frameworks will be set up in an ERDF compliant manner to allow these externally funded projects to be procured under the Frameworks by way of mini-competition. • Other local authorities in Staffordshire will be consulted to see if they wish to be included as a potential user under the Frameworks. • The previous report did not include a recommendation for delegated authority to award the Framework Agreements to be given to the Director of City Renewal in consultation with the relevant Cabinet Member. Furthermore, that delegated authority to award discrete pieces of work under the Framework Agreements is given to the Director of City Renewal and relevant Assistant Directors.
Report Page 1 092C
The Framework Agreements will be procured in compliance with EU 1.2 procurement law and will be called off on an “as required basis” to provide additional support to the capital programme. They will improve the efficiency and effectiveness of the delivery of projects within the “Mandate for Change’’.
1.3Cabinet should note that the framework agreements that currently exist for technical services will be unaffected by the new proposed Frameworks Agreements, and will continue to run in parallel with them.
2 Recommendation(s)
2.1That Cabinet note the update to the earlier report of June 2013 and endorse the actions taken since then, as set out in this report. That delegated authority to award the Framework Agreements is given to the 2.2 Director of City Renewal in consultation with the relevant Cabinet Member. That delegated authority to award individual pieces of work under the 2.3 Framework Agreements is given to the Director of City Renewal and relevant Assistant Directors, in consultation with the relevant Cabinet Member.
Options considered
3.1Option 1 (Recommended) – Procure our own Framework Agreements A number of benefits will arise from procuring our own Framework Agreements as follows: a. The Council will be able to design the Framework Agreements to exactly match our needs and requirements. b. A bespoke legal contract will be drawn up for the Frameworks, again to match our exact requirements. c. By entering into a Framework Agreement, the City Council is not committing itself to any expenditure and can use the Framework as and when required (to a greater or lesser extent) to meet requirements. d. Framework agreements allow the Council to call-off requirements in a timely way without the need to carry out a full procurement process including advertisement for each individual scheme or project.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Framework Agreements for Project and Programme Management and Technical and Design Services; and Estates Development Advisor Services (Notice of Decisions Ref. 497)Decisions
452Framework Agreements for Project and Programme Management and Technical and Design Services; and Estates Development Advisor Services (Notice of Decisions Ref. 497)This decision
Framework Agreements for Project and Programme Management and Technical and Design Services; and Estates Development Advisor Services (Notice of Decisions Ref. 497)This decision
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.