Stoke-on-Trent City Council
Cabinet, Tuesday 14 July 2026 at 1.00pm

Proposed establishment of contract frameworks for repairs and maintenance works to Housing Revenue Account owned stock (Notice of Decisions Reference: 2415)

Agreed Executive 1 paper

AI summaryStoke-on-Trent Cabinet approves procurement of three four-year contract frameworks for void clearances, structural and damp proofing works, and environmental works to council social housing stock, worth an estimated £2.3M, £360,000 and £3M respectively.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedProcurement exercises for void clearances, environmental works, structural and damp proofing
Moneycirca £2.3M, £360,000 and £3MEstimated four-year framework values, based on historical data
What happens nextProcurement to startFramework agreements to be awarded under delegated authority
Who it affectsCouncil social housing tenantsAll wards, 17,022 HRA units as at 31 March 2026

What was decided

Cabinet approved three separate four-year procurement exercises for internal and external property clearances, environmental works, and structural and damp proofing works to Housing Revenue Account owned social housing stock. Report 1.0

Authority to approve procurement and appoint contractors was delegated to the Corporate Director of Housing Regeneration and Operations, in consultation with the Cabinet Member for Safe and Resilient Communities and Housing.

Authority to award and enter into framework agreements was delegated to the Corporate Director of Housing Regeneration and Governance, in line with the council's procurement and decision making procedures.

Why

The council has 17,022 social housing units and a duty to keep them safe, habitable and well maintained, and the council's in-house Responsive Maintenance Service lacks the resources to carry out all the work required.

Existing JCT Measured Term Contract arrangements for these workstreams are due to expire in January 2027 and March 2027, so replacement frameworks are needed.

The new frameworks will support compliance with the Decent Homes Standard, the council's Empty Property Standard, and statutory health and safety duties. Report 6.0

What happens next

Run three Most Advantageous Tender exercises, with 10% of the evaluation weighting on responsible procurement covering social, economic and environmental characteristics.

Award framework agreements under delegated authority, with Legal Services drafting each agreement based on the JCT MTC 2024 template and the Procurement Act 2023. Report 8.2

Each framework will list up to two contractors available for call-off, and a further report will set out confirmed contract values once procurement is complete.

The money

  • circa £2.3M Estimated value of the four-year internal and external property clearances framework
  • circa £360,000 Estimated value of the four-year structural and damp proofing framework
  • circa £3M Estimated value of the four-year environmental works framework

Options considered

  • Rejected: Do nothing. Would risk failing the Decent Homes Standard and Empty Property Standard, with potential regulatory action, unlimited fines, and reputational damage
  • Rejected: Tender using a third party framework. Would incur additional framework fees, whereas open tender should give more competitive prices
  • Chosen: Establish three new four-year contract frameworks via open tender. Maintains property standards, replaces expiring JCT MTC arrangements, and provides capacity the in-house team cannot deliver Report 3.0, 6.0, 7.0

Implications

  • Financial: Framework expenditure will be met from existing Housing Revenue Account budgets, with revenue funding for responsive repairs and void clearances and capital funding for some environmental works, and a further report will set out confirmed contract values after procurement.
  • Legal: Procurement will follow the Procurement Act 2023, with framework agreements based on JCT MTC 2024 and drafted by Legal Services. Report 8.2
  • Equalities: Equality Impact Assessment screenings found no negative outcomes for any group with a protected characteristic, so full Equality Impact Assessments are not required. Report 9.2
  • Climate: The proposals will not negatively impact on the environment, and 10% of tender weighting will cover environmental characteristics. Report 9.4
  • Risk: Risk that tendered rates are higher than expected, mitigated by reviewing usage and specification, and risk of contractor resource scarcity, mitigated by listing up to two contractors on each framework for call-off.
  • Staffing: There are no direct human resource implications from this decision.
  • Other: The proposals do not directly impact on social inequalities, including poverty, social exclusion or health.

Who and where

  • Tenants of the council's 17,022 Housing Revenue Account homes (as at 31 March 2026) Report P23
  • The council's Responsive Maintenance Service, which will oversee framework operation and monitoring
  • Tendering contractors bidding for the three frameworks
  • Residents across all wards of Stoke-on-Trent Report P23

Timeline

  • 31st March 2026: Council social housing stock recorded as 17,022 units
  • January 2027: Existing JCT MTC framework for internal and external property clearances is due to expire
  • February 2027: Proposed new internal and external property clearances framework expected to commence
  • March 2027: Existing JCT MTC frameworks for structural and damp proofing and for environmental works are due to expire
  • April 2027: Proposed new structural and damp proofing and environmental works frameworks expected to commence

Plain English for the jargon

  • HRA: Housing Revenue Account: the ring-fenced account that councils use to manage income and spending on their own social housing stock
  • Void property: A council home that is empty between tenancies and needs work before it can be re-let
  • RMS: Responsive Maintenance Service: the council's in-house maintenance delivery function
  • JCT MTC 2024: Joint Contracts Tribunal Measured Term Contract 2024, a standard construction contract template for ongoing maintenance work
  • Framework agreement: An arrangement with pre-selected contractors that the council can call off to deliver work without re-tendering each time
  • Most Advantageous Tender (MAT): A procurement evaluation approach under the Procurement Act 2023 that scores tenders on price, quality and other criteria
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item27

Resolved

Agreed ( i ) - That Cabinet approves the implementation of a procurement exercise for the creation of a framework for the provision of internal and external property clearances to void properties within the Council owned social housing stock for a period of four years. Agreed (ii) - That Cabinet approves the implementation of a procurement exercise for the creation of a framework for the provision of environmental works to Council owned social housing stock for a period of four years. Agreed (iii) - That Cabinet approves the implementation of a procurement exercise for the creation of a framework for the provision of structural and damp proofing works to Council owned social housing stock for a period of four years. Agreed (iv) - That Cabinet delegates authority to the Corporate Director of Housing Regeneration and Operations, in consultation with the Cabinet Member for Safe and Resilient Communities and Housing, to approve the procurement and appointment of contractors to the frameworks referenced in 1.1, 1.2 and 1.3 above. Agreed (v) - That Cabinet delegates authority to the Corporate Director of Housing Regeneration and Governance, operating in accordance with the established frameworks, to award and enter into framework agreements with the selected contractors in accordance with the Council’s agreed procurement and decision making procedures.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 5 pages

Cabinet

Tuesday, 14 July 2026

Open

Proposed establishment of contract frameworks for repairs and maintenance works to Housing Revenue Account owned stock.

Report of Corporate Director of Housing, Regeneration and Operations - Carol Gibbs Cabinet Member for Safe and Resilient Communities and Housing

Purpose of Report The purpose of the report is to seek approval to establish three separate contract frameworks to support the delivery of property repairs and maintenance works to Housing Revenue Account (HRA) owned stock.

1.0Recommendations 1.1 That Cabinet approves the implementation of a procurement exercise for the creation of a framework for the provision of internal and external property clearances to void properties within the Council owned social housing stock for a period of four years. 1.2 That Cabinet approves the implementation of a procurement exercise for the creation of a framework for the provision of environmental works to Council owned social housing stock for a period of four years. 1.3 That Cabinet approves the implementation of a procurement exercise for the creation of a framework for the provision of structural and damp proofing works to Council owned social housing stock for a period of four years. 1.4 That Cabinet delegates authority to the Corporate Director of Housing Regeneration and Operations, in consultation with the Cabinet Member for Safe and Resilient Communities and Housing, to approve the procurement and appointment of contractors to the frameworks referenced in 1.1, 1.2 and 1.3 above. 1.5 That Cabinet delegates authority to the Corporate Director of Housing Regeneration and Governance, operating in accordance with the established frameworks, to award and enter into framework agreements with the selected contractors in accordance with the Council’s agreed procurement and decision making procedures.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Proposed establishment of contract frameworks for repairs and maintenance works to Housing Revenue Account owned stock (Notice of Decisions Reference: 2415)Decisions 5 pages DownloadRead as text

At this meeting

Whole meeting
16Minutes of Last Meeting (23/06/26)On the agenda 20Progression of proposals for local government reorganisation and devolution in Stoke-on-Trent and Staffordshire (Notice of Decisions Reference: 2419)Agreed 21Vehicle & Plant Hire Framework (Notice of Decisions Reference: 2411)Agreed 2218+ Care Homes Contracts and Updating of the Residential Charging Policy (Notice of Decisions Reference: 2413)Agreed 23VCSE integrated Wellbeing Pathways Re-Commission (Notice of Decisions Reference: 2401)Agreed 24School-based Nursery Capital Grant 2027-2030 (Notice of Decisions Reference: 2422)Agreed 25Schools Capital Programme 2026-27 (Notice of Decisions Reference: 2421)Agreed 26Future Delivery Model for Bentilee Nursery School (Notice of Decisions Reference: 2416)Agreed
27Proposed establishment of contract frameworks for repairs and maintenance works to Housing Revenue Account owned stock (Notice of Decisions Reference: 2415)This decision
28Adoption of a new Civil Penalties Policy for Private Sector Housing (Notice of Decisions Reference: 2402)Agreed 29Renters Right Delegation 2025 (Notice of Decisions Reference: 2420)Agreed 30Phase 2 - Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2429)Agreed 31IT Network Hardware Refresh (Notice of Decisions Reference: 2428)Agreed 32Review of Policy on the Regulation of Investigatory Powers Act 2000 (Notice of Decisions Reference: 2450)Agreed 33Packmoor - Feedback from the recent Masterplan consultation and approval of the preferred Masterplan option (Notice of Decisions Reference: 2418)Agreed 34Stoke-on-Trent Local Plan 2020-2040: Publication Plan (Regulation 19) (Notice of Decisions Reference: 2388)Agreed 35Exclusion of the PublicOn the agenda 36Renewal of Social Care System (Liquid Logic) (Notice of Decisions Reference: 2407) (Para. 3)Private 37Development Agreement for Etruscan Square sites, Hanley (Notice of Decisions Reference: 2349) (Para. 3)Private

On this subject at Stoke-on-Trent

Search all
  1. Proposed establishment of contract frameworks for repairs and maintenance works to Housing Revenue Account owned stock (Notice of Decisions Reference: 2415)This decision
  2. Proposed establishment of frameworks to support the delivery of property improvements to Housing Revenue Account owned stock (Notice of Decisions Reference: 2425)Agreed
  3. Proposed establishment of Two Contract Frameworks; One for Replacing External Doors and Associated Canopies and Cladding and One for Aids and Adaptations Internal and External Alterations (Notice of Decisions Reference: 2373)Agreed

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies