IT Network Hardware Refresh (Notice of Decisions Reference: 2428)

Agreed Executive 1 paper

AI summaryStoke-on-Trent Cabinet approves £1,765,000 direct award to Virgin Media O2 to replace end-of-life Cisco network hardware across its 50 council buildings, using the CCS Network Services 3 framework.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedNetwork equipment and upgrade via CCS framework RM6116
Money£1,765,000Capital funding, provided for in the capital programme
What happens nextProcurement to proceedDirector, Digital, Transformation & Customer Services to award the contract
Who it affectsCouncil IT networkReplaces Cisco switch hardware installed in 2015 across 50 buildings

What was decided

Cabinet agreed to use the Crown Commercial Services RM6116 Network Services 3 framework to directly award a contract to Virgin Media O2 (Virgin Media Business Limited) for network equipment and upgrade at a cost of £1,765,000. Report 1.0

Cabinet delegated authority to the Director of Digital, Transformation and Customer Services to take all decisions relating to the procurement, including award of contracts. Report 1.0

Why

The council's existing Cisco network switch hardware, installed in 2015, is reaching end of life and will no longer be supported by Cisco, creating risks of performance degradation, outages and cyber security exposure.

Virgin Media O2 was chosen because it designed and supports the current network, has worked with the council for over 20 years, and its Cisco solution integrates with the existing data centre and wireless infrastructure, avoiding the cost and complexity of a new vendor.

The CCS RM6116 framework offers a speedy, compliant procurement route under the Public Contracts Regulations 2015, and an MoU with Virgin Media O2 provides tiered discounts and social value commitments.

What happens next

The Director of Digital, Transformation and Customer Services will take all decisions needed to award and document the contract, with legal support to ensure public funding is protected. Report 1.0

The network is being optimised, reducing the number of switches required from 216 to 144, with an expected life of at least 10 years.

The money

  • £1,765,000 Total cost of the IT network hardware refresh project, provided for within the capital programme Report 1.0
  • £1,300,000 Network Switches element of the proposal
  • £465,000 Cisco Gateway element of the proposal
  • £2,287,556 Indicative cost if procurement was carried out later in the year, due to rising hardware prices
  • £56m over 2 years Expected Virgin Media O2 funding commitment to the National Databank under the MoU

Options considered

  • Chosen: Direct award to Virgin Media O2 via CCS RM6116 framework. Most advantageous solution, compliant procurement route, supplier has detailed knowledge of the network, avoids cost and complexity of new vendor Report 5.0
  • Rejected: Do nothing. Would leave infrastructure out of support and beyond end of life, not a sensible or realistic option
  • Rejected: Competitive procurement process. Would extend the process significantly, does not guarantee another bidder or better pricing, carries significant risk and cost of change
  • Rejected: Full open tender process. Additional time and complexity present material risk to cost certainty, service continuity and delivery given end-of-life status and imminent price increases

Implications

  • Financial: Total cost of £1.765 million is provided for within the capital programme; delaying could push the cost to an indicative £2,287,556.
  • Legal: Use of the CCS RM6116 framework ensures compliance with the Public Contracts Regulations 2015; legal support should be obtained when documenting the contract.
  • Equalities: An Equality Impact Assessment is not required; the proposals do not impact on social inequalities.
  • Climate: No environmental impact identified; supplier commitments include Carbon Net Zero operations by 2025, aiming for full net zero by 2040.
  • Risk: Doing nothing is the significant risk: loss of manufacturer support would lead to performance degradation, outages and cyber security exposure. The direct award via CCS framework mitigates procurement risk.
  • Staffing: No human resources implications identified.

Who and where

  • Council staff and hybrid workforce using the IT network across 50 buildings
  • The council's digital, data and building systems reliant on the network (computers, printers, building control, wireless access points, IoT devices)
  • Neighbouring authorities Newcastle-under-Lyme and Staffordshire Moorlands, which also use Cisco switches and could integrate networks under a future combined authority

Timeline

  • 2015: Cisco switch hardware installed across the council's IT network
  • 2022: Council invested in data centre networking with Virgin Media and Cisco
  • Tuesday, 14 July 2026: Cabinet meeting at which the decision was made Report P1, P2
  • at least 10 years: Expected operational life of the new network switches

Plain English for the jargon

  • CCS RM6116 Network Services 3 framework: A procurement framework established by Crown Commercial Services for buying IT network hardware and services, compliant with the Public Contracts Regulations 2015.
  • Cisco DNA Centre: Management platform for the campus network infrastructure, integrating with the data centre network so security policies apply across the whole network.
  • Cisco Gateway: Security product that filters web traffic, blocks malware and restricts access to sites that risk data loss for staff on site and at home.
  • Memorandum of Understanding (MoU): Agreement with Crown Commercial Services providing Virgin Media O2 with tiered discounts based on past spend, plus social value, carbon net zero and National Databank funding commitments.
  • Direct award: A procurement route where a contract is awarded to a single named supplier on a framework, without a competitive tender.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item31

Resolved

Agreed ( i ) - To utilise Crown Commercial Services RM6116 Network Services 3 framework to directly award to Virgin Media O2 (Virgin Media Business Limited) for network equipment and upgrade at a cost of £1,765,000 Agreed (ii) - To delegate authority to the Director – Digital, Transformation & Customer Services to take all decisions relating to this procurement including award of contracts.
Word for word from the decision Stoke-on-Trent published for this meeting. Source: moderngov.stoke.gov.uk

Follow this further

Built from Stoke-on-Trent's papers

What the report saysPro

Report to Cabinet, 4 pages

Cabinet

Tuesday, 14 July 2026

Open

IT Network Hardware Refresh

Report of Chief Executive - Jon Rouse Cabinet Member for Finance, Anti-Poverty, Governance and Corporate Services

Purpose of Report This report seeks approval to procure IT network hardware to replace end of life equipment

1.0Recommendations 1.1 To utilise Crown Commercial Services RM6116 Network Services 3 framework to directly award to Virgin Media O2 (Virgin Media Business Limited) for network equipment and upgrade at a cost of £1,765,000 1.2 To delegate authority to the Director – Digital, Transformation & Customer Services to take all decisions relating to this procurement including award of contracts.

2.0Background and Introduction 2.1 The Council has an IT network based around Cisco switch hardware installed in 2015. This supports 50 buildings connected via the SPON city fibre network. The hardware is now reaching end of life when it will no longer be supported by Cisco. This would result in performance degradation and outages as hardware fails, and would be a cyber security risk as there would no longer be updates provided by the manufacturer. 2.2 In 2022 the council invested in the Data Centres networking with Virgin Media and Cisco. This provides a high bandwidth backbone for the Council servers and applications, with deep integration with the core network giving a seamless experience for staff while protecting the network with unified security policies.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
IT Network Hardware Refresh (Notice of Decisions Reference: 2428)Decisions 4 pages DownloadRead as text

At this meeting

Whole meeting
16Minutes of Last Meeting (23/06/26)On the agenda 20Progression of proposals for local government reorganisation and devolution in Stoke-on-Trent and Staffordshire (Notice of Decisions Reference: 2419)Agreed 21Vehicle & Plant Hire Framework (Notice of Decisions Reference: 2411)Agreed 2218+ Care Homes Contracts and Updating of the Residential Charging Policy (Notice of Decisions Reference: 2413)Agreed 23VCSE integrated Wellbeing Pathways Re-Commission (Notice of Decisions Reference: 2401)Agreed 24School-based Nursery Capital Grant 2027-2030 (Notice of Decisions Reference: 2422)Agreed 25Schools Capital Programme 2026-27 (Notice of Decisions Reference: 2421)Agreed 26Future Delivery Model for Bentilee Nursery School (Notice of Decisions Reference: 2416)Agreed 27Proposed establishment of contract frameworks for repairs and maintenance works to Housing Revenue Account owned stock (Notice of Decisions Reference: 2415)Agreed 28Adoption of a new Civil Penalties Policy for Private Sector Housing (Notice of Decisions Reference: 2402)Agreed 29Renters Right Delegation 2025 (Notice of Decisions Reference: 2420)Agreed 30Phase 2 - Fire Safety Improvements to High Rise Residential Blocks (Notice of Decisions Reference: 2429)Agreed
31IT Network Hardware Refresh (Notice of Decisions Reference: 2428)This decision
32Review of Policy on the Regulation of Investigatory Powers Act 2000 (Notice of Decisions Reference: 2450)Agreed 33Packmoor - Feedback from the recent Masterplan consultation and approval of the preferred Masterplan option (Notice of Decisions Reference: 2418)Agreed 34Stoke-on-Trent Local Plan 2020-2040: Publication Plan (Regulation 19) (Notice of Decisions Reference: 2388)Agreed 35Exclusion of the PublicOn the agenda 36Renewal of Social Care System (Liquid Logic) (Notice of Decisions Reference: 2407) (Para. 3)Private 37Development Agreement for Etruscan Square sites, Hanley (Notice of Decisions Reference: 2349) (Para. 3)Private

More from Stoke-on-Trent Cabinet

All decisions
MeetingDecisionOutcome
3 Nov 2026 Extension to funding agreement between Stoke-on-Trent City Council and Thrive at Five (Notice of Decisions Reference: 2482)Agreed ( i ) - Approval is granted to extend the funding agreement between Stoke-on-Trent City Council and Thrive at ... Agreed Open
3 Nov 2026 Soft Block Fostering Options (Notice of Decisions Reference: 2468)Agreed ( i ) - That approval is granted to undertake a competitive procurement exercise for a soft block fostering co... Agreed Open
3 Nov 2026 Youth Justice Strategic Plan (Notice of Decisions Reference: 2470)Agreed - That Cabinet approves the Youth Justice Plan 2026/27 and recommends its adoption by the City Council. N.B. T... Agreed Open
3 Nov 2026 Reviewing powers for reducing anti-social behaviour including requiring the removal of facing coverings where necessary and appropriate (Notice of Decisions Reference: 2477)Agreed ( i ) – That Cabinet note the current Public Spaces Protection Orders (PSPOs) operating within Hanley and Long... Agreed Open
3 Nov 2026 Housing Revenue Account (HRA) Rent Setting Report 2027/28 (Notice of Decisions Reference: 2457)Agreed - That Cabinet recommends to City Council that, as part of the budget setting processes approval is given to: ... Agreed Open