The Cabinet, Monday 5 October 2026

New Settlement and Large Urban Extension - Community Infrastructure

Noted Executive 2 papers

AI summaryStratford-on-Avon District Council Cabinet endorses Community Infrastructure Strategy from Hyas Associates, feeding findings into the South Warwickshire Local Plan and preparing a 2027/28 growth bid to keep Community Builder roles in three new settlements.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedFour-part decision noted strategy and set follow-up actions
Money2027/28 growth bid plannedNo immediate cost, bid for Community Builders work
What happens nextLocal Plan work and budget bidFindings feed into South Warwickshire Local Plan
Who it affectsNew settlements and large urban extensionsCommunities in Stratford-upon-Avon, Bidford-on-Avon, Shackleton, Meon Vale

What was decided

The Cabinet noted the agenda report and the Community Infrastructure Strategy at Appendix 1, and agreed its findings should be considered in the development and delivery of the South Warwickshire Local Plan. Report P7

A growth bid is to be prepared for the 2027/28 budget setting process to secure the medium-term delivery of the tendered Community Builder work in Stratford-upon-Avon, Bidford-on-Avon, Shackleton and Meon Vale. Report P7

The Council will work with the Planning Policy Team to develop a generic guidance note or specification for delivering community facilities, so they are available in a timely manner and meet community needs. Report P7

Why

New settlements and large urban extensions are expected to deliver a significant share of Stratford-on-Avon's future housing and need coordinated infrastructure, early service delivery and integrated community development to become self-sustaining. Report P8, P10

Past delivery has been criticised for delayed community facilities, weak early governance, car dependency and isolation, particularly where affordable housing was delivered before supporting services. Report P8

The Hyas review set out strategic recommendations covering policy, leadership, developer collaboration, governance, early infrastructure, affordable housing, stewardship, communications and S106, and many align with work already underway in the South Warwickshire Local Plan preparation. Report P8, P9

What happens next

Policy Manager will report to the October 2026 Cabinet on leadership, developer collaboration, project boards, early infrastructure delivery, affordable housing delivery and parish council support for new settlements. Report P9

Officers will work with the Planning Policy Team to develop a generic guidance note or specification for community facilities delivery and consider stewardship and governance options, including the Long Marston Airfield site as a pilot. Report P7, P10

A growth bid for the 2027/28 budget will be drawn up to continue Community Builder community development work in Stratford-upon-Avon, Bidford-on-Avon, Shackleton and Meon Vale. Report P7

The money

  • 2027/28 budget setting process Growth bid to be prepared to secure Community Builder work in the medium term Report P7

Options considered

  • Chosen: Endorse the recommendations as set out Report P10
  • Rejected: Amend the recommendations and then endorse them Report P10
  • Rejected: Do not endorse the recommendations Report P10

Implications

  • Financial: No immediate financial implications, but a more developed approach may bring additional pressures and new roles, with a 2027/28 growth bid planned for Community Builder work. Report P10
  • Legal: Policy and S106 recommendations will be progressed through the South Warwickshire Local Plan, with subsidy control compliance and procurement rules to be observed where financial assistance or services are provided. Report P10
  • Equalities: An initial screening found no negative implications and likely positive community-wide implications for people with protected characteristics. Report P10, P33
  • Climate: Well-executed delivery of new settlements and large urban extensions is expected to optimise environmental and climate change performance over time. Report 5.4
  • Staffing: No immediate human resources or staffing implications, though further work may necessitate new roles. Report P10
  • Risk: Reliance on new settlements and large urban extensions to deliver South Warwickshire Local Plan growth makes improvements to community stewardship and the transition from settlement to community a priority. Report P10

Who and where

  • Residents and future residents of new settlements and large urban extensions in Stratford-on-Avon District Report P8, P10
  • Community Builders and community development activity in Stratford-upon-Avon, Bidford-on-Avon, Shackleton and Meon Vale Report P7, P9
  • Developers and delivery partners involved in new settlement sites, including Long Marston Airfield Report P8, P10
  • Council planning, housing, public health, transport, police and education stakeholders engaged in strategic growth Report P8

Timeline

  • October 2026: Policy Manager to report to Cabinet on leadership, developer collaboration, project boards, early infrastructure, affordable housing and parish council engagement Report P9
  • 2027/28 budget setting process: Growth bid to be prepared to secure Community Builder work in the medium term Report P7
  • 5 October 2026: Cabinet considered the Hyas Associates report and agreed the recommendations Report P1, P7

Plain English for the jargon

  • South Warwickshire Local Plan (SWLP): The emerging local plan covering Stratford-on-Avon and neighbouring areas, which will set policy for new settlements and large urban extensions.
  • Community Builder: A tendered community development role supporting new communities, currently in Stratford-upon-Avon, Bidford-on-Avon, Shackleton and Meon Vale.
  • S106: Section 106 agreement, a legal planning obligation under which a developer provides funding or facilities to mitigate the impact of a development.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item257

Resolved

(1) That the contents of the agenda report and the Community Infrastructure Strategy, as detailed in Appendix 1 to the agenda report, be noted; (2) That the findings of the agenda report be considered in the development and delivery of the South Warwickshire Local Plan; (3) That given the important role of the tendered community development activity undertaken by the Community Builders in Stratford-upon-Avon and Bidford-on-Avon, Shackleton and Meon Vale, a growth bid be prepared for the 2027/28 budget setting process to secure delivery of this work in the medium term; and (4) That works with the Planning Policy Team to develop a generic guidance note/specification for the delivery of community facilities, to ensure that community facilities were available in a timely manner and met the needs of the community. Note: In accordance with the Council’s Constitution, this item is not subject to call-in to the OSC
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

The Cabinet 5 October 2026

Title: New Settlement and Large Urban Extension - Community Infrastructure

Lead Officer: Nick Cadd, Communities and Social Inclusion Manager

(01789 260841)

Portfolio Holder/ Lead Member: Councillor L Coles

Summary This report summarises the findings of a piece of work Stratford-on-Avon District Council (SDC), commissioned the consultancy Hyas Associates to undertake. The report took the delivery challenges that new settlements and larger urban extensions present and examined local efforts and national best practice to develop a strategy to enhance the collective approach. The resultant report accompanies this document, and it provides a strategic framework to guide the planning, phasing, and delivery of community infrastructure in new settlements and large-scale urban extensions. The work is designed to ensure emerging communities are cohesive, resilient, and well-supported by services, facilities, and social capital from the outset.

Recommendations (1) That the contents of the report and the Community Infrastructure Strategy, as detailed in Appendix 1, be noted; (2) That the findings of the report be considered in the development and delivery of the South Warwickshire Local Plan; (3) That given the important role of the tendered community development activity undertaken by the Community Builders in Stratford-upon-Avon and Bidford-on-Avon, Shackleton and Meon Vale, a growth bid be prepared for the 2027/28 budget setting process to secure delivery of this work in the medium term; and (4) Work with the Planning Policy Team to develop a generic guidance note / specification for the delivery of community facilities to ensure that community facilities are available in a timely manner and meet the needs of the community.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 2.2 MB Download
PDF
New Settlement and Large Urban Extension: Community InfrastructureReport 614 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 20 attended
SJ
Councillor Susan JunedLeader, expected
GC
Councillor George CowcherDeputy Leader, expected
LA
Councillor Louis AdamPortfolio Holder, expected
LC
Councillor Liz ColesPortfolio Holder, expected
DC
Councillor David CurtisPortfolio Holder, expected
NG
Councillor Natalie GistPortfolio Holder, expected
LG
Councillor Lorraine GrocottPortfolio Holder, expected
TH
Councillor Trevor HarveyObservers, expected
MR
Councillor Mike RiceObservers, expected
DP
Councillor Dave PassinghamObservers, expected
DP
Councillor Daren PembertonObservers, apologies, sent representative
SW
Councillor Sarah Whalley-HogginsObservers, expected

All 20 on the meeting page

On this subject at Stratford-on-Avon

Search all
  1. New Settlement and Large Urban Extension - Community InfrastructureThis decision
  2. Application No. 22/01385/VARY - Land Adjacent To The Old Gated Road, Banbury Road, Upper Lighthorne New Settlement (formerly Gaydon/Lighthorne Heath)Deferred
  3. New Settlement Proposal Gaydon /Lighthorne Health - Draft Supplementary Planning DocumentDecided
  4. Creation of a New Settlement Delivery TeamDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies