South Warwickshire Local Plan Strategic Sites Governance and Delivery Framework - Long Marston Airfield New Community
ApprovedExecutive2 papers
AI summaryStratford-on-Avon District Council Cabinet approves a governance framework for delivering the Long Marston Airfield New Community, a 10,300-home site in the emerging South Warwickshire Local Plan.
Written from the decision and the officer reportPDF Pro
OutcomeApproved
MoneyNo direct costs from this reportOfficer resources funded from existing SWLP budget in the short-term
What happens nextNot stated
Who it affectsNot stated
What was decided
The Cabinet approved the Strategic Sites Governance and Delivery Framework for Long Marston Airfield New Community, noting it may evolve as the site progresses. Report P6, P7
The Cabinet noted that similar governance structures will be needed for the other 17 South Warwickshire Local Plan residential-led strategic sites, working with Warwick District Council once long-term officer resources are identified. Report P6, P7
Specific membership and Terms of Reference for the Strategic Board will be approved later through a Leader's Decision Notice, and the decision is not subject to call-in to the Overview and Scrutiny Committee.
Why
Delivering the South Warwickshire Local Plan is a corporate priority, and the scale of infrastructure required, including the Stratford-upon-Avon southern western bypass, means governance must be set up early. Report 1.5, P7
Most strategic sites are in multiple land ownerships, requiring strong local leadership, consistent masterplanning, and timely coordination with infrastructure providers and statutory bodies. Report P7
What happens next
A Leader's Decision Notice will set the Strategic Board's membership and Terms of Reference, and a further Cabinet report is anticipated in the coming months on governance for the other 17 strategic growth locations. Report P7
An interim Site Delivery Officer will be recruited using funds available within the South Warwickshire Local Plan budget. Report P7
Options considered
Chosen: Endorse the recommendations. Portfolio Holder for Planning and Economic Development supported the recommendation and a governance structure is needed now given the complexity and scale of the site Report P7
Rejected: Amend the recommendations and then endorse Report P7
Rejected: Not endorse the recommendations. Failure to set up governance would create significant risk to delivering a corporate priority Report P7
Implications
Legal: Compulsory acquisition of land may be needed, notably for the Stratford-upon-Avon Western Relief Road, and a separate body may be required to deliver the bypass. Report P7
Financial: Future delivery will depend on securing S106, CIL, grant and forward funding; financial and legal input should be contained within existing budgets. Report P7
Equalities: An equalities screening exercise found no implications arising from the proposal. Report P7
Climate: An effective governance and delivery framework will enable environmental and climate change challenges and opportunities to be addressed at the site. Report P7
Staffing: Setting up governance will have resource and skills development implications; an interim Site Delivery Officer will be recruited from the SWLP budget. Report P7
Risk: Without appropriate governance, the Council risks its ability to deliver the SWLP as a corporate priority. Report P7
Who and where
Future residents of the Long Marston Airfield New Community (planned 10,300 homes, 4,500 by 2050) Report P7
Landowners across the multi-ownership strategic site Report P7
Warwick District Council as joint authority on the South Warwickshire Local Plan Report P7
Existing and new communities, infrastructure providers and statutory bodies Report P7
Timeline
15 July: South Warwickshire Local Plan Publication (Regulation 19) version approved for consultation Report P7
8 September: End of the 7-week consultation period on the Publication version Report P7
5 October 2026: Cabinet approved the governance framework Report P1
by 2050: Target of 4,500 of the planned 10,300 homes to be delivered at the site Report P7
December 2026: Plan scheduled for submission Report P7
2027: Examination of the South Warwickshire Local Plan Report P7
early 2028: Adoption of the South Warwickshire Local Plan due Report P7
Plain English for the jargon
SWLP: South Warwickshire Local Plan, the emerging plan covering Stratford-on-Avon and Warwick districts
Strategic Growth Location: A large residential-led development site within the SWLP, including two proposed new settlements
S106: Section 106 agreement, a planning obligation used to secure developer contributions
CIL: Community Infrastructure Levy, a charge on new development to fund infrastructure
PPA: Planning Performance Agreement, a project management tool for major planning applications
Western Relief Road: Proposed highway improvement south-west of Stratford-upon-Avon, key infrastructure for the Long Marston site
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item258
Resolved
(1) That the approach defined by the South Warwickshire Local Plan Strategic Sites Governance and Delivery Framework, as detailed in Appendix 1 of the agenda report, for the Long Marston Airfield New Community within the emerging SWLP, with the recognition that this might evolve as the site progressed through different stages of development and delivery, be approved; (2) That the need to set up similar governance structures for all of the remaining South Warwickshire Local Plan residential-led strategic sites in due course and in conjunction with Warwick District Council be noted, once long-term officer structures and resources have been identified; and (3) That the specific membership and Terms of Reference of the Strategic Board for the Long Marston Airfield New Community be approved through a Leader’s Decision Notice in due course. Note: In accordance with the Council’s Constitution, this item is not subject to call-in to the OSC
Word for word from the decision Stratford-on-Avon published for this meeting.Source: democracy.stratford.gov.uk
Title: South Warwickshire Local Plan Strategic Sites Governance and Delivery Framework – Long Marston Airfield New Community
Lead Officer: Jo Bozdoganli, Policy Manager
(01789 260473)
Portfolio Holder/ Lead Member: Councillor G Cowcher
Summary This report seeks approval for the creation of a governance structure to oversee the delivery of the Long Marston Airfield New Community site within the emerging South Warwickshire Local Plan (SWLP), recognising it as a corporate priority for the Council. In due course, a similar structure will be put forward for approval for all of the other emerging SWLP residential-led strategic sites once appropriate officer resources have been identified. Recommendations (1) That the approach defined by the South Warwickshire Local Plan Strategic Sites Governance and Delivery Framework, as detailed in Appendix 1, for the Long Marston Airfield New Community within the emerging SWLP, recognising that this may evolve as the site progresses through different stages of development and delivery be approved; and (2) That the need to set up similar governance structures for all of the remaining South Warwickshire Local Plan residential-led strategic sites in due course and in conjunction with Warwick District Council be noted, once long-term officer structures and resources have been identified.
1 Background/Information 1.1 The SWLP Publication (Regulation 19) version was approved for consultation on 15 July and is subject to a 7-week consultation period ending 8 September, followed by submission by December 2026, examination in 2027 with adoption due in early 2028. 1.2 Successful adoption and subsequent implementation of the SWLP is a corporate priority, and to enable timely delivery of the strategic growth locations identified within the SWLP early consideration of how this should best be coordinated is essential. Working alongside the private sector and infrastructure providers, effective implementation will be a time and resource-intensive process which requires commitments to strong local leadership, a clear vision and consistent political will to achieve. 1.3 Challenges include the funding and timing of infrastructure delivery, land ownership and assembly, engagement with existing and new communities, cross-border influences, climate change adaptation, place-making and community cohesion, managing skills and resources, development management processes and S106/CIL, monitoring, ongoing political commitment, sustainable long-term stewardship. 1.4 The Publication version of the SWLP includes eighteen residential-led Strategic Growth Locations (including two new settlements) one of which is the Long Marston Airfield New Community which has key requirements as set out in Table 1. Table 1: Key requirements for the Long Marston Airfield New Community within the emerging SWLP Site Location Homes Employment Key Ref. Infrastructure LMA Long Total 15ha Education, retail, Marston 10,300 community, health, Airfield New (with open space, active Community 4,500 by travel, highway 2050) improvements, western bypass, 21 G&T solar farm pitches Affordable Housing
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.