Stratford Gateway Demolition

Agreed Executive 2 papers

AI summaryStratford-on-Avon Cabinet approves demolition of Windsor Street car park and three other buildings at Stratford Gateway, releasing a £1.5 million earmarked reserve for the enabling works.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedFour buildings at Stratford Gateway site
Money£1.5 million earmarked reservePreviously approved, now released for demolition
What happens nextProcurement and planning during 2026Contractor mobilisation expected end 2026 into 2027
Who it affectsNot stated

What was decided

Cabinet agreed to demolish Windsor Street Multi-Storey Car Park, Apex House, Elizabeth Place and Conrad House, subject to legal, technical and statutory requirements. Report P5

The previously approved £1.5 million earmarked reserve is to be applied to the demolition project. Report P5, P6

The Deputy Chief Executive was authorised to procure contractors, enter agreements with the West Midlands Combined Authority and set up a temporary surface car park of around 90 spaces after demolition. Report P5, P6

Why

The four buildings are vacant, underutilised or approaching the end of their useful life, and they continue to generate maintenance, security and business rate liabilities for the Council. Report P6

The demolition is an enabling phase for the wider Stratford Gateway regeneration, which is guided by the Supplementary Planning Document adopted in 2023 by the Council and the West Midlands Combined Authority. Report P6

Officers found that refurbishing the multi-storey car park would not be economical and would conflict with the Council's wider regeneration priorities for the site. Report P6

What happens next

Officers will complete remaining surveys, ecology work, utility investigations, Party Wall processes and the planning application during 2026. Report P6

Procurement of a demolition contractor is expected to conclude in 2026, with appointment and mobilisation towards the end of 2026 and into early 2027. Report P6

After demolition, a temporary surface car park with around 90 spaces will be set up on the Windsor Street site, with the Arden Street sites cleared and secured. Report P6

The money

  • £1.5 million Previously approved earmarked reserve to be applied to the demolition project Report P5, P6
  • circa £225,000 per annum Current business rates liability for the site Report P6
  • £712,404 Expected remaining balance in the Gateway holding cost reserve by the end of 2026/27 Report P6
  • approximately £4,470 per annum Income from access licences that may be suspended during the works Report P6
  • 243 parking spaces Existing capacity of Windsor Street Multi-Storey Car Park Report P6
  • in the order of 90 parking spaces Indicative capacity of the proposed temporary surface car park Report P6

Options considered

  • Chosen: Approve the recommendations as set out in the report. Maintains momentum on a strategically important regeneration project and supports delivery of the wider Stratford Gateway vision. Report P6
  • Rejected: Approve the recommendations with amendment Report P6
  • Rejected: Determine not to proceed with the demolition project at this time Report P6

Implications

  • Legal: Planning permission will be required before demolition, along with compliance with statutory requirements covering demolition, utilities, Party Wall matters, environmental protection and construction. A legal agreement with the West Midlands Combined Authority is also required. Report P6
  • Financial: The £1.5 million earmarked reserve will fund the works. Final costs will be set through remaining technical work and procurement. The temporary car park will be smaller than the existing facility, so a revised business rates assessment is likely and specialist rating advice is being obtained. Report P6
  • Equalities: An Equality Impact Screening Assessment found the proposal has low or no direct relevance to protected characteristics under the Equality Act 2010. Future redevelopment will be assessed separately. Report P6
  • Climate: The demolition strategy will seek to maximise reuse and recycling of materials, including crushing reinforced concrete from the car park for reuse in site build-up and hardstanding, and recovery of steel and metals. Report P6
  • Risk: The project remains subject to legal, technical, ecological and statutory risks which are being managed through the project governance process. A Risk Register is being maintained. Report P6

Who and where

  • Users of Windsor Street Multi-Storey Car Park, who will lose spaces but may use the temporary surface car park, other Council car parks or the Park and Ride Report P6
  • Holders of access licences to the car park, whose arrangements may be suspended Report P6
  • Visitors to Stratford-upon-Avon town centre and the Canal Quarter Report P6
  • West Midlands Combined Authority, as joint landowner and partner in the Stratford Gateway programme Report P6
  • Future developers and residents of the redeveloped Stratford Gateway site Report P6

Timeline

  • 2023: Stratford Gateway Masterplan adopted as a Supplementary Planning Document Report P6
  • during 2026: Remaining technical and statutory workstreams to be completed, including surveys, ecology and the planning application Report P6
  • 5 October 2026: Cabinet decision to approve demolition and release the £1.5 million reserve Report P5
  • end of 2026 into early 2027: Demolition contractor to be appointed and mobilised, based on current assumptions Report P6
  • by the end of 2026/27: Gateway holding cost reserve expected to have a remaining balance of £712,404 Report P6

Plain English for the jargon

  • Supplementary Planning Document (SPD): A planning document that adds further detail to policies in the local plan, in this case the Stratford Gateway Masterplan adopted in 2023.
  • WMCA: West Midlands Combined Authority, the joint landowner and partner on the Stratford Gateway site.
  • OSC: Overview and Scrutiny Committee, to which this Cabinet decision is subject to call-in.
  • Earmarked reserve: Money set aside by the Council for a specific purpose, in this case £1.5 million for the demolition project.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item263

Resolved

(1) That the demolition of Windsor Street Multi-Storey Car Park, Apex House, Elizabeth Place and Conrad House be agreed, subject to completion of all necessary legal, technical and statutory requirements; (2) That the previously approved earmarked reserve of £1.5 million be applied to the delivery of the demolition project; (3) That the Deputy Chief Executive be authorised to procure and appoint the contractors, consultants and specialist advisers required to deliver the project, in accordance with the Council's Contract Standing Orders and within the approved budget; (4) That the Deputy Chief Executive be authorised to undertake all necessary surveys, investigations, statutory processes, utility disconnections and approvals, and to take such operational decisions as were necessary to deliver the project within the approved budget; (5) That the Deputy Chief Executive be authorised to vary and terminate existing arrangements at Windsor Street Multi-Storey Car Park and to enter into temporary or permanent alternative arrangements as are necessary to deliver the project; (6) That the Deputy Chief Executive be authorised to enter into such agreements, arrangements and ancillary documents with the West Midlands Combined Authority and other nearby landowners as were necessary to deliver the demolition project; and (7) That the Deputy Chief Executive be authorised to implement temporary arrangements for the Windsor Street site following demolition, including the provision of a temporary surface car park, pending future redevelopment proposals. Note: This item is subject to call-in to the OSC.
Word for word from the decision Stratford-on-Avon published for this meeting. Source: democracy.stratford.gov.uk

Follow this further

Built from Stratford-on-Avon's papers

What the report saysPro

Report to The Cabinet

The Cabinet 5 October 2026

Title: Stratford Gateway Demolition

Lead Officer: Tony Perks, Deputy Chief Executive (01789 260620)

Portfolio Holder/ Lead Member: Councillor L Adam

Summary The Stratford Gateway site represents a significant regeneration opportunity. The site is owned by Stratford-on-Avon District Council and the West Midlands Combined Authority, which are working in partnership to deliver the vision set out in the adopted Stratford Gateway Masterplan. This report seeks approval to proceed with the demolition of a number of existing buildings, including the Council owned Windsor Street Multi-Storey Car Park, as an enabling phase of the project. The proposed works will remove vacant and underutilised buildings, reduce ongoing liabilities, improve public safety and prepare development-ready sites to support future redevelopment. Recommendations (1) That the demolition of Windsor Street Multi-Storey Car Park, Apex House, Elizabeth Place and Conrad House be agreed, subject to completion of all necessary legal, technical and statutory requirements; (2) That the previously approved earmarked reserve of £1.5 million be applied to the delivery of the demolition project; (3) That the Deputy Chief Executive be authorised to procure and appoint the contractors, consultants and specialist advisers required to deliver the project, in accordance with the Council's Contract Standing Orders and within the approved budget; (4) That the Deputy Chief Executive be authorised to undertake all necessary surveys, investigations, statutory processes, utility disconnections and approvals, and to take such operational decisions as are necessary to deliver the project within the approved budget; (5) That the Deputy Chief Executive be authorised to vary and terminate existing arrangements at Windsor Street Car Park and to enter into temporary or permanent alternative arrangements as are necessary to deliver the project; (6) That the Deputy Chief Executive be authorised to enter into such agreements, arrangements and ancillary documents with the West Midlands Combined Authority and other nearby landowners as are necessary to deliver the demolition project; and (7) That the Deputy Chief Executive be authorised to implement temporary arrangements for the Windsor Street site following demolition, including the provision of a temporary surface car park pending future redevelopment proposals.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 623 KB Download
PDF
Stratford Gateway DemolitionReport 436 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

1 of 20 attended
SJ
Councillor Susan JunedLeader, expected
GC
Councillor George CowcherDeputy Leader, expected
LA
Councillor Louis AdamPortfolio Holder, expected
LC
Councillor Liz ColesPortfolio Holder, expected
DC
Councillor David CurtisPortfolio Holder, expected
NG
Councillor Natalie GistPortfolio Holder, expected
LG
Councillor Lorraine GrocottPortfolio Holder, expected
TH
Councillor Trevor HarveyObservers, expected
MR
Councillor Mike RiceObservers, expected
DP
Councillor Dave PassinghamObservers, expected
DP
Councillor Daren PembertonObservers, apologies, sent representative
SW
Councillor Sarah Whalley-HogginsObservers, expected

All 20 on the meeting page

On this subject at Stratford-on-Avon

Search all
  1. Stratford Gateway DemolitionThis decision
  2. Minute 632 - Stratford-upon-Avon Gateway Site Framework Masterplan Supplementary Planning DocumentApproved
  3. Stratford-upon-Avon Gateway - Collaboration AgreementAgreed
  4. Stratford-upon-Avon Gateway Draft Masterplan Supplementary Planning DocumentAgreed
  5. Stratford-upon-Avon Gateway Development BriefAgreed
  6. Urgent Business - Urgent Update on the Purchase of the Gateway Site, Stratford-upon-AvonDecided

More from Stratford-on-Avon The Cabinet

All decisions
MeetingDecisionOutcome
2 Nov 2026 Future of Southam United Football Club(1) That subject to the conditions identified in paragraph 1.4.3 of the agenda report, and subject to the above amend... Decided Open
2 Nov 2026 Strategic Risk RegisterThat the , attached as Appendix 1 to the agenda report, be endorsed. Note: In accordance with the Council’s Constitut... Decided Open
2 Nov 2026 Options for Boosting the Supply of Housing Land Update Report(1) That the progress in delivering the Housing Land Supply Action Plan, the September 2026 housing land supply calcu... Noted Open
2 Nov 2026 Youth Catalyst Project – Service Specification and Permission to Tender(1) That permission to procure a Youth Catalyst Project provision to meet the requirements of the specification, as d... Approved Open
2 Nov 2026 Revenue Budget Monitoring Period 1 - 6 2026/27(1) That the actual net variance as at Period 6, and the estimated revenue outturn for 2026/27, be received; and (2) ... Noted Open