That the projected revenue budget and the Capital programme direction be noted (as set out in Annex 1, Sections A and B of the report submitted). 2. That the work to agree business rates pooling with Surrey districts and boroughs (as set out in Annex 1, Section A of the report submitted) be noted and endorsed. 3. That it be agreed that the government grant changes be reflected in directorate budgets (as set out in Annex 1, Section C of the report submitted). 4. That the further quarter 2 financial information on treasury, debts reserves and balances and the Chief Financial Officer’s delegated authority to write off £305,203 of debts this quarter (as set out in Annex 1, Section D of the report submitted) be noted. Reason for Decisions To comply with the agreed strategy of considering budget monitoring and any necessary actions on a monthly basis. [The decisions on this item can be called in by the Council Overview and Scrutiny Committee]
Word for word from the decision Surrey published for this meeting.Source: mycouncil.surreycc.gov.uk
1. notes the projected revenue budget; (Annex 1 – Section A) and the Capital programme direction; (Section B)
2. notes and endorses work to agree business rates pooling with Surrey districts and boroughs; (Annex 1 Section A, para 68-75)
3. confirms that government grant changes are reflected in directorate budgets; (Section C)
4. notes further quarter 2 financial information -treasury, debts reserves and balances. (Annex 1 – Section D) and the Chief Financial Officer’s delegated authority to write off £305,203 of debts this quarter (Annex 1 – Section D para 107)
Reason for recommendations
To comply with the agreed strategy of providing a monthly budget monitoring report to Cabinet for approval and action as necessary.
DETAILS:
1. The council’s 2012/13 financial year commenced on 1 April 2012 and this is the fourth financial report of this financial year.
2. The council has implemented a risk based approach to budget monitoring across all directorates and services. The risk based approach is to ensure that resources are focused on monitoring those budgets assessed high risk, due to their value or volatility. There is a set of criteria to evaluate all budgets into high, medium and low risk. 3. High risk areas report monthly, where as low risk services areas report on an exception basis. This is if the year to date budget and actual spend vary by more than 10%, or £50,000, whichever is lower.
4. Annex – Section A to this report sets out the council’s revenue budget forecast year end outturn as at the end of September 2012. The forecast is based upon current year to date income and expenditure as well as projections using information available to the end of the month. The report provides explanations for significant variations from the budget.
5. Annex – Section B to this report updates Cabinet on the council’s capital budget.
6. Annex – Section C provides details of the revenue changes to government grants and other budget virements.
7. Finally the Annex – Section D provides information about the treasury information and further financial information on the current position on the Balance Sheet and outstanding debts relating the second quarter end.
Consultation
8. All Cabinet Members will have consulted their relevant Strategic Director on the financial positions of their portfolios.
Risk management and implications:
9. Risk implications are stated throughout the report and each Strategic Director has updated their strategic and or service risk registers accordingly. In addition, the Leadership risk register continues to reflect the increasing uncertainty of future funding likely to be allocated to the council.
Financial and value for money implications
10. The financial and value for money implications are considered throughout this report and will be further scrutinised in future budget monitoring reports. The council continues to have a strong focus on its key objective of providing excellent value for money.
Section 151 Officer commentary
11. The Section 151 officer confirms that all material, financial and business issues and risks are considered throughout the report.
Legal implications – Monitoring Officer
12. There are no legal issues and risks.
Equalities and Diversity
13. Any impacts of the budget monitoring actions will be evaluated by the individual services as they implement the management actions necessary.
2 Climate change/carbon emissions implications
14. The County Council attaches great importance to being environmentally aware and wishes to show leadership in cutting carbon emissions and tackling climate change.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.