That the achievements delivered through the Public Value Review Programme be acknowledged. 2. That officers, Members and other stakeholders who contributed to the PVR Programme be thanked. 3. That the PVR Programme be formally closed and Cabinet Members and Strategic Directors be asked to ensure agreed PVR improvements and savings are delivered and monitored through the Council’s financial, performance and risk management arrangements. 4. That Select Committees continue to play a vital role via monitoring and scrutiny to ensure delivery of PVR improvements and savings. 5. That the PVR Programme Closing Report be published on the Council’s website and circulated widely within and outside of the Council. Reasons for
Word for word from the decision Surrey published for this meeting.Source: mycouncil.surreycc.gov.uk
1. Acknowledges the achievements ach delivered through the Publicc Value Review Programme. 2. Thanks officers,, Members and other stakeholders who contributed to the PVR Programme. 3. Agrees to formally close the PVR Programme and asks Cabinet Members and Strategic Directors ectors to ensure agreed PVR improvements and savings are delivered and monitored through the Council’s financial, performance and risk management arrangements.
4. Requests that Select Committees continue to play a vital role via monitoring and scrutinyy to ensure delivery of PVR improvements and savings.
5. Agrees that the PVR Programme Closing Report be published on the Council’s website and circulated widely within and outside of the Council. Council
Reason for recommendations
The PVR Programme Closing Report provides a summary of the benefits the Programme has delivereded (and will continue to deliver) for Surrey rey residents and also describes key lessons learnt over the past three th years.
Page 183 DETAILS:
Background 1. In July 2009 Surrey County Council announced the PVR Programme to take a systematic and focused look at all its services and functions over a three- year period. The emphasis was put on ‘public value’ to ensure the things most important to Surrey residents were at the heart of the work.
2. A flexible but clear methodology was used for each review to ensure there was rigour to the approach. A PVR Steering Board chaired by the Leader of the Council oversaw the Programme, providing leadership and challenge. Individual reviews were sponsored by Strategic Directors and Cabinet Members, led by small teams of Council officers, and supported and challenged by representatives of Select Committees through Member Reference Groups. “Experts” from outside the Council were used to provide independent challenge to the emerging findings of each review.
Achievements and lessons learnt 3. The 29 PVRs completed have delivered a wide range of service improvements. They have been a vehicle for identifying and implementing new and innovative ways of delivering services, in particular through stronger partnership working and involving residents in the design and delivery of services. For example, community groups are running youth centres, and residents have volunteered to run some local libraries. At the same time, the Programme has made a vital contribution to reducing costs, identifying total savings of £279m which will be delivered by 2016.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.