Resolved
To note the report.
Pension Board noted this item on Thursday 19 August 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
To note the report.
1.1The Board are invited to review the progress made on recent procurements which have taken place since the Board meeting in March 2021.
2. Recommendation(s)
2.1To note the report
3. Background and Key Information
3.1The Pension Fund uses external providers to support its decision making and to conduct work on its behalf. This includes a range of specialist advisers which the Fund procures on a regular basis. The procurement activity outlined in this report concerns contracts that are less than £1m in value over the contract duration.
3.2The National LGPS Frameworks Group has set up a number of National Frameworks for key services to facilitate ease of access for LGPS Funds, with the Frameworks using OJEU compliant procurement and extensive due diligence to appoint providers to a range of frameworks. LGPS Funds are then able to call off the available frameworks for services without having to undertake full procurements, either being able to run mini-competitions for services or direct awards of providers as appropriate. The Fund has used the National Frameworks to undertake the following procurements.
Report Page 1 Agenda Item 8 Page 34 Procurement Update
Governance Review
3.4The Fund has appointed AON to provide a governance review to cover both the LB Sutton and RB Kingston governance arrangements. This was made via a direct award from the National LGPS framework. Work is now underway to conduct the review with a report to be provided to the Pensions Committee and Pensions Board in December on the outcome of the review.
Appointment of Investment Consultant
3.1The Fund worked closely with the RB Kingston to run a mini-competition to search for an investment consultant to cover both Funds. The Fund’s adviser has for a number of years been Hymans and similarly for RB Kingston they have had AON as their investment consultant for a number of years.
3.2The Fund using the National LGPS Framework for investment consultancy services issued a Request for Proposals to advisers on the framework and received 3 tender submissions which were evaluated according to a number of set questions and an interview process. The basis for evaluating the tenders and interviews is set out below:
Stage Criteria Weighting 1 Price: Value for Money 30% Quality (Written Submission) 40% 2 Service Fit (Written, Presentation and Interview) 30% Total 100%
Following the evaluation process the both Sutton and Kingston Pension Funds have appointed Mercer as investment adviser as the overall top scoring tender against the criteria set out above.
3.3The appointment of the investment adviser is for a period of 4 years with the potential to extend for a further two years subject to satisfactory performance and Fund requirements.
Appointment of Actuarial and Benefit Advisers
3.4At the time of writing this report, the procurement process is ongoing, but it is anticipated that by the time of the Pensions Committee meeting, officers will be able to advise on the appointment of the advisers.
3.5As with the investment consultant advisers, the Fund worked closely with the RB Kingston running two mini-competitions to search for actuarial and benefits advisers to cover both Funds. Prior to the procurement, Sutton Pension Fund used Barnett Waddingham as
Report Page 2 Page 35 Agenda Item 8 Procurement Update
Actuarial advisers whilst Kingston used Hymans. Neither Fund had previously had an appointed Benefits Consultant.
3.6Each bid was assessed against the Evaluation Criteria set out below:
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
(8) Procurement UpdateReport | 208 KB | DownloadRead as text |
Follow Pension Board at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Jul 2026 | Minutes of the previous meetingRESOLVED : that the minutes of the meeting held on 19 March 2026 be agreed as an accurate record. | Agreed | Open |
| 16 Jul 2026 | Pension Administration Performance UpdateRESOLVED : To note the update. | Noted | Open |
| 16 Jul 2026 | Pension Administration Projects UpdateRESOLVED : To note the update. | Noted | Open |
| 16 Jul 2026 | Governance and Risk UpdateRESOLVED : To note the update. | Noted | Open |
| 16 Jul 2026 | Work Programme UpdateRESOLVED : To note the updated Work Programme for the Board. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.