Resolved
That the delivery plan for the CAIP 24/25 programme be agreed .
Strategy and Resources Committee agreed this item on Monday 15 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
That the delivery plan for the CAIP 24/25 programme be agreed .
1.1The Corporate Assets Investment Programme (CAIP) is a capital budget allocated on an annual basis, for use when elements of our estates building fabric are beyond planned preventative maintenance, or at the end of the materials / plants life expectancy. This is important to ensure the assets are fit for purpose to support the delivery of our Ambitious for Sutton plans.
1.2This report sets out the 2024/25 CAIP Capital Programme as set out in Appendix A. It also provides an overview on the performance and management of the CAIP programme. The capital programme includes an allocation of £1.42m during 2024/25, (as well as the remainder of any budgets carried over the 2023/24 CAIP programme for projects nearing completion in early April/May 2024).
1.3The CAIP programme is compiled of information gathered from building condition surveys, general maintenance feedback and any onsite knowledge gathered by the Asset Management, Capital Projects and Facilities Management teams as part of the corporate landlord model. This assessment allows the Council to keep all operational assets in a safe and reasonable condition, for the benefit of customers and staff. The works are
Report page 1 Agenda Item 13 Page 116 CAIP (Health and Safety Works) Report June 2024
prioritised on the business and health and safety through an evaluation process.
2.1To agree the delivery plan for the CAIP 24/25 programme.
3 Background and Key Information
3.1The Corporate Assets Investment Programme - (CAIP) ensures the Council's building stock is statutory compliant and is delivered annually to ensure that all operational assets and facilities are maintained, kept safe and fit for purpose. Additional work includes backlog maintenance and resolving areas of health and safety concern, which are derived through surveys and day to day intelligence.
3.2Key projects listed in the 2024/25 schedule are;
● Hill House (Wind & watertight works) - £120,000 Phase 3 of 3 planned works and funded via CAIP. The planned repairs to the external envelope are much needed and will protect the building for years to come. The works entail a new central rooflight, replacement windows and re-rendering the external facade.
● Times Square Car Park Health and Safety works - £260,000 - a variety of safety related improvements to the car park stairwells and underpinning to the main structure to enhance safety for users, and maintain the overall condition of the car park to avoid further deterioration.
● Improvements to assets in Public Health and Wellbeing - £550,000. Detailed condition surveys in all four Leisure Centres were undertaken during 2023 and these identified requirements for decoration, repair and replacement of ageing M&E equipment.
3.3The building's condition and data is noted and compiled in the CAIP schedule to inform a capital programme which is then followed as part of the effective assessment and then each project has strict monitoring, governance and reporting along with value for money for the Council. The existing governance procedures in place include monthly meetings to review progress against spending on a monthly basis, and any issues are escalated to the Strategic Director of Resources.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Corporate Assets Investment Programme (CAIP) (Health and Safety Works): ReportReport | 237 KB | DownloadRead as text |
Follow Strategy and Resources Committee at Sutton and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 22 Jun 2026 | MinutesRESOLVED : that the minutes of the meeting held on 16 February 2026 be agreed as an accurate record. | Agreed | Open |
| 22 Jun 2026 | Strategy and Resources Committee: Policy and Strategy OverviewThat the role and remit of the Strategy and Resources Committee as set out in the report be noted. | Noted | Open |
| 22 Jun 2026 | Financial Performance and Outturn 2025/26That the general fund revenue outturn service overspend of £0.46m,which is offset by £2.00m use of contingency and a ... | Noted | Open |
| 22 Jun 2026 | Selection of tenant - Throwley YardThat the grant of a lease for up to 15 years to Bidder A, as identified in the accompanying Appendix A be approved. | Approved | Open |
| 22 Jun 2026 | Electric Vehicle Charging Point (EVCP) ProcurementThat the award of the contract for an electric vehicle charging supplier following the procurement process, be delega... | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.