Proposed Management Budget 2026/27

Approved Committee 3 papers

AI summarySLWP Joint Committee approves £707k 2026/27 management budget, equivalent to £177k per partner borough, up just under £16k each on the prior year.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSLWP management budget of £707k agreed
Money£707k total, £177k per boroughUp just under £16k per borough on 2025/26
What happens nextApplies in 2026/27New financial year from April 2026
Who it affectsFour SLWP partner boroughsSutton, plus three other London boroughs

What was decided

The Joint Committee approved the 2026/27 SLWP management budget of £707k, equivalent to £177k per partner borough, an increase of just under £16k per borough on the previous year.

Why

The funding allows the partnership team to manage 19 waste treatment and disposal contracts with an annual value of just under £35m, and to deliver the five year work programme. Report 3.1, 4.1, 7.1

Legal support of £7,500 per borough has been reintroduced to handle expected change of law claims linked to upcoming legislation and any significant contract updates from cost saving work. Report 7.2

Staffing costs assume 3.5% inflation, in line with the expected LGA pay award, with no change to the seven post structure introduced in April 2025. Report 5.1, 7.3

What happens next

A more detailed joint commissioning strategy for Household Reuse and Recycling Centres and waste transfer stations will be presented to the November 2026 Joint Committee. Report 6.3, 7.5

Cost mitigation will include reduced contract document storage capacity and a review of payment mechanism indices to publicly available alternatives. Report 7.7

Additional funding for commissioning activities will be brought to the committee as standalone project proposals as the need arises. Report 7.8

The money

  • £707k Total SLWP management budget for 2026/27
  • £177k Annual cost per partner borough for 2026/27
  • just under £16k Increase per borough on the previous year
  • just under £35m Estimated annual value of 19 delegated waste contracts in 2026/27 Report 4.1
  • £7,500 Legal support provision per borough, reintroduced for 2026/27 Report 7.2
  • just over £8k Staffing cost increase per borough assuming 3.5% inflation Report 7.3
  • £366 Finance and data cost increase per borough per year Report 7.6
  • £116 Rise per borough per year in contract documentation storage Report 7.6
  • £63 Annual increase in the i-Auditor health and safety system Report 7.6
  • £187 Rise per borough per year in BCIS Online access licence Report 7.6
  • £5m Savings delivered for boroughs by SLWP led projects over the last 5 years Report 2.2

Options considered

  • Rejected: Retain the prior year budget uplifted by RPI plus 2% (the Inter Authority Agreement default if no new budget is agreed). The Joint Committee approved a new budget for 2026/27 instead, so the default uplift does not apply Report 3.2

Implications

  • Financial: Each partner borough will pay £177k towards SLWP running costs in 2026/27, around £16k more than in 2025/26. Report 7.9
  • Staffing: No changes to the seven post SLWP structure; pay award for staff is in line with the LGA agreement. Report 5.1, 5.2, 7.3
  • Legal: Legal support provision has been reintroduced to respond to change of law claims from contractors and to support contract updates from future cost saving work. Report 7.2
  • Risk: Cost cutting focus is moving to the £35m annual waste treatment and disposal budget, with an income and savings strategy being developed with partner boroughs. Report 6.1, 6.2
  • Other: The communications budget remains unchanged and will deliver year two of the five year plan, covering six objectives including carbon impact, HRRC satisfaction and website development. Report 7.4, 7.5, P24, P25, P26, P27, P28, P29

Who and where

  • The four SLWP partner boroughs (including the London Borough of Sutton), which each contribute to the management budget. Report 2.1
  • Waste treatment and disposal contractors holding the 19 SLWP managed contracts. Report 4.1
  • Residents using the Household Reuse and Recycling Centres, who will be the subject of a combined survey and consultation during the HRRC recommissioning project. Report 7.5

Timeline

  • 2025/26 financial year: SLWP management costs were reduced by 33% and staffing cut from nine to seven posts in April 2025. Report 5.1
  • April 2025: New seven post SLWP staffing structure came into effect. Report 5.1, 5.2
  • 2026/27 financial year: Approved £707k management budget applies, costing each borough £177k.
  • November 2026: More detailed HRRC and waste transfer station joint commissioning strategy to be presented to the Joint Committee. Report 6.3, 7.5

Plain English for the jargon

  • SLWP: South London Waste Partnership, a voluntary partnership of four London boroughs working together on waste treatment and disposal.
  • HRRC: Household Reuse and Recycling Centre, a site where residents can drop off bulky items and recyclables.
  • WTS: Waste Transfer Station, a site where waste is sorted or bulked before onward treatment or disposal.
  • IAA: Inter Authority Agreement, the legal agreement between the four partner boroughs that governs the partnership.
  • LGA: Local Government Association, the body that negotiates national local government pay awards.
  • BCIS: Building Cost Information Service, an online construction cost data subscription used by the partnership.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item9

Resolved

To approve the 2026/27 SLWP Budget of £707k. This represents an annual cost of £177k per borough and an increase of just under £16k per borough on the previous year.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to South London Waste Partnership Joint Committee

Appendices

1. SLWP Work Programme 2025 to 2030

2. Commissioning Programme (By Quarter) 2025 to 2030 Agenda Item 9 Page 54

Summary

Background

2.1The South London Waste Partnership (SLWP) is a voluntary partnership that allows the four partner Authorities to work at a sub-regional level on waste treatment and disposal services; to pool resources, share good practice, to procure, negotiate and manage services through a central team, and to undertake projects together that might otherwise be too expensive to deliver as individual boroughs.

2.2The SLWP boroughs have worked together as a voluntary partnership since 2007 and a great deal has been achieved in that time. In the last 5 years alone a number of SLWP led projects have delivered in excess of £5m in savings for boroughs. Whilst the clienting structure continues to evolve as the needs of the boroughs change, the original purpose of the SLWP and the value of working in partnership remains unchanged.

3. Setting the SLWP Budget

3.1Each year, the South London Waste Partnership (SLWP) is required to produce a budget for the consideration of the Joint Committee that covers the cost of delivering partnership wide activities and running the partnership team.

3.2The Inter Authority Agreement (IAA) between the Partner boroughs sets out that should a new budget not be agreed by the Joint Committee, the previous year’s budget, uplifted by RPI+2%, will be deemed to be agreed and will be the annual budget for the following year.

3.3The partnership team budget is set to enable shared contracts to be managed effectively and the administration of the partnership activities to be carried out. Spend is monitored monthly to allow budgets to be flexed where appropriate in order to respond to any budget pressures.

4. SLWP Delegated Services Page 55 Agenda Item 9

4.1The primary function of the SLWP is to ensure that the waste treatment and disposal services delegated to it are commissioned and then managed in the most efficient and effective way, in accordance with the governance requirements in each of the four boroughs, and in line with applicable legislation. In order to deliver the delegated services, the SLWP has commissioned and currently manages 19 contracts with an estimated annual value for the financial year 2026/27 of just under £35m.

5. Setting the Budget for 2026/27

5.1There has been an extended period of budget cuts and cost saving challenges across all departments in recent years. As part of this on-going budget challenge process, the SLWP management costs were reduced by 33% in 2025/26 and staffing numbers were reduced from nine posts down seven in April 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
4.0 SLWP Management Budget 2026 27: JWC V3Report 168 KB DownloadRead as text
PDF
4.1 Appendix 1 SLWP Work programme: 2025 to 2030Appendix 3.8 MB Download
PDF
4.2 Appendix 2 Commissioning Quarterly Work PlanAppendix 85 KB Download

At this meeting

Whole meeting

Who was there

7 of 8 attended
CW
Councillor Christopher WoolmerChair, present
SN
Councillor Stuart NeaversonVice-Chair, present
SA
Councillor Stephen AlambritisCommittee Member, apologies
IA
Councillor Isabel AraujoCommittee Member, present
NN
Councillor Nicola NardelliCommittee Member, present
TR
Councillor Tom ReeveCommittee Member, present
SR
Councillor Scott RocheCommittee Member, present
RW
Councillor Robert WardCommittee Member, present

On this subject at Sutton

Search all
  1. Proposed Management Budget 2026/27This decision
  2. Asset Management Report - Acquisition of Part of Mile Road for Proposed Pocket ParkAgreed
  3. All saints road, sutton - proposed traffic management measuresDecided
  4. Sutton Garden Suburb Conservation Area Draft Management Plan –Response to Community Engagement and approval of the proposed Revised Management PlanApproved

More from Sutton South London Waste Partnership Joint Committee

All decisions
MeetingDecisionOutcome
26 Nov 2025 Minutes of the previous meetingThat the minutes of the previous meeting held on 11 June 2025 were approved as a correct record. Approved Open
26 Nov 2025 Communications and Engagement UpdateTo Note the contents of this report and comment on any aspects of communications and engagement activities relating t... Noted Open
26 Nov 2025 Contracts Performance ReportNote the latest position with the ERF residual waste treatment contract related to the recent CEMS calibration issue ... Noted Open
26 Nov 2025 Budget Update 2025/26To note the content of this report. Noted Open
13 Jul 2022 Welcome and introductionsRESOLVED that: 1. Councillor Natasha Irons be appointed as Chair for the duration of the meeting. Decided Open