London Borough of Sutton
South London Waste Partnership Joint Committee, Wednesday 26 November 2025 at 6.30pm

Budget Update 2025/26

Noted Committee 2 papers

AI summarySouth London Waste Partnership Joint Committee notes a forecast £20,575 overspend at month 6 of 2025/26, driven by a higher pay award and unbudgeted legal costs for new recyclates contracts.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedDecision is to note the budget update
Money£20,575 forecast overspendEquates to £5,144 per borough
What happens nextNo new actions agreedCommittee simply noted the position
Who it affectsSouth London Waste Partnership boroughsEach borough shares the overspend equally

What was decided

The Joint Waste Committee noted the contents of the budget update report for 2025/26. Report P17

Members accepted the forecast position showing a £20,575 total overspend against the approved partnership budget at month 6. Report P3, P4

Why

The Core Partnership Team Activity is forecast to overspend by £11,082, mainly because the 2025/26 NJC pay award for local government services was settled at 3.2% in September 2025, above the 2.5% uplift originally built into the budget, adding £9,537 to the Core Staff Resources line. Report 3.3, 3.4, P10, P13

Document management system subscription costs are £1,544 over budget across health and safety monitoring, price adjustment indices and contract storage systems. Report 3.5, P13

An additional £9,493 of legal support costs were incurred outside the agreed budget to finalise the new jointly procured recyclates contracts and respond to last-minute queries from a contractor; this work is now complete. Report 3.8, P16

What happens next

The report contains no new recommendations beyond noting the position, so no further committee action is proposed at this stage. Report P17, P18

Spending will continue to be monitored monthly against the approved 2025/26 budget so that pressures can be responded to and budgets flexed where appropriate. Report P5

The money

  • £20,575 Total forecast overspend against the partnership budget at month 6 Report P3, P4
  • £5,144 Forecast overspend per borough Report P3
  • £11,082 Forecast overspend on Core Partnership Team Activity Report P3, 3.3, P13
  • £9,537 Forecast overspend on Core Staff Resources, mainly due to the pay award uplift Report 3.4, P13
  • £1,544 Forecast overspend on the three document management systems Report 3.5, P13
  • £9,493 Legal support costs incurred outside the agreed budget for the recyclates contracts Report 3.8, P16
  • £643,355 Total approved partnership budget for 2025/26 Report P4, P13
  • £663,930 Total forecast spend for 2025/26 Report P4

Options considered

  • Chosen: Note the budget update report as presented. Recommended by the report, with no alternative put forward. Report P17

Implications

  • Financial: Each member borough is set to bear around £5,144 of the £20,575 forecast partnership overspend unless the position changes before year end. Report P3
  • Financial: The pay award uplift from 2.5% to 3.2% is the main driver of the core staff pressure and will need to be reflected in future budget setting. Report 3.4, P10
  • Financial: Subscription costs for the three document management systems are running above budget, with no mitigation proposed in the report. Report 3.5
  • Other: Legal work supporting the new jointly procured recyclates contracts has now concluded, with no further spend anticipated. Report 3.8

Who and where

  • The four member boroughs of the South London Waste Partnership, which share the partnership budget Report P2, P3
  • The officers and advisors funded through the Core Partnership Team Activity budget Report 3.3
  • Contractors involved in the new jointly procured recyclates contracts Report 3.8

Timeline

  • December 2024: The Partnership's 2025/26 budget was approved by the Joint Committee Report P5
  • September 2025: The NJC pay award for local government services was agreed at 3.2%, above the 2.5% assumed in the budget Report 3.4, P10
  • 30th September 2025: Month 6 forecast date used for this budget update Report P3
  • 26th November 2025: Joint Waste Committee meeting at which the update was noted Report P2

Plain English for the jargon

  • South London Waste Partnership (SLWP): A joint arrangement of South London boroughs that manages waste disposal and related contracts on a shared basis.
  • NJC Pay Award: The annual pay settlement negotiated for Local Government Services employees, applied to council staff on all pay scales.
  • Recyclates contracts: Contracts for the processing and marketing of materials collected for recycling, jointly procured by the partnership.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item8

Resolved

To note the content of this report.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to South London Waste Partnership Joint Committee

Page 49 Agenda Item 8

Report to: South London Waste Partnership (SLWP) Joint Waste Committee Date: 26th November 2025 Author(s): Francesco Grieco, Head of Finance & Business Intelligence Report title: South London Waste Partnership Budget Update 2025/26 – Period 6

SUMMARY 1.1 This paper provides a forecast position on the Partnership’s budget for the 2025/26 financial year. 1.2 At month 6 of the financial year 2025/26, that being 30th September 2025, the forecast is a total overspend of £20,575 against the approved budget, which equates to £5,144 per borough. 1.3 The overspend can be summarised as: £9,493 in unbudgeted legal costs and a £11,082 overspend in the core activity budget.

Budget Forecast Variance TOTAL £643,355 £663,930 £20,575

BACKGROUND 2.1 The Partnership sets its budget each year for the forthcoming financial year. Spend against budget is monitored monthly in order to respond to pressures and to allow budgets to be flexed where appropriate. The budget for 2025/26 was approved at the December 2024 Joint Committee. Appendix 1 contains a breakdown of the approved budget, along with individual borough out turns.

FINANCIAL POSITION COMMENTARY – 2025/26

3.1Core Budget 3.2 The Core Partnership Activity budget covers staff salaries, communications advisor support, IT and HR support, and the document management system. The core staff activities include contract management, commissioning, infrastructure development work, and finance administration.

3.3The budget for the ‘Core Partnership Team Activity’ is currently forecasting an overspend of £11,082.

3.4There is a forecast overspend in the Core Staff budget line of £9,537 which can be largely attributed to the NJC Pay Award for Local Government Services for 2025/26. An estimated 2.5% uplift had been included in the approved 2025/26 budget however

1 Agenda Item 8 Page 50 the final settlement was agreed in September 2025 with an increase of 3.2% applying to Council employees on all pay scales.

3.5There is a forecast overspend in relation to the three SLWP document management systems of £1,544. This can be attributed to increased subscription costs for both the Health and Safety monitoring system (£200 above budget), the Price adjustment and cost indices system (£610 above budget) and the Contract Storage system (£734 above budget).

3.6The Advisors and Corporate Support budget line is currently forecast to be delivered to budget.

Budget Forecast Variance Core Partnership Team Activity £643,355 £654,437 £11,082 Advisors and Corporate Support £42,400 £42,400 £0 Document Management £17,550 £19,094 £1,544 Core Staff Resources £583,405 £592,942 £9,537

3.7Additional Costs Outside of Agreed Budget

3.8Legal Support Costs – Year to date the Partnership has incurred legal support costs totalling £9,493 which fall outside of the agreed budget. This work involved the finalisation of contract documentation for the new jointly procured recyclates contracts, as well as addressing a number of last-minute queries raised by one of the contractors. This work has now been completed and we are not anticipating any further spend in this area.

Budget Forecast Variance Additional Costs £0 £9,493 £9,493 Legal Support £9,493 £9,493 £9,493

Recommendations: 4.1 To note the content of this report.

Impacts and Implications 5.1 Finance - Contained within report.

Appendices 6.1 Appendix 1 SLWP Budget Detail 2025/26

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
3.0 PART A: JWC Partnership Budget Update P6 2025-26 V4Report 486 KB DownloadRead as text
PDF
3.1 Appendix 1: SLWP Budget Detail 2025_26Appendix 84 KB Download

At this meeting

Whole meeting

Who was there

7 of 8 attended
CW
Councillor Christopher WoolmerChair, present
SN
Councillor Stuart NeaversonVice-Chair, present
SA
Councillor Stephen AlambritisCommittee Member, apologies
IA
Councillor Isabel AraujoCommittee Member, present
NN
Councillor Nicola NardelliCommittee Member, present
TR
Councillor Tom ReeveCommittee Member, present
SR
Councillor Scott RocheCommittee Member, present
RW
Councillor Robert WardCommittee Member, present

On this subject at Sutton

Search all
  1. Budget Update 2025/26This decision
  2. Business Plan 2026-29 and Budget 2026-27Noted
  3. Business Plan 2026-29 and Budget 2026-27Approved
  4. Sutton Decentralised Energy Network (SDEN) Business Plan and BudgetApproved
  5. Cognus Business Plan and BudgetNoted
  6. Sutton Living Limited (SLL) 2026/27 Budget & Ten Year Business PlanApproved

More from Sutton South London Waste Partnership Joint Committee

All decisions
MeetingDecisionOutcome
26 Nov 2025 Minutes of the previous meetingThat the minutes of the previous meeting held on 11 June 2025 were approved as a correct record. Approved Open
26 Nov 2025 Communications and Engagement UpdateTo Note the contents of this report and comment on any aspects of communications and engagement activities relating t... Noted Open
26 Nov 2025 Contracts Performance ReportNote the latest position with the ERF residual waste treatment contract related to the recent CEMS calibration issue ... Noted Open
26 Nov 2025 Proposed Management Budget 2026/27To approve the 2026/27 SLWP Budget of £707k. This represents an annual cost of £177k per borough and an increase of j... Approved Open