Contract Award - Cloud Data Centre Services

Approved Committee 1 paper

AI summarySutton's Strategy and Resources Committee approved a 5-year cloud data centre contract with AWS, starting 18 December 2025, expected to deliver net savings of £41k per year from 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedCloud data centre services, starts 18 Dec 2025, 60 months total
MoneyNet saving £41k per year from 2026/27Part year saving £11k in 2025/26; £540k per year for Sutton
What happens nextContract commences 18 December 2025Direct award via YPO framework 001126; Contracts Finder notice needed
Who it affectsSutton and Royal Borough of KingstonShared cloud data centre services contract

What was decided

The committee approved awarding the cloud data centre services contract to AWS, commencing 18 December 2025, for a total of 60 months: 36 months initial term plus two optional 12-month extensions.

Why

The new AWS contract is expected to be more energy efficient than the existing on-premises data centres, supporting the council's environmental goals and AWS's net-zero commitment by 2040. Report P1

Although the new contract costs £156k more per year than the current one, the closure of the Civic data centre will save £119k per year in electricity, producing a net saving of £41k per year from 2026/27. Report P4, P5, P6

Awarding to AWS avoids migration costs and service disruption risks associated with moving to an untested supplier, as the council already uses AWS services. Report P9

What happens next

Officers will use the YPO framework 001126 to make a direct award, following the framework's user guide and direct award guidance to stay compliant with Public Contract Regulations 2015. Report P12, P13, P14

Legal commentary recommends clarifying the conflict in the user guide on pre-defined terms, or using the template terms and conditions. Report P15

A Contracts Finder Notice must be published and the council's Contract Register updated to reflect the new call-off contract. Report P16

The money

  • £1,342k Annual cost of the new AWS contract shared between Sutton and Kingston Report P4
  • £156k Annual increase compared with the existing contract Report P4
  • £78k Increased cost to Sutton per year Report P4
  • £119k Forecast annual electricity savings for Sutton from closing the Civic data centre Report P5
  • £41k Net saving per year for Sutton from 2026/27 Report P6
  • £11k Net savings in 2025/26 part year Report P6
  • £540,000 Estimated annual contract value for Sutton Report P12
  • £540,000 Estimated annual contract value for the Royal Borough of Kingston Report P12

Options considered

  • Chosen: Award the AWS contract via direct award from the YPO framework 001126. Avoids migration costs and service disruption; existing AWS services in use; lower risk Report P8, P9, P12
  • Rejected: Migrate to a different supplier. Would involve significant transition and migration costs and risks from moving to an untested supplier Report P9

Implications

  • Financial: Net revenue saving of £41k per year from 2026/27 and £11k part year in 2025/26, to be reflected in the 2026/27 budget and Medium Term Financial Plan. Report P6
  • Legal: Direct award must follow the YPO framework user guide to remain compliant with Regulation 33 of the Public Contract Regulations 2015; clarity on terms needed. Report P13, P14, P15
  • Climate: Expected significant positive environmental impact from cloud energy efficiency; AWS targets 100% renewable energy globally by 2025 and net-zero by 2040. Report P1
  • Risk: Financial checks show low risk of supplier financial failure; staying with AWS avoids migration and disruption risks. Report P8, P9
  • Other: Contracts Finder Notice must be published and the contract register updated. Report P16

Who and where

  • London Borough of Sutton council services using cloud data centre Report P4, P12
  • Royal Borough of Kingston, as joint user of the shared AWS contract Report P4, P12
  • Sutton residents and staff using council digital services Report P9

Timeline

  • 11 January 2024: YPO framework 001126 commenced Report P13
  • 13 October 2025: Procurement (Steve Hoy, Head of Commissioning and Procurement) consulted Report P30
  • 14 October 2025: Legal (James Fry, Senior Lawyer) consulted Report P29
  • 11 November 2025: Finance (Victoria Goddard, Director of Finance) consulted Report P28
  • 8 December 2025: Strategy and Resources Committee decision date
  • 18 December 2025: Contract with AWS commences
  • 2025/26: Part year net savings of £11k Report P6
  • 2026/27: Full year net savings of £41k begin, reflected in budget and MTFP Report P6
  • January 2028: YPO framework 001126 expires Report P13

Plain English for the jargon

  • YPO framework 001126: A pre-established procurement framework agreement that allows permitted councils to call off cloud data centre services.
  • Direct award: A procurement method where a contract is awarded to a single supplier on a framework, without a competitive mini-tender.
  • Public Contract Regulations 2015 (PCR): The UK regulations governing how public sector bodies must procure works, goods and services.
  • Regulation 33 PCR: The provision setting out conditions under which contracts may be awarded via a framework agreement, including direct awards.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item32

Resolved

That the award of the contract to AWS for the cloud data centre services to the AWS commencing 18 Dec 2025 for total duration of 60 months including 36 months of initial duration with optional two extensions of 12 months each be approved.
Word for word from the decision Sutton published for this meeting. Source: moderngov.sutton.gov.uk

Follow this further

Built from Sutton's papers

What the report saysPro

Report to Strategy and Resources Committee

Page 161 Agenda Item 11 Contract Award - Cloud Data Centre Services

Report Title Contract Award - Cloud Data Centre Services

Committee Strategy and Resource Committee

Meeting Date 08 December 2025

Chair Councillor Barry Lewis, Leader of the Council

Lead Member Councillor Sunita Gordon, Lead Member for Resources

Report From Richard Simpson, Strategic Director of Resources

Report Author(s) Ben Unsworth, Director for Digital & IT Shared Service

Ward(s) Affected Council Business

Ambitious for Sutton Action on climate change priorities An efficient and well run Council

Open/Exempt Open

Signed Date 24 November 2025

1​ Summary​

1.1​ Ambitious for Sutton sets out the vision for the borough, focused on making Sutton a great place to live, work and raise a family. Priorities include creating an inclusive community, keeping people safe and ensuring the Council is well run.The Council relies on high availability cloud data centre services as critical infrastructure for the delivery of digital and technology services.

1.2​ The Council’s strategy, in line with the UK government’s recommended approach, is to reduce the use of on-premise infrastructure and exploit the benefits of more resilient, scalable and energy efficient cloud provision.

1.3​ This report outlines the procurement approach to support this strategy.

2​ Recommendation​

2.1​ To approve the award of the contract to AWS for the cloud data centre services to the AWS commencing 18 Dec 2025 for total duration of 60 months including 36 months of initial duration with optional two extensions of 12 months each.

3​ Background and Key Information​

3.1​ The Council has used Amazon Web Services (AWS) for its primary cloud data centre provision since 2022 through a contract with reseller Bytes Software Services UK Limited.

Report page 1 Agenda Item 11 Page 162 Contract Award - Cloud Data Centre Services

Soft market testing was conducted, considering the three major providers including Microsoft Azure and Google Cloud Platform (GCP). Cloud compute and storage are commodity services and analysis showed that the competing platforms did not offer additional functional or commercial benefits over the existing AWS services.

3.2​ The anticipated migration costs and complexity associated with moving all core services would be significant. Given the successful, reliable partnership with AWS and to achieve the best outcome it is necessary to continue with AWS directly rather than its reseller to meet the Council’s cloud data centre requirements for the next 60 months.

3.3​ This will be a joint contract with The Royal Borough of Kingston upon Thames who will be the lead purchaser. In view of the contract value, a dual commissioning governance process is being undertaken for compliance and value for money assurance. The Kingston committee meeting is on 27 November. The aim is to go live with a new contract on 18 December 2025.

3.4​ With no requirement or intention to move from AWS for at least 36 months, the recommended approach is to continue with the existing cloud data centre provider through a contract directly with the supplier for up to 60 months.

4​ Procurement Strategy

4.1​ This procurement is a continuation of the Council’s previous decision to migrate from on-premise data centres to AWS cloud data centre services. The migration is complete, with almost all of the Council’s digital and technology services provided via the cloud, replacing legacy on-premises infrastructure hosted on our own servers. The Council has also invested heavily in developing the skills required to efficiently and safely operate AWS cloud services.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Contract Award: Cloud Data Centre Services: ReportReport 249 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 16 attended
BL
Councillor Barry LewisChair, present
SM
Councillor Sam MartinVice-Chair, present
RC
Councillor Richard CliftonCommittee Member, present
SG
Councillor Sunita GordonCommittee Member, present
MJ
Councillor Marian JamesCommittee Member, present
CM
Councillor Cryss MennaceurCommittee Member, present
JS
Councillor Jake ShortCommittee Member, present
CW
Councillor Christopher WoolmerCommittee Member, present
TD
Councillor Tom DrummondCommittee Member, present
NG
Councillor Neil GarrattCommittee Member, present
BL
Councillor Bryony Lindsay-CharltonCommittee Member, apologies
JM
Councillor James McDermott-HillCommittee Member, present

All 16 on the meeting page

On this subject at Sutton

Search all
  1. Contract Award - Cloud Data Centre ServicesThis decision
  2. E-bike Contract AwardNoted
  3. Award of contract - Housing Support for Vulnerable AdultsApproved
  4. Contract Award - Parking Enforcement & OperationsApproved
  5. Contract Award - Parking Enforcement and OperationsApproved
  6. Award of contract for waste and street cleansing servicesApproved

More from Sutton Strategy and Resources Committee

All decisions
MeetingDecisionOutcome
22 Jun 2026 MinutesRESOLVED : that the minutes of the meeting held on 16 February 2026 be agreed as an accurate record. Agreed Open
22 Jun 2026 Strategy and Resources Committee: Policy and Strategy OverviewThat the role and remit of the Strategy and Resources Committee as set out in the report be noted. Noted Open
22 Jun 2026 Financial Performance and Outturn 2025/26That the general fund revenue outturn service overspend of £0.46m,which is offset by £2.00m use of contingency and a ... Noted Open
22 Jun 2026 Selection of tenant - Throwley YardThat the grant of a lease for up to 15 years to Bidder A, as identified in the accompanying Appendix A be approved. Approved Open
22 Jun 2026 Electric Vehicle Charging Point (EVCP) ProcurementThat the award of the contract for an electric vehicle charging supplier following the procurement process, be delega... Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies