Resolved
(1) That the report be noted.
Swale Joint Transportation Board noted this item on Monday 7 September 2015. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the report be noted.
To: Swale Joint Transportation Board
By: KCC Highways and Transportation
Date: 7th September 2015
Subject: Highway Works Programme 2015/16
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction in 2015/16
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2015/16
Footway and Carriageway Improvement Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D
Casualty Reduction Measures – see Appendix D1 Integrated Transport Schemes – see Appendix D2 Local Growth Fund – see Appendix D3
Developer Funded Works – see Appendix E
Public Rights of Way – see Appendix f
Traffic Systems – see Appendix G
Bridge Works – see Appendix H
Member Highway Fund – see Appendix I
Conclusion
1. This report is for Members information Contact Officers:
The following contact officers can be contacted on 03000 418181
Toby Howe Highway Manager (East) Alan Blackburn Swale District Manager Alan Casson Resurfacing Manager Katie Lewis Drainage Manager Sue Kinsella Street Lighting Manager Toby Butler Intelligent Transport Systems Manager Kirstie Williams/Melvyn Twycross Transportation, PROW and Safety Schemes Tony Ambrose Structures Manager Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes
Machine Resurfacing – Contact Officer Byron Lovell
Road Name Parish Extent of Works Current Status
Junction with Tory Hill, Programmed for Old Lenham Road Torry Hill Doddington 30th October 2015 and Endings Wood (2 days) Road
Programmed for A2 London Road / Junction with Breach Upchurch 21st August 2015 (5 Hartlip Hill Lane nights)
Footway Improvement - Contact Officer Neil Tree
Road Name Parish Extent of Works Current Status
Entire Length (Replacement of Works commenced Brookes Place Newington tarmac surface and on 20th July 2015 kerbing where (3 weeks) required)
From its junction with Rowetts Way in southerly direction past Parsonage Farm entrance, including To be programmed Church Road Eastchurch the section enclosed August 2015 to by hedgerow. December 2015 (Replacement of tarmac surface and kerbing where required)
Programmed to From Opposite Oak commence on 4th Lane Stores to the September 2015 Oak Lane Minster-on-Sea property The Nook (Deferral possible (Footway protection depending on Stat treatment) work completion)
Works deferred until next financial Entire Length year due to Shurland Avenue Sittingbourne (Footway protection proposed Gas treatment) mains replacement works Entire Length Programmed to Regency Court Sittingbourne (Footway protection commence on 24th treatment) August 2015
From its junction with the A2 Fox Hill to Programmed to junction with Ashtead School Lane Bapchild commence on 1st Drive September 2015 (Footway protection treatment)
Entire Length Programmed to Meads Avenue Sittingbourne (Footway protection commence on 15th treatment) August 2015
Entire Length Programmed to Knightsfield Road Sittingbourne (Footway protection commence on 19th treatment) August 2015
Surface Dressing - Contact Officer [name removed] Name Parish Extent of Works Current Status
From its junction with Tonge/Lynsted with Kinsgdown Road to its Dully Road Completed Kingsdown junction with Upper Road
From its junction with Housefield Road to its Heel Road Throwley/Stalisfield Completed junction with Pettfield Hill Road
From its junction with Throwley Road to its Housefield Road Throwley/Stalisfield Completed junction with Heel Road
From its junction with Kingsdown Road Lynsted with Kingsdown Doddington Lane to its Completed junction with Dully Rd
From its junction with A2 London Road to its Nouds Lane Lynsted with Kingsdown Completed junction with Bogle Road
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Swale Highway Works Programme Report: September 2015Report | 139 KB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.