Resolved
(1) That the report be noted and that KCC officers present a presentation at the next meeting of the JTB on 28 February 2022.
Swale Joint Transportation Board noted this item on Monday 6 December 2021. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the report be noted and that KCC officers present a presentation at the next meeting of the JTB on 28 February 2022.
Introduction Kent County Council as the Highway Authority in Kent manages over a quarter of a million roadside drains across the county together with 6200km of pipework, manholes, soakaways, and other assets associated with highway drainage. It is the second largest asset group within the highway authority.
The asset base is increasing every year as part of our highway improvements and as newly adopted highways join the network from new developments.
Highway Drains are designed to:
• remove surface water run-off from the highway to help keep roads safe and minimise problems • prevent damage and make roads last longer through effective drainage • minimise surface water from the highway affecting properties or land
Our highway drains are not usually designed to provide drainage for other areas outside of the highway boundary, such as for land drainage or privately owned property or developments.
Planned and Reactive Maintenance KCC need take an asset management led approach to maintaining over 0.25 million highway drains across the county. Our current approach is set out below.
• Yearly inspections and cleansing of roadside drains throughout our key routes that link towns and villages. • Twice yearly cleansing of roadside drains we have designated as most vulnerable to flooding – which are identified using enquiry data from historic reports from the public.
If a drain is not on the planned programme, it is maintained in response to reports of flooding. Reported drains are then risk assessed for highway safety and internal property flooding.
Other parts of the drainage system owned by the highway authority, such as pipes, soakaways, lagoons, and ponds are maintained on a reactive basis if problems are found during the routine drain maintenance or identified from flooding reports. Reactive maintenance is usually undertaken within 28 to 90 days of a report being received, unless it is an emergency.
Emergency attendances are undertaken as a ‘make safe’ service, particularly those which occur out of hours. In these instances, KCC would act within 2 hours. This may involve closing the road temporarily, clearing the flood with tankers or assisting the emergency services or partner organisations.
The highway authority does not maintain public foul or surface water sewers, drainage serving private property, or land drainage features such as roadside ditches and watercourses. KCC would refer these matters to the relevant authority or landowner as appropriate.
Drainage repairs, improvements, and schemes: If any defects within the drainage system are identified during routine maintenance operations, the enquiry will be passed to one of our local Drainage Engineers for further assessment. KCC aim to undertake these assessments within 28 days of being referred to the engineer. KCC currently have one drainage engineer covering the Swale Borough, together with two schemes engineers for larger improvement works between them covering the entire county. Our engineers carry out a variety of investigation and civil engineering works to repair or improve our drainage systems. KCC can carry out specialist work such as CCTV investigations in order identify defects. This is supported by dedicated contractor resources via our Drainage Framework Contract (comprising three civil engineering contractors) to enhance our resources for delivery of drainage repair works in addition to those services provided by our term maintenance contractor, Amey.
If flooding keeps happening in the same place, KCC will investigate how the situation can be improved and these sites will be entered onto a forward programme of planned work. Currently our countywide highway drainage capital works budget for 21/22 is £4.5m of which £1.5m is allocated to drainage improvement schemes across the county.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Swale DrainageReport | 218 KB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.