Item468

Resolved

(1) That the report be noted.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Swale Joint Transportation Board

To: Swale Joint Transportation Board

By: KCC Highways, Transportation & Waste

Date: 6th December 2021

Subject: Highways Forward Works Programme: 2021/22 and 2022/23

Classification: Information Only

Summary: This report updates Members on the identified schemes approved for construction

1. Introduction

This report provides an update and summarises schemes that have been programmed for delivery in 2021/22 and 2022/23.

Kent County Council has recently published a forward works programme for the next five years covering planned maintenance of our highway assets. It is in two parts: the first concerns the next two years (2021/22 - 2022/23), and most of the sites included have already been verified by our engineers. The second part relates to years three to five of our five-year programme (2023/24 - 2025/26), and is largely based on data from our asset management systems, so may be subject to more changes as the schemes are verified.

This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect our changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase, and additional sites may be added or others advanced if their condition deteriorates rapidly so that we need to react in order to keep the highway in a safe and serviceable condition.

Further information about how we manage our highway infrastructure, including our county- wide five-year forward works programme, may be found on our website: https://www.kent.gov.uk/about-the-council/strategies-and-policies/transport-and-highways- policies/managing-highway-infrastructure

In addition to planned maintenance of our highway assets, this report includes transportation and safety schemes, developer funded works, Combined Members Grant schemes, and planned maintenance of public rights of way.

Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A

Drainage Repairs & Improvements – see Appendix B

Street Lighting – see Appendix C

Transportation and Safety Schemes – see Appendix D • Casualty Reduction Measures • Externally funded schemes

Developer Funded Works – see Appendix E Bridge Works – see Appendix F

Traffic Systems – see Appendix G

Combined Members Grant – Member Highway Fund – see Appendix H

Public Rights of Way – see Appendix I

Conclusion

1. This report is for Members’ information.

Contact Officers:

The following contact officers can be contacted on 03000 418181

Pauline Harmer Highway Manager Mid Kent Alan Blackburn Swale District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage Asset Manager Neill Coppin Structures Operations Team Leader Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Jamie Watson Schemes Programme Manager Appendix A – Road, Footway and Cycleway Renewal and Preservation Scheme

The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.

Machine Resurfacing – Contact Officer Byron Lovell

Road Name Parish Extent of Works Current Status

Eden Meadow to A2 Boyces Hill Sittingbourne Completed Keycol Farm House

B2005 Grovehurst Kemsley Bridge over A249 To be confirmed Interchange Investigation and design works Stabilisation Works Canterbury Road (Boughton being carried out. Boughton-under-Blean East of Staplestreet Hill) Construction Road works to begin early 2022

Footway Improvement - Contact Officer Neil Tree

Extent and Road Name Parish Current Status Description of Works

Footway Reconstruction From the junction with Leysdown Road Leysdown Warden Bay Road to Completed. approx. o/s the exit of the bus layby (North side).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Highways Work ProgrammeReport 418 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

18 of 35 attended
BA
Billy AttawayOfficer, in attendance
MB
Mr Mike BaldockKent County Councillor, present
CB
Mr Cameron BeartKent County Councillor, present
AB
Alan BlackburnOfficer, in attendance
MB
Monique BonneyCommittee Member, present
AB
Mr Andy BoothKent County Councillor, present
DB
Mr David BrazierVisiting Councillor, in attendance
MC
Martyn CassellOfficer, in attendance
SC
Simon ClarkCommittee Member, apologies, sent representative
SD
Steve DaveyVisiting Councillor, in attendance
MD
Mr Mike DendorKent County Councillor, present
OE
Oliver EakinVisiting Councillor, in attendance

All 35 on the meeting page

On this subject at Swale

Search all
  1. Highways Work ProgrammeThis decision
  2. Highways Work ProgrammeNoted
  3. Highways Work ProgrammeNoted
  4. Highways Work ProgrammeNoted
  5. Verbal update from National Highways on the M2 Junction 5 Stockbury WorksNoted
  6. Highways Work ProgrammeNoted

More from Swale Swale Joint Transportation Board

All decisions
MeetingDecisionOutcome
29 Jun 2026 Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... Decided Open
29 Jun 2026 Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. Noted Open
6 Oct 2025 Highways Work Programme(1) That the report be noted. Noted Open
6 Oct 2025 Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. Noted Open
30 Jun 2025 Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. Noted Open