Resolved
(1) That the report be noted.
Swale Joint Transportation Board noted this item on Monday 20 June 2022. Below is the council's own wording, with the papers it was decided on.
Resolved
(1) That the report be noted.
To: Swale Joint Transportation Board
By: KCC Highways, Transportation & Waste
Date: 20th June 2022
Subject: Highways Forward Works Programme: 2022/23
Classification: Information Only
Summary: This report updates Members on the identified schemes approved for construction
1. Introduction
This report provides an update and summarises schemes that have been programmed for delivery in 2021/22 and 2022/23.
Kent County Council has recently published a forward works programme for the next five years covering planned maintenance of our highway assets. It is in two parts: the first concerns the next two years (2021/22 - 2022/23), and most of the sites included have already been verified by our engineers. The second part relates to years three to five of our five-year programme (2023/24 - 2025/26), and is largely based on data from our asset management systems, so may be subject to more changes as the schemes are verified.
This programme is subject to regular review and may change for a number of reasons including budget allocation, contract rate changes, and to reflect our changing priorities. The programme and extent of individual sites within the programme may also be revised following engineering assessment during the design phase, and additional sites may be added or others advanced if their condition deteriorates rapidly so that we need to react in order to keep the highway in a safe and serviceable condition.
Further information about how we manage our highway infrastructure, including our county- wide five-year forward works programme, may be found on our website: https://www.kent.gov.uk/about-the-council/strategies-and-policies/transport-and-highways- policies/managing-highway-infrastructure
In addition to planned maintenance of our highway assets, this report includes transportation and safety schemes, developer funded works, Combined Members Grant schemes, and planned maintenance of public rights of way.
Road, Footway & Cycleway Renewal and Preservation Schemes – see Appendix A
Drainage Repairs & Improvements – see Appendix B
Street Lighting – see Appendix C
Transportation and Safety Schemes – see Appendix D Casualty Reduction Measures Externally funded schemes
Developer Funded Works – see Appendix E Bridge Works – see Appendix F
Traffic Systems – see Appendix G
Combined Members Grant – Member Highway Fund – see Appendix H
Public rights of way – see Appendix I
Conclusion
1. This report is for Members’ information.
Contact Officers:
The following contact officers can be contacted on 03000 418181
Richard Emmett Highway Manager Mid Kent Alan Blackburn Swale District Manager Alan Casson Strategic Asset Manager Earl Bourner Drainage Asset Manager Neill Coppin Structures Operations Team Leader Sue Kinsella Street Light Asset Manager Toby Butler Traffic & Network Solutions Asset Manager Jamie Hare Development Agreements Manager Jamie Watson Schemes Programme Manager Appendix A – Footway and Carriageway Improvement Schemes
The delivery of these schemes is weather dependent; should it prove not possible to carry out these works on the planned dates, new dates will be arranged and the residents will be informed by a letter drop to their homes.
Machine Resurfacing – Contact Officer Byron Lovell
Road Name Parish Extent of Works Current Status
Design work being Stabilisation Works carried out. Works Canterbury Road (Boughton Dunkirk East of Staplestreet maybe delayed due Hill) Road to high material costs Between Halfway Programmed 8th B2008 Minster Road Minster-On-Sea Crossroads to Barton June 2022 Hill Drive From Park Road to Programmed 13th High Street / West Street Sittingbourne Central Avenue July 2022
Between South Road Programmed 1st A251 Stone Street Faversham and Preston Street June 2022
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highways Work ProgrammeReport | 1 MB | DownloadRead as text |
Follow Swale Joint Transportation Board at Swale and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 29 Jun 2026 | Presentation from Network Rail(1) That it be recommended to the relevant parties at Swale Borough Council and Kent County Council that a joint work... | Decided | Open |
| 29 Jun 2026 | Update on the Local Electric Vehicle Infrastructure (LEVI) Project and other Electric Vehicle (EV) charging infrastructure(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Highways Work Programme(1) That the report be noted. | Noted | Open |
| 6 Oct 2025 | Progress Update Report - including updates on Grovehurt Road junction Sittingbourne and Key Street junction Sittingbourne(1) That the update report and verbal updates be noted. | Noted | Open |
| 30 Jun 2025 | Update Report - Proposed Double Yellow Lines, Park Road, Faversham(1) That the report be noted. | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.