AI summarySwale Housing, Health and Communities Committee notes Cockleshell Walk update, recommends dissolving Swale Rainbow Homes Local Housing Company, and sets up a sub-committee to oversee the project.
Written from the decision and the officer reportPDF Pro
OutcomeNotedSub-committee to oversee Cockleshell Walk Social Homes Project
MoneyNot stated
What happens nextReferral to Policy and Resources CommitteeRecommend dissolving Swale Rainbow Homes Local Housing Company
Who it affectsSwale Rainbow Homes Local Housing CompanyLocal housing company linked to the project
What was decided
The update on the Cockleshell Walk Social Homes Project was noted.
It was agreed to recommend to the Policy and Resources Committee that Swale Rainbow Homes Local Housing Company be dissolved.
A sub-committee of the Housing, Health and Communities Committee was established to oversee and scrutinise the project, with power to set up time-limited task and finish groups.
What happens next
The recommendation to dissolve Swale Rainbow Homes Local Housing Company goes to the Policy and Resources Committee for decision.
The new sub-committee will oversee and scrutinise the Cockleshell Walk Social Homes Project, and can set up short-term task and finish groups as needed.
Implications
Governance: A new sub-committee of the Housing, Health and Communities Committee is created, with delegated authority to set up time-limited task and finish groups.
Legal: Dissolution of Swale Rainbow Homes Local Housing Company is recommended to the Policy and Resources Committee, which would end the company as a separate legal entity.
Who and where
Swale Rainbow Homes Local Housing Company
Cockleshell Walk Social Homes Project
Housing, Health and Communities Committee
Policy and Resources Committee (as recommending body)
Timeline
2026-03-25: Housing, Health and Communities Committee meeting where the decision was made.
Plain English for the jargon
Local Housing Company: A council-owned or council-linked company set up to deliver housing, as named in the decision.
Sub-committee: A smaller group of committee members given delegated powers to act on its behalf.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item850
Resolved
That the update be noted. That it be recommended to the Policy and Resources Committee that Swale Rainbow Homes Local Housing Company be dissolved. That a sub‑committee of the Housing, Health and Communities Committee be established to oversee and scrutinise the project, with authority to establish time‑limited task and finish groups as required.
Word for word from the decision Swale published for this meeting.Source: democracy.swale.gov.uk
Report to Housing, Health and Communities Committee
Housing, Health, and Community Committee Meeting Date 25th March 2026
Report Title Cockleshell Walk Social Homes
EMT Lead Emma Wiggins, Director of Regeneration and Neighbourhoods Head of Service Charlotte Hudson, Head of Housing and Communities
Lead Officer Charlotte Hudson, Head of Housing and Communities
Classification Open
Recommendations The committee is recommended: 1. To note the current update on the Cockleshell Walk Project 2. To recommend to Policy and Resources the closure of Swale Rainbow Homes, Local Housing Company. 3. To discuss the future governance arrangements to manage the project.
1 Purpose of Report and Executive Summary 1.1 This report provides the Housing, Health, and Community Committee with an update on the Cockleshell Walk Social Homes project and discusses the requirement for changes to the governance arrangements for the project.
2 Background 2.1 In October 2020 Cabinet resolved to set-up a Local Housing Company, Swale Rainbow Homes (SRH) and to loan the company up to £23m to fund the Capital development. This decision was called in by Scrutiny in November 2020.
The principal aims of the Council in undertaking the LHC was to:
• Increase the supply of affordable housing; • ensure that the solution is financially viable and doesn’t place a financial burden on the Council; • ensure the properties are energy efficient as possible within the financial constraints; • ensure densities are appropriate for the location and management of any scheme; • control and influence around what is delivered; • quality and design standards; and • acts as exemplar landlord in the rented sector.
2.2This decision was based upon the model produced by Savills and provided a scheme that provided 139 properties of a mix of 1- and 2-bedroom properties, over three sites. The model was developed based upon build costs, provides allowances to enable energy efficiency standards as well as factoring in whole lifecycle costs of developing, managing, and maintaining the properties.
2.3The detailed modelling was presented to Cabinet and Scrutiny by Savills at the time, it demonstrated a financially viable scheme and based the financing of SRH entirely from the Council with a repayment period within the 50-year period (as per terms of the PWLB at a modelled rate of 3%).
2.4Overall development costs were deemed to be between £20 million and £23 million for all three sites. Since the initial modelling in 2020, there has been significant changes to the UK economy and in particular the construction industry. With significant inflation in materials and labour market shortage, and significant increase in borrowing rates, this has led SRH to review the financial appraisal assumptions of the schemes.
2.5A revised model was developed by the Director of Resources (s.151 Officer) taking into consideration modelled build costs, current interest rates and the intended operating models. Different tenures and therefore rent levels were also considered as part of the modelling. This identified the shortfall in funding for the scheme and levels of external funding that needed to be secured, to make the scheme viable and meet the objectives set out by Cabinet in 2020.
Scheme Design, Planning Permission and Appropriation
2.6To pursue the development SRH appointed consultants Counties and Capital Consulting to take forward the scheme developments and act as Development Managers. The scheme on Cockleshell Walk delivers a policy complaint scheme which consists of 51 homes spread across three residential blocks on the site along with associated landscaping and car parking. The Planning application, provides details of the full scheme. Planning Permission was granted at Planning Committee on the 23rd of May 2024 & Memorandum of Understanding (S106 equivalent) was signed on 18th March 2025.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.