Cockleshell Walk Social Homes Project

Noted Committee 1 paper

AI summarySwale Housing, Health and Communities Committee notes Cockleshell Walk update, recommends dissolving Swale Rainbow Homes Local Housing Company, and sets up a sub-committee to oversee the project.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeNotedSub-committee to oversee Cockleshell Walk Social Homes Project
MoneyNot stated
What happens nextReferral to Policy and Resources CommitteeRecommend dissolving Swale Rainbow Homes Local Housing Company
Who it affectsSwale Rainbow Homes Local Housing CompanyLocal housing company linked to the project

What was decided

The update on the Cockleshell Walk Social Homes Project was noted.

It was agreed to recommend to the Policy and Resources Committee that Swale Rainbow Homes Local Housing Company be dissolved.

A sub-committee of the Housing, Health and Communities Committee was established to oversee and scrutinise the project, with power to set up time-limited task and finish groups.

What happens next

The recommendation to dissolve Swale Rainbow Homes Local Housing Company goes to the Policy and Resources Committee for decision.

The new sub-committee will oversee and scrutinise the Cockleshell Walk Social Homes Project, and can set up short-term task and finish groups as needed.

Implications

  • Governance: A new sub-committee of the Housing, Health and Communities Committee is created, with delegated authority to set up time-limited task and finish groups.
  • Legal: Dissolution of Swale Rainbow Homes Local Housing Company is recommended to the Policy and Resources Committee, which would end the company as a separate legal entity.

Who and where

  • Swale Rainbow Homes Local Housing Company
  • Cockleshell Walk Social Homes Project
  • Housing, Health and Communities Committee
  • Policy and Resources Committee (as recommending body)

Timeline

  • 2026-03-25: Housing, Health and Communities Committee meeting where the decision was made.

Plain English for the jargon

  • Local Housing Company: A council-owned or council-linked company set up to deliver housing, as named in the decision.
  • Sub-committee: A smaller group of committee members given delegated powers to act on its behalf.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item850

Resolved

That the update be noted. That it be recommended to the Policy and Resources Committee that Swale Rainbow Homes Local Housing Company be dissolved. That a sub‑committee of the Housing, Health and Communities Committee be established to oversee and scrutinise the project, with authority to establish time‑limited task and finish groups as required.
Word for word from the decision Swale published for this meeting. Source: democracy.swale.gov.uk

Follow this further

Built from Swale's papers

What the report saysPro

Report to Housing, Health and Communities Committee

Housing, Health, and Community Committee Meeting Date 25th March 2026

Report Title Cockleshell Walk Social Homes

EMT Lead Emma Wiggins, Director of Regeneration and Neighbourhoods Head of Service Charlotte Hudson, Head of Housing and Communities

Lead Officer Charlotte Hudson, Head of Housing and Communities

Classification Open

Recommendations The committee is recommended: 1. To note the current update on the Cockleshell Walk Project 2. To recommend to Policy and Resources the closure of Swale Rainbow Homes, Local Housing Company. 3. To discuss the future governance arrangements to manage the project.

1 Purpose of Report and Executive Summary 1.1 This report provides the Housing, Health, and Community Committee with an update on the Cockleshell Walk Social Homes project and discusses the requirement for changes to the governance arrangements for the project.

2 Background 2.1 In October 2020 Cabinet resolved to set-up a Local Housing Company, Swale Rainbow Homes (SRH) and to loan the company up to £23m to fund the Capital development. This decision was called in by Scrutiny in November 2020.

The principal aims of the Council in undertaking the LHC was to:

• Increase the supply of affordable housing; • ensure that the solution is financially viable and doesn’t place a financial burden on the Council; • ensure the properties are energy efficient as possible within the financial constraints; • ensure densities are appropriate for the location and management of any scheme; • control and influence around what is delivered; • quality and design standards; and • acts as exemplar landlord in the rented sector.

2.2This decision was based upon the model produced by Savills and provided a scheme that provided 139 properties of a mix of 1- and 2-bedroom properties, over three sites. The model was developed based upon build costs, provides allowances to enable energy efficiency standards as well as factoring in whole lifecycle costs of developing, managing, and maintaining the properties.

2.3The detailed modelling was presented to Cabinet and Scrutiny by Savills at the time, it demonstrated a financially viable scheme and based the financing of SRH entirely from the Council with a repayment period within the 50-year period (as per terms of the PWLB at a modelled rate of 3%).

2.4Overall development costs were deemed to be between £20 million and £23 million for all three sites. Since the initial modelling in 2020, there has been significant changes to the UK economy and in particular the construction industry. With significant inflation in materials and labour market shortage, and significant increase in borrowing rates, this has led SRH to review the financial appraisal assumptions of the schemes.

2.5A revised model was developed by the Director of Resources (s.151 Officer) taking into consideration modelled build costs, current interest rates and the intended operating models. Different tenures and therefore rent levels were also considered as part of the modelling. This identified the shortfall in funding for the scheme and levels of external funding that needed to be secured, to make the scheme viable and meet the objectives set out by Cabinet in 2020.

Scheme Design, Planning Permission and Appropriation

2.6To pursue the development SRH appointed consultants Counties and Capital Consulting to take forward the scheme developments and act as Development Managers. The scheme on Cockleshell Walk delivers a policy complaint scheme which consists of 51 homes spread across three residential blocks on the site along with associated landscaping and car parking. The Planning application, provides details of the full scheme. Planning Permission was granted at Planning Committee on the 23rd of May 2024 & Memorandum of Understanding (S106 equivalent) was signed on 18th March 2025.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Cockleshell Walk Social Homes ProjectReport 271 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

15 of 21 attended
LB
Lloyd BowenCommittee Member, present
HB
Hayden BrawnCommittee Member, present
DC
Derek CarnellCommittee Member, apologies
AC
Ann CavanaghCommittee Member, present
SC
Steph CurtisOfficer, in attendance, virtual
KG
Kieran GoldingCommittee Member, apologies, sent representative
AG
Alastair GouldCommittee Member, present
AH
Angela HarrisonVice-Chair, present
CH
Charlotte HudsonOfficer, in attendance
PM
Peter MacDonaldCommittee Member, apologies, sent representative
PM
Peter MarchingtonCommittee Member, present
BJ
Ben J MartinCommittee Member, present

All 21 on the meeting page

On this subject at Swale

Search all
  1. Cockleshell Walk Social Homes ProjectThis decision
  2. Appropriation of Cockleshell Walk, SittingbourneApproved
  3. Procurement of Build Contract for Cockleshell Walk, SittingbourneAgreed
  4. 4.1 - 23/503228/FULL Cockleshell Walk Car Park, SittingbourneApproved

More from Swale Housing, Health and Communities Committee

All decisions
MeetingDecisionOutcome
14 Jul 2026 Forward Decisions Plan(1) The be noted. Noted Open
14 Jul 2026 Housing, Homelessness and Rough Sleeping Strategy(1) That the draft Homelessness and Rough Sleeping Strategy 2026-2030 be approved for consultation Approved Open
13 May 2026 Election of Chair(1) That Councillor Hannah Perkin be elected as Chair for the municipal year 2026/27. Decided Open
13 May 2026 Election of Vice-Chair(1) That Councillor Angela Harrison be elected as Vice-Chair for the municipal year 2026/27. Decided Open
21 Apr 2026 Procurement of Build Contract for CCTV Control Room ExpansionResolved : (1) That the Committee approves the appointment of Company A as supplier for the CCTV Control Centre Expan... Approved Open