RESOLVED that: (1) the position with respect to Regional Transport Consortia Grant spend at the end of February 2014 and the end of year claims process and timescales be noted; (2) the virements proposed by SWWITCH Programme Management Group be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
1.1As the 2013/14 financial year draws to a close this paper provides an update on progress on delivery of the 2013/14 Regional Transport Consortia Grant allocation of £6.882m. As final claims will not be submitted until late in April, the details in this paper only include spend up to the end of February 2014.
1.2Also included are details of virements during the last two months.
2.0RTCG PROGRESS TO THE END OF FEBRUARY 2014
2.1As at the end of February (month eleven of the financial year) RTCG spend is as shown in the table below.
Table One – RTCG spend up to the end of February 2014 Element Allocation Actual spend Amount to be % remaining (£k) on ledger spent (£k) (£k) RTP capital 5,239 3,181 2,058 39% RTP revenue 205 167.6 37.4 18% RSG capital 959 519.8 439.5 45% RSG revenue 479 404.1 74.9 16% Total 6,882 4,272.5 2,609.5
2.2The revenue budgets, whether Road Safety or RTP are progressing according to plan and full expenditure is predicted. For RTP and Road Safety Capital allocations there remain large sums (and significant proportions) of the annual allocation to be claimed.
2.3However, Project Managers from each Council are still confident of achieving full spend and have confirmed that (in a similar fashion to previous years) much of the allocation has been spent. The delay is administrative, related to ensuring that invoices get on the ledger in time.
2.4The “end of year” processes for the RTCG have been circulated and final estimates have already been submitted to the WG. These clearly show that full grant expenditure is predicted. The next steps are the submission of the final claims which are due with WG by the end of April. Final payment, assuming all the details of the submission are correct, will then be made within a month to Swansea as Host financial authority and then paid onward to individual Local Authorities in response to invoices raised. 3.0 VIREMENTS
3.1At last Joint Committee it was reported that two virements requests (approved by SWWITCH PMG) had been submitted to the Welsh Government and a response was outstanding. The two virements were approved and appropriate adjustments to allocations have been made.
3.2Since December further virements have been requested as shown in Table Two below.
Table Two – RTCG virement requests Element of RTCG and Project Value of PMG Next steps Virement decision RTP Capital - Virement of £33k to £52k Agreed Approved by WG Ammanford to Cross Hands Bus Corridor officials and £19k to Carmarthenshire rural interchanges. Both form Carmarthen to Swansea bus corridor RTP Capital - Virement of £18k from £32k Agreed Approved by WG Fabian way Walking/cycling scheme and officials £14k from NPT Walking/cycling scheme – both to Amman Valley Cycleway RTP Capital – Virement of £2.9k from £4k Agreed Approved by WG Community Transport capital enhancement officials grant and £1.9k form Programme management and monitoring - both to Port Talbot to Swansea Bus Corridor (and Baglan bridge) RTP Capital – An additional £12k for each £50k Agreed Referred for of Milford Haven and Pembroke dock Ministerial interchanges, an additional £20k to approval and Carmarthenshire Riverside route and an approval granted additional £6k to Port Talbot to Swansea 17th March 2014 Bus Corridor (and Baglan bridge). All from preparation for Post 2015 policy and planning allocation of £50k
Recommendations
4.1It is RECOMMENDED that:
(i) Joint Committee notes the position with respect to Regional Transport Consortia Grant spend at the end of February 2014 and the end of year claims process and timescales (ii) Joint Committee approves the virements proposed by SWWITCH Programme Management Group
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.