Resolved
Resolved that: 1) The progress in relation to the More Homes Delivery Programme be noted.
Economy & Infrastructure Service Transformation Committee noted this item on Thursday 29 February 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that: 1) The progress in relation to the More Homes Delivery Programme be noted.
Report of the Director of Place
Economy & Infrastructure Service Transformation Committee - 29 February 2024
More Homes Delivery Programme Purpose: To provide a briefing on the progress of the More Home Delivery Programme.
Policy Framework: HRA Capital Investment Programme, HRA Business Plan, More Homes Strategy.
Consultation: Access to Services, Finance, Legal.
Recommendation(s): It is recommended that:
1) Councillors consider the report, to give their views and make recommendations to the Cabinet Member as necessary.
Report Author: Rosie Jackson
Finance Officer: Ben Smith
Legal Officer: Adrian Jeremiah
Access to Services Officer: Rhian Millar
1. Introduction
1.1The More Homes Delivery Programme is a key mechanism to deliver the corporate commitment to increase the amount of affordable housing in Swansea.
1.2This report will provide information on progress to date, outline the schemes currently in development and future plans. It will also outline the challenges and opportunities faced. 2. Background
2.1Cabinet approved the first Housing Revenue Account Development Plan in February 2019, which set out a programme to develop over 140 new homes. In January 2020, the Council increased this goal and approved a 10-year ambition to deliver 1,000 additional Council homes from 2021-2031. The recommendations of the report also noted that any changes in the financial assumptions made at that time would result in an increase or decrease in the number of units that the Council can afford to deliver.
2.2Housing demand has steadily increased since 2016 and more rapidly since 2020, due to the impact of the pandemic and other external factors such as the cost-of-living increase, fuel price rises, reduction in availability of private rented accommodation and changes to homelessness legislation by Welsh Government. As a result, the housing waiting list currently stands at over 8,000 households and there are currently just over 300 households in temporary accommodation. These are the highest numbers ever in Swansea and it is a situation replicated across Wales and nationally. Therefore, the need to deliver additional affordable housing as quickly as possible has never been more essential.
2.3To help address this need the More Homes Delivery Programme has increased the amount of accommodation delivered via a successful acquisitions programme and property conversations to sit alongside the development plans to build new homes.
3. Progress to date
3.1To date the More Homes Programme has delivered an additional 255 council homes via a mixed strategy of new build developments, acquisitions and conversions of existing properties. The table below gives further details:
Scheme name / type No. Year Delivery method units completed New Build schemes Colliers Way 1, Penlan 18 2017 In-house Parc Y Helig, Birchgrove 16 2020 In-house Colliers Way 2, Penlan 18 2021 In-house Hillview, Clase 25 2022 In-house Bryn House PODS, 5 2022 External Uplands Cherry Blossom Close, 6 2023 In-house West Cross New Build Sub total 88 Property conversions Acacia Road, West 2 2022 In-house Cross Bryn House, Uplands 4 2022 In-house Ty Forest House, 3 2022 In-house Ravenhill Alexandra Road, 2 2023 In-house Gorseinon Eastside DHO, 4 2023 In-house Bonymaen Penlan DHO 6 2023 In-house Conversion sub total 21 Acquisitions (of former right to buy properties) Acquisition sub total 146 2018-2023 In-house Overall total 255 4. Swansea Standard
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
More Homes Delivery Programme.Report | 417 KB | DownloadRead as text |
Follow Economy & Infrastructure Service Transformation Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 23 Jul 2026 | Disclosures of Personal & Prejudicial Interests from Members.None | Decided | Open |
| 23 Jul 2026 | Minutes.Approved | Approved | Open |
| 23 Jul 2026 | Renewables/District Heat Network.For Infomation | Decided | Open |
| 23 Jul 2026 | Culture Strategy.For Information | Decided | Open |
| 23 Jul 2026 | Work Plan.Noted | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.