Sustainable Swansea - Fit for the Future: Budget Proposals 2016/17 - 2018/19.

Approved Executive 4 papers

Cabinet approved this item on Thursday 10 December 2015. Below is the council's own wording, with the papers it was decided on.

Item129

Resolved

RESOLVED that: 1) The Budget proposals summarised in the report and detailed in Appendix A and Appendix C of the report as the basis of consultation be approved; 2) The approach to consultation and engagement with staff, trade unions, residents, partners and other interested parties set out in Section 7 of the report be agreed; 3) A report on the outcome of the consultation and final budget proposals be presented to Cabinet on 10 th February 2016.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Appendix ‘A’ SUSTAINABLE SWANSEA DELIVERY PROGRAMME 2016/17 – ASSURANCE AND RISK STATEMENT NOVEMBER 2015

The report provides a high-level overview of the Sustainable Swansea Programme and the target savings for 2016/17. The report aims to give an overview of the anticipated activity and risks to delivery at this point in time. The Programme Team, Sponsors, Service Leads, Finance and Performance colleagues will continue to work together over the coming months to further refine savings and opportunities for 2016 and beyond. This will be captured in Service Plans and budget setting activity while delivery and risk will continue to be reported through Programme and Corporate Governance.

Workstream –Efficiency Sponsor – Dean Taylor

Strand Project 2016/17 Action to Achieve Savings Assurance Statement Risks to Lead RAG Savings (including resources) Delivery target £’000 Continuous Lean 200 Training has been delivered Savings are low and Failure to Khan GREEN Improvement Systems by Vanguard achievable complete the Prince Projects reviews 5 Systems Thinking reviews Savings need to be allocated are underway as follows: to each project Overlap with Commissioning  Waste Mgt Support from Vanguard is in Reviews to be  HR – part 1 complete, place managed part 2 underway  LAC/NEET/SEN Joint working with NPT is Failure to align  Customer Contact taking place savings with  Domestic Abuse budgets

Further projects are envisaged across Directorates Workforce Senior Staff 3,000 The purpose and scope of Scope includes 470 posts, Delay in Jack AMBER Appendix ‘A’ Strand Project 2016/17 Action to Achieve Savings Assurance Statement Risks to Lead RAG Savings (including resources) Delivery target £’000 Review the review has been agreed savings are based on a agreeing a new Straw (includes by Directors reduction of 100 posts structure new (average costs of £40k) ie: manager Leadership Team sessions £4m Resources for structure have taken place to consider implementation from design principles and the Target is based on a part year Stopping overall architecture for the saving ie: £3m Compulsory Services) new structure redundancies Further savings are expected will be involved Implementation of the in 2017/18 from later waves changes will be in ”waves”, Budgets need to starting with the Leadership Support has been retained be adjusted mid- Team but dovetailing with from IESE for the initial year depending structural change needed in facilitation and design phase on outcomes Adult Social Care, Business Support and Operations Resources will be required for Alignment of the implementation phase changes with Approval of new leadership commissioning structure expected February Reviews 2016 Reducing 1,000 Changes to terms and Total potential savings are Failure to Cllr Lloyd RED the Paybill conditions of employment around £7m, £1m should be secure Cabinet (JCC achievable agreement to Chair) Options paper reviewed by consult Steve Cabinet. Achievement of savings is Rees dependent on Cabinet Failure to reach Options supported : support to consult Trade agreement with Unions on changes (and their Trade Unions  Reducing the working ideas)early in 2016 following week consultation  Review of standby and Changes can be delivered Appendix ‘A’ Strand Project 2016/17 Action to Achieve Savings Assurance Statement Risks to Lead RAG Savings (including resources) Delivery target £’000 call out payments using internal resources, led Budgets need to  Review of various by HR be adjusted mid- allowances year depending  Ceasing professional on outcomes body payments

Other options are possible Smarter 200 Review of all aspects of our Total council spend on Failure of Khan AMBER Training training functions to design a training is around £4m so Services to Prince single approach to training target savings are low and engage in the across the Council achievable project

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
09 (2 of 4): A4 Sustainable Swansea Delivery Programme AssuranceReport 127 KB DownloadRead as text
PDF
09 (3 of 4): APPENDIX B BGSAppendix 146 KB Download
PDF
09 (4 of 4): Appendix 'C' service savingsAppendix 15 KB Download
PDF
Sustainable Swansea: Fit for the Future: Budget Proposals 2016/17: 2018/19.Report 237 KB Download

At this meeting

Whole meeting

Who was there

8 of 20 attended
RS
Rob StewartLeader of the Council, present
CR
Christine RichardsDeputy Leader of the Council, apologies
MC
Mark ChildCommittee Member, present
WE
William EvansCommittee Member, present
RF
Robert Francis-DaviesCommittee Member, present
JH
Jane HarrisCommittee Member, present
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, apologies
CL
Clive LloydCommittee Member, present
JR
Jennifer RaynorCommittee Member, present
HE
Huw EvansOfficer, in attendance
PF
Patrick FletcherOfficer, expected

All 20 on the meeting page

On this subject at Swansea

Search all
  1. Sustainable Swansea - Fit for the Future: Budget Proposals 2016/17 - 2018/19.This decision
  2. Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.Decided
  3. Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.Approved
  4. Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2024-25.Decided
  5. Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2024-25.Approved
  6. Successful and Sustainable Swansea Corporate Transformation Plan.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies