Revenue and Capital Budget Monitoring – 2nd Quarter 2015/16.

Noted Executive 4 papers

Cabinet noted this item on Thursday 10 December 2015. Below is the council's own wording, with the papers it was decided on.

Item130

Resolved

RESOLVED that: 1) The comments and variations in the report and the actions in hand to address them be noted.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Finance and Strategy

Cabinet – 10 December 2015

REVENUE AND CAPITAL BUDGET MONITORING 2ND QUARTER 2015/16

Purpose: To report on financial monitoring of the 2015/16 revenue and capital budgets, including the delivery of budget savings.

Policy Framework: Budget 2015/16 Sustainable Swansea –fit for the future

Reason for Decision: To note any significant variations from the agreed budget 2015/16 and savings plan and the actions planned to seek to achieve a balanced budget.

Consultation: Cabinet Members, Corporate management Team, Legal Services and Corporate Equalities Unit.

Recommendation: It is recommended that the comments and variations in this report, and the actions in hand to address these, are noted.

Report Author: Mike Hawes

Finance Officer: Mike Hawes

Legal Officer: Sharon Heys

Access to Services Sherill Hopkins Officer:

1. Background and Introduction

1.1This report details forecast variations from the agreed budget for 2015/16, including the latest assessment of the delivery of savings.

1.2In respect of Revenue Budgets, this report provides a consolidated forecast which combines the three key elements that contribute to budget variations, being:

 Variations to planned budget savings (mainly shortfalls) agreed by Council in February 2015 (Appendices C, D and E to this report)  Upward variations overspends arising from service pressures not directly linked to specific savings plans (e.g. increased demand) These variations may be one-off or recurring

 Additional savings/additional income identified during the year that can mitigate the effects of the above. These variations may be one-off or recurring.

1.3The report includes comments from Directors in relation to the variations highlighted and the action that is in hand or proposed as appropriate.

2. Revenue Outturn Forecast Based on September position

2.1Appendix ‘A’ to this report details the approved Revenue Budget for 2015/16 and the forecast variation at this time.

2.2Other than projected variations on Directorate expenditure, there is the potential for variations to occur in three main areas of the Council’s budget. These are:-

 Use of contingency fund, detailed in Section 3 of this report.  Movements in Capital Financing charges – these cannot be forecast at the present time but given prevailing interest rates are not likely to result in overspend  Collection of Council Tax – whilst a surplus may occur it should be treated as a one off and not reflected in overall performance against service budgets. However, at this stage it would be prudent to assume nil variance from budget.

2.3The overall Directorate position is summarised below:-

DIRECTORATE FORECAST SAVINGS OTHER VARIATION VARIATION VARIATION 2015/16 2015/16 2015/16 £000 £000 £000 CORPORATE SERVICES -840 100 -940 PEOPLE - POVERTY AND PREVENTION -25 -25 0 PEOPLE - SOCIAL SERVICES 2,112 2,155 -43 PEOPLE - EDUCATION 1,732 663 1,069 PLACE -320 285 -605 ADDITIONAL SAVINGS STRANDS - TO BE ALLOCATED 2,418 2,418 NET DIRECTORATE EXPENDITURE 5,077 5,596 -519

2.4Directors’ comments on the above variations are shown at appendix ‘B’ :- 2.5 The position on Workstream savings is dependent on savings being identified and reflected within Directorate Budgets for 2015/16. It is clearly essential that work continues in this area if the forecast budget outturn is to be improved. Following the approval of the revised Sustainable Swansea Delivery Programme, work is underway to develop service delivery plans that will include all savings requirements across Workstreams and Delivery Strands.

2.6The above predicted overspend represents a significant improvement on the forecast year end position as at quarter 1 (£8.056m overspend), but still represents a significant risk to the Council’s finances.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10 (2 of 4): Copy of appendix DAppendix 6 KB Download
PDF
10 (3 of 4): Copy of Appendix EAppendix 8 KB Download
PDF
10 (4 of 4): APPENDIX FAppendix 45 KB Download
PDF
Revenue and Capital Budget Monitoring: 2nd Quarter 2015/16.Report 149 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

8 of 20 attended
RS
Rob StewartLeader of the Council, present
CR
Christine RichardsDeputy Leader of the Council, apologies
MC
Mark ChildCommittee Member, present
WE
William EvansCommittee Member, present
RF
Robert Francis-DaviesCommittee Member, present
JH
Jane HarrisCommittee Member, present
DH
David HopkinsCommittee Member, present
AL
Andrea LewisCommittee Member, apologies
CL
Clive LloydCommittee Member, present
JR
Jennifer RaynorCommittee Member, present
HE
Huw EvansOfficer, in attendance
PF
Patrick FletcherOfficer, expected

All 20 on the meeting page

On this subject at Swansea

Search all
  1. Revenue and Capital Budget Monitoring – 2nd Quarter 2015/16.This decision
  2. Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Noted
  3. Revenue and Capital Budget Monitoring 3rd Quarter 2025/26.Decided
  4. Housing Revenue Account – Capital Budget and Programme 2025/26 – 2029/30.Approved
  5. Revenue and Capital Budget Monitoring 3rd Quarter 2025/26.Noted
  6. Housing Revenue Account – Capital Budget and Programme 2025/26 – 2029/30.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies