New Build for YGG Lon Las - Referral from Cabinet.

Noted Finance 2 papers

Governance & Audit Committee noted this item on Tuesday 22 March 2016. Below is the council's own wording, with the papers it was decided on.

Item72

Resolved

RESOLVED that: - 1) The contents of the report be noted; 2) The Chair / Chief Auditor draft a report summarising the key lessons to be learned, for consideration by the Audit Committee prior to being submitted to Cabinet.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Governance & Audit Committee

Report of the Director of People

Audit Committee - 22 March 2016

NEW BUILD FOR YGG LÔN LAS

Purpose: Cabinet on the 17 September 2015 referred the decisions and plans with regard to the capital programme authorisation for YGG Lôn Las new build project to Audit Committee, this being in the interest that lessons may be learned and adopted within future projects.

Policy Framework:  One Swansea Plan.  The Revenue and Capital Budget as reported to and approved by Council on the 10th February 2015.  QEd 2020 programme.  Sustainable Swansea Programme.  Asset Management Plan.  Corporate Priority – Safeguarding vulnerable young people  Corporate Priority – Improving pupil attainment.  Corporate Priority – Tackling poverty.  Corporate Priority – Building sustainable communities. Reason for Decision: To comply with the Cabinet decision on the 17 September 2015 referring the decisions and plans and authorisation for YGG Lôn Las new build to proceed to Audit Committee, this being in the interest that lessons may be learned and adopted within future projects.

Consultation: Education, Finance, Legal and Democratic Services, Commercial Services, Corporate Building and Property Services.

Recommendations: That; 1. A robust case for the preferred way forward for each scheme is established prior to the submission of the Strategic Outline Programme (SOP). 2. The means of cost planning at SOP development stage is reviewed, to ensure that all foreseeable costs are accounted for and adequate contingency is allowed. 3. All school organisation proposals are completed where possible prior to SOP submission to ensure that proposals are deliverable and within the proposed timescales. 4. The basis of cost estimates in SOP submissions is reviewed with Welsh Government. 5. Provision of an adequate budget and appropriate resource to facilitate business case development at prior to SOP submission is sought.

Report Author: Louise Herbert-Evans

Finance Officer: Jayne James

Legal Officer: Debbie Smith

Access to Services Sherill Hopkins Officer:

1.0Introduction

1.1Cabinet on the 17 September 2015 referred the decisions and plans with regard to the capital programme authorisation for YGG Lôn Las new build project to Audit Committee, this being in the interest that lessons may be learned and adopted within future projects.

2.021st Century Schools Programme process

2.1In December 2011 approval in principle was granted by the Welsh Government to proceed with the Band A projects outlined in the Authority’s Strategic Outline Programme (SOP) which provided an overarching view of the strategy.

2.2This approval was subject to contract and an Authority contribution of 50% towards the overall costs.

2.3SOPs are devised to support the development and agreement of programmes in support of an agreed strategy/ strategies, and secure an overall funding envelope, which in Swansea’s case is £51m for Band A.

2.4It is unrealistic to expect that the values and detail within that programme would remain constant in any event during the lifecycle of that programme.

2.5Authorities are required to provide Welsh Government (WG) with a funding matrix, which sets out the funding profile for the duration of the programme, which in the case of Band A extends from 2011/12 to 2018/19. This matrix is adjusted to reflect the variances in project costs and programming, whilst seeking to maintain the required WG contribution for each year and the overall 50 / 50 split in contributions, so as to avoid the loss of the WG contribution.

2.6All of the business cases for projects forming part of Band A submitted to Welsh Government are therefore underpinned by the Strategic Outline Programme (SOP).

2.7Individual projects can only then be approved subject to receipt of a satisfactory business case.

2.8For projects over £5 million, business cases are submitted in three stages:

Stage one - Strategic Outline Case (SOC); Stage two - Outline Business Case (OBC); and Stage three - Full Business Case (FBC).

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
QEd 2020 Governance v0.2Appendix 2 74 KB Download
PDF
New Build for YGG Lon Las: Referral from Cabinet.Report 153 KB DownloadRead as text

At this meeting

Whole meeting
72New Build for YGG Lon Las - Referral from Cabinet.This decision

Who was there

12 of 17 attended
AM
Alan M ThomasChair, present
CA
Cyril AndersonCommittee Member, present
TH
Terry HenneganCommittee Member, present
BC
Bob ClayCommittee Member, present
PH
Paxton Hood-WilliamsCommittee Member, present
LJ
Lynda JamesCommittee Member, present
JJ
Jeff JonesCommittee Member, present
PM
Paul MearaCommittee Member, apologies
DP
David PhillipsCommittee Member, apologies
RS
Robert SmithCommittee Member, present
CT
Ceinwen ThomasCommittee Member, apologies
LW
Lesley WaltonCommittee Member, present

All 17 on the meeting page

On this subject at Swansea

Search all
  1. New Build for YGG Lon Las - Referral from Cabinet.This decision
  2. Commitment of Capital Funding for the Contractor Appointment and Design Development of the New Build Special School.Approved
  3. Contract Award and Capital Programme Authorisation for the New Build Replacement of YGG Tirdeunaw.Approved
  4. Contract Award and Capital Programme Authorisation for New Build for YGG Tan-y-lan.Approved
  5. Call-In of Cabinet Decision on 21 February 2019 - Item 9 - 21st Century Schools Programme - New Build for Gorseinon Primary School (Report of the Cabinet Member for Education Improvement, Learning and Skills).Agreed
  6. 21st Century Schools Programme - New Build for Gorseinon Primary School.Approved

More from Swansea Governance & Audit Committee

All decisions
MeetingDecisionOutcome
2 Sep 2026 Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. Decided Open
2 Sep 2026 Minutes.Approved. Approved Open
2 Sep 2026 Internal Audit Monitoring Report – Q1 2026/27.Noted. Noted Open
2 Sep 2026 Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. Decided Open
2 Sep 2026 Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. Decided Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies