Swansea Council
Cabinet, Thursday 23 January 2020 at 1.00pm

Contract Award and Capital Programme Authorisation for the New Build Replacement of YGG Tirdeunaw.

Approved Executive 3 papers

Cabinet approved this item on Thursday 23 January 2020. Below is the council's own wording, with the papers it was decided on.

Item131

Resolved

Resolved that: 1) The contract be awarded for the remaining design and construction of a new build for YGG Tirdeunaw on land in the ownership of the Council at Heol Gwyrosydd to Tender No. 2, subject to confirmation of grant and contract with Welsh Government; 2) The capital scheme as detailed in the report together with the financial implications be approved in line with FPR7, subject to confirmation of the grant and contract with Welsh Government.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Education Improvement, Learning and Skills

Special Cabinet – 23 January 2020

Contract Award and Capital Programme Authorisation for the New Build Replacement of YGG Tirdeunaw Purpose:  To approve the scheme for the new build YGG Tirdeunaw subject to confirmation of grant and contract with Welsh Government  To seek authorisation to award the construction contract to Tender Number 2 subject to the confirmation of grant and contract with Welsh Government.  To note the requirement to modify the implementation date to enlarge YGG Tirdeunaw in line with the proposed contractor appointment and updated project timeline, and that a further report will be brought to Cabinet prior to the original January 2021 implementation date, to seek approval to the delay and of the modification to the implementation date.

Policy Framework:  QEd Programme and Strategic Outline Programme for Band B of the 21st Century Schools and Colleges Programme  Asset Management Plan  Contract and Financial Procedure Rules  The Revenue Budget 2019/2020 and the Capital Budget 2018/2019 to 2023/25 approved by Council on 28 February 2019.

Consultation Access to Services, Finance, Legal, Corporate Building Services and Procurement.

Recommendation(s): It is recommended that:

1) Cabinet award the contract for the remaining design and construction of a new build for YGG Tirdeunaw on land in the ownership of the Council at Heol Gwyrosdd to Tender No.2, subject to confirmation of grant and contract with Welsh Government; 2) The capital scheme as detailed together with the financial implications is approved in line with FPR7, subject to confirmation of the grant and contract with Welsh Government.

Report Author: Louise Herbert-Evans

Finance Officer: Ben Smith

Legal Officer: Debbie Smith

Access to Services Officer: Rhian Millar

1. Introduction

1.1The Welsh Government (WG) formally confirmed on the 7 December 2017 that the envelope for Band B of the Council’s 21 st Century Schools and Colleges / QEd Programme was approved in principle with an estimated programme envelope cost of £149.7 million, since amended to £149.5m, to reflect the reciprocal increase in the Band A programme. This is subject to the approval of individual project business cases.

1.2The approval in principle of the Strategic Outline Programme for Band B does not commit the Council, since the final approval of any capital allocation from the WG is subject to the submission of further detailed business cases in respect of each specific project.

1.3Swansea Council’s Quality in Education (QEd) / 21st Century Schools and Colleges Band B Programme focuses on an investment need which reflects the challenges remaining across our schools. The Band B programme remains consistent with local policies, priorities and commitments, as well as the priorities and specific criteria set down by the WG as follows:

 To provide an efficient and effective educational infrastructure that will meet current and future demand for places by 2024  Ensuring the right size schools in the right location, with enough places to deliver Welsh and English medium education, whilst ensuring effective and efficient use of the educational estate  Reducing backlog maintenance costs by at least 50% whilst improving any category C or D condition buildings to A or B

1.4The Council’s 21st Century Schools and Colleges Programme Capital Expenditure & Financing 2018/19 - 2023/24 provides an outline spending profile for the priority projects. Included within this phase of priority projects is an enlarged and relocated school build for YGG Tirdeunaw and a Flying Start setting. 1.5 A joint strategic outline /outline business case (SOC/OBC) was approved by WG in November 2018 and a supplementary Welsh medium capital grant allocation approved in December 2018.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
08 (2 of 3): Appendix 3 EIA TirdeunawAppendix 416 KB Download
PDF
08 (3 of 3): Appendix 4 TirdeunawAppendix 204 KB Download
PDF
Contract Award and Capital Programme Authorisation for the New Build Replacement of YGG Tirdeunaw.Report 592 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 25 attended
AP
Alyson PughCommittee Member, present
MC
Mark ChildCommittee Member, apologies
JD
Jeffrey DongOfficer, expected
HE
Huw EvansOfficer, present
PF
Patrick FletcherOfficer, expected
RF
Robert Francis-DaviesCommittee Member, present
AL
Andrea LewisCommittee Member, present
AH
Adam HillOfficer, present
DH
David HopkinsCommittee Member, present
DH
David HowesOfficer, expected
KJ
Kate JonesOfficer, expected
RJ
Rhodri JonesOfficer, expected

All 25 on the meeting page

On this subject at Swansea

Search all
  1. Contract Award and Capital Programme Authorisation for the New Build Replacement of YGG Tirdeunaw.This decision
  2. Contract Award Report – Contracts for Local Bus Services.Decided
  3. Second Stage (Construction) FPR7 Contract Award and associated Capital Programme Authorisation for the Remodelling and Refurbishment Project at Bishopston Comprehensive School.Approved
  4. Contract Award and Capital Programme Authorisation for the Extension and Remodelling of Ysgol Gyfun Gŵyr.Approved
  5. Contract Award and Capital Programme Authorisation for New Build for YGG Tan-y-lan.Approved
  6. Contract Award Report - Tender for the Provision of Local Bus Services.Decided

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies