RESOLVED that: 1) The capital project with revised costs as detailed together with the financial implications set out in Appendix A of the report be approved, subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government; and 2) The 2 nd Stage Contract for the refurbishment, remodelling and extension works to Pentrehafod School be awarded to Tender No. 1 (Morgan Sindell ) subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Finance & Strategy
Cabinet – 20 October 2016
21st CENTURY SCHOOLS PROGRAMME
CONTRACT AWARD AND CAPITAL PROGRAMME AUTHORISATION FOR THE REMODELLING AND REFURBISHMENT OF PENTREHAFOD SCHOOL’S EXISTING SCHOOL BUILDINGS
Purpose: To approve and commit to the Capital Programme the project with revised costs for the refurbishment of Pentrehafod Comprehensive School subject to confirmation of the grant and entering into a contract with Welsh Government (subject to planning approval). To seek authorisation to award the second stage contract to Morgan Sindall, under the agreement that the contractor must obtain planning approval and all risks associated with not achieving planning approval are those of the contractor, and subject to confirmation of the grant and entering into a contract with Welsh Government (subject to planning approval).
Policy Framework: One Swansea Plan. The Revenue and Capital Budget as reported to and approved by Council on the 25 February 2016 QEd 2020 programme. Corporate Priority – Safeguarding vulnerable young people Corporate Priority – Improving pupil attainment Corporate Priority – Tackling poverty Corporate Priority – Building sustainable communities
Reason for decision: To comply with Financial Procedure Rule No. 7 (Capital Programming and Appraisals) – to commit and authorise a new project onto the Capital Programme. Although this has previously been the subject of a report to Cabinet the revised costs of the project have increased by more than 5% of the current budget.
To comply with Contract Procedure Rule 13, the award of contract. Consultation: Education, Finance, Legal, Corporate Building and Property Services.
Recommendation(s); It is recommended that: (iiii It is recommended that 1) The capital project with revised costs as detailed together with the financial implications set out in Appendix A is approved, subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government and,
2) The 2nd Stage Contract for the refurbishment, remodelling and extension works to Pentrehafod School be awarded to Tender No. 1 (Morgan Sindell) subject to confirmation of the grant and entering into a contract (subject to planning approval) with Welsh Government.
Report Author: Sarah Weir
Finance Officer: Jayne James/Jeff Dong
Legal Officer: Debbie Smith
Access to Services Sherill Hopkins Officer:
1.0Introduction/Background
1.1The Strategic Outline Programme (SOP) detailing the re-organisation and investment need for schools across Swansea was submitted to the Welsh Government (WG) in 2010.
1.2In December 2011, further approval in principle was granted by the WG subject to contract and a local authority contribution of 50% towards the overall costs of the Band A programme.
1.3In line with WG programme requirements, the Capital Budget Programme 2013-2014 to 2019-2020 provides an outline spending profile for priority projects, totalling £51 million. Included within this band of priority projects is the refurbishment and remodelling of Pentrehafod School, with an indicative budget of £12.720 million to be funded by the Council and WG.
1.4WG approval of the Strategic Outline and Outline Business Cases was granted in February 2015.
1.5Two stage tenders were requested from contractors from the SEWSCAP regional framework for the proposed works. Having subsequently been awarded Stage 1, officers worked with the successful contractor, Morgan Sindall Construction & Infrastructure Ltd., to develop the scheme design and negotiate an acceptable cost for the proposed works. This report seeks to award the Stage 2 contract to Morgan Sindall Construction & Infrastructure Ltd
1.6Subject to the successful approval of the full business case which is due to be presented to the WG Capital Panel on the 20 October 2016; the Council will enter into a formal contract with the WG.
2.0Description of works at Pentrehafod School
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
73Contract Award and Capital Programme Authorisation for the Refurbishment of Pentrehafod Comprehensive Schools Existing School Buildings.This decision
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.