Resolved that: 1) The scheme for the extension and remodelling of YG Gŵyr be approved subject to confirmation of grant and contract with Welsh Government; 2) The contract be awarded to Tender No. 2, subject to confirmation of grant and contract with Welsh Government; 3) The capital scheme as detailed in the report together with the financial implications be approved, subject to confirmation of the grant and contract with Welsh Government.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Education Improvement, Learning and Skills
Special Cabinet – 23 January 2020
Contract Award and Capital Programme authorisation for the Extension and Remodelling of Ysgol Gyfun Gŵyr Purpose: To seek approval of the scheme for the extension and remodelling of YG Gŵyr subject to confirmation of grant and contract with Welsh Government. To seek authorisation to award the Contract to Tender no 2 subject to confirmation of grant and contract with Welsh Government. To comply with Financial Procedure Rule No.7 (Capital Programming and Appraisals) to commit and authorise schemes as per the Capital Programme or to include new schemes in the Capital Programme.
Policy Framework: QEd Programme and Strategic Outline Programme for Band B of the 21st Century Schools Programme Asset Management Plan Contract Procedure Rules and Financial Procedure Rules The Revenue Budget 2019/2020 and the Capital Budget 2018/2019 to 2023/25 were approved by Council on 28 February 2019.
Consultation: Access to Services, Finance, Legal, Corporate Building Services and Procurement.
Recommendation(s): It is recommended that:
1) The scheme for the extension and remodelling of YG Gŵyr is approved subject to confirmation of grant and contract with Welsh Government;
2) That Cabinet award the contract to Tender No 2, subject to confirmation of grant and contract with Welsh Government; 3) The capital scheme as detailed together with the financial implications is approved, subject to confirmation of the grant and contract with Welsh Government.
Report Author: Louise Herbert-Evans
Finance Officer: Ben Smith
Legal Officer: Debbie Smith
Access to Services Officer: Rhian Millar
1. Introduction / Background
1.1The Welsh Government (WG) formally confirmed on the 7 December 2017 that the envelope for Band B of the Council’s 21st Century Schools and Colleges / QEd Programme was approved in principle with an estimated programme envelope cost of £149.7 million, since amended to £149.5m, to reflect the reciprocal increase in the Band A programme. This is subject to the approval of individual project business cases.
1.2The approval in principle of the Strategic Outline Programme for Band B does not commit the Council, since the final approval of any capital allocation from the WG is subject to the submission of further detailed business cases in respect of each specific project.
1.3Swansea Council’s Quality in Education (QEd) / 21st Century Schools and Colleges Band B Programme focuses on an investment need which reflects the challenges remaining across our schools. The Band B programme remains consistent with local policies, priorities and commitments, as well as the priorities and specific criteria set down by the WG as follows:
To provide an efficient and effective educational infrastructure that will meet current and future demand for places by 2024 Ensuring the right size schools in the right location, with enough places to deliver Welsh and English medium education, whilst ensuring effective and efficient use of the educational estate Reducing backlog maintenance costs by at least 50% whilst improving any category C or D condition buildings to A or B
1.4Band B of the Council’s 21st Century Schools and Colleges Programme Capital Expenditure & Financing 2018/19 - 2023/24 provides an outline spending profile for the priority projects. Included within this phase of priority projects is an extension and remodelling at Y G Gŵyr as it is projected that by September 2021, there will be insufficient capacity on the current site to meet the demands of pupils transferring from the partner primary schools. 1.5 A joint strategic outline /outline business case (SOC/OBC) was approved by WG in April 2019.
1.6Planning consent for the extension and remodelling was approved on 8 May 2019.
1.7Approval was given under a Delegated Powers Report in March 2018, to commit £242,920 to the capital programme to fund the development of the above project and design fees.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.