Resolved
Resolved that: 1) The proposed capital maintenance schemes listed in Appendix A (to the report) be approved; and 2) The financial implications identified in Appendix B and C (to the report) be included in the capital programme.
Cabinet approved this item on Thursday 15 March 2018. Below is the council's own wording, with the papers it was decided on.
Resolved
Resolved that: 1) The proposed capital maintenance schemes listed in Appendix A (to the report) be approved; and 2) The financial implications identified in Appendix B and C (to the report) be included in the capital programme.
Report of the Cabinet Member for Housing, Energy & Building Services
Cabinet – 15 March 2018
Building Capital Maintenance Programme 2018/19
Purpose: To agree the schemes to be funded through the Capital Maintenance programme
Policy Framework: Revenue and Capital Budget 2018/19
Consultation: Finance, Legal, Access to Services, Education
Recommendation: It is recommended that Cabinet:
1) Approves the proposed capital maintenance schemes as listed in Appendix A.
2) Authorises the financial implications identified in Appendix B & C to be included in the capital programme.
Report Author: Andrew Shaw
Finance Officer: Paul Roach (Revenue) Jayne James (Capital)
Legal Officer: Debbie Smith
Access to Services Officer: Sherill Hopkins
1. Introduction
1.1Cabinet has previously approved the Council’s Asset Management Plan for Property Assets which sets out a series of measures to improve the management and performance of the property portfolio. This Report sets out the way in which the Capital Maintenance resources for 2018/19 will be deployed. 2. Capital Programme Process
On 6th March 2018, Council approved a Capital Maintenance allocation of £4 Million for the financial year 2018/2019, together with an additional £1 Million Capital Maintenance for Schools
3. Objectives of Scheme
3.1The proposals set out will directly support the corporate objectives of the Authority, in relation to the maintenance and improvement of the Authority’s building portfolio.
3.2This maintains the previous commitment to address the significant backlog of maintenance and minimise the potential effect of unforeseen breakdowns of building elements.
3.3As was reported in previous building maintenance programme reports, attention needs to be drawn to the fact that the Authority still has a significant backlog of maintenance and whilst there have been some reductions in this backlog, the limited programme contained within the 2018/19 budget, whilst being very important, will not remedy the immediate backlog.
Notwithstanding the current financial pressures, further budget provisions will therefore need to be made in subsequent years to maintain this investment and minimise the risks of failure and unplanned closures.
3.4The list of identified schemes (Appendix A) has been selected on a priority basis. The criteria for selection (unless otherwise stated) was based upon Condition rating, Legislative compliance, Health and Safety implications, likelihood of failure and business continuity. Whilst all schemes have been selected on these criteria there are a number of similar priorities which we are unable to progress within the budgets available.
4. Description of Schemes
4.1The recommended list of schemes is included in Appendix A and to assist, a brief summary of the planned works have been included as follows:-
1a) Statutory Compliance - Electrical The schemes listed consist of total rewires, partial rewires or upgrades to ensure safety and compliance with electrical regulations and maintained operation of the premises.
1b) Mechanical/Heating Schemes The schemes listed in this section deal with the avoidance of heating failures within our establishments on a prioritised basis.
1c&1d)Statutory Compliance - Legionella and Asbestos As a result of the existing policy to enable compliance with the legionella and asbestos legislation, capital repairs arising out of risk assessments and surveys need to be carried out to maintain compliance. These upgrades are actioned throughout the year and therefore a list of schemes cannot be prepared in advance. Separate revenue monies have been set aside to deal with the ongoing management process and minor repairs.
1e) Statutory Compliance – Radon Further to the Welsh Government’s directive for an awareness programme of RADON in schools, and in line with the “Ionising Radiations regulations 1999”.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
12 (2 of 4): Building Capital Maintanance Programme: Appendix AAppendix | 14 KB | Download |
PDF |
12 (3 of 4): Building Capital Maintenance: Appendix BAppendix | 48 KB | Download |
PDF |
12 (4 of 4): Building Capital Maintenance: Appendix CAppendix | 52 KB | Download |
PDF |
Building Capital Maintenance Programme 2018/19.Report | 149 KB | DownloadRead as text |
Follow Cabinet at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 16 Sep 2026 | Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... | Approved | Open |
| 16 Sep 2026 | Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... | Approved | Open |
| 16 Sep 2026 | Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... | Approved | Open |
| 16 Sep 2026 | Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... | Noted | Open |
| 16 Sep 2026 | Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... | Noted | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.