Resolved that: 1) The proposed allocations, together with the Financial Implications set out Appendix A (to be report), be approved and included in the Capital Programme; and 2) Authority be delegated to the Head of Service for Highways and Transportation in conjunction with the Cabinet Member for Environment to prioritise, finalise and allocate funding to those schemes not specifically referred to in the report.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Environment Services
Cabinet – 15 March 2018
Financial Procedural Rule 7 Capital Allocation to Highway Infrastructure Assets 2018-19 Purpose: To confirm the Capital Work Programme for highway infrastructure assets.
Policy Framework: The Revenue and Capital budget as reported to and approved by Council on 6th March 2018.
Consultation: Access to Services, Finance, Legal.
Recommendation(s): It is recommended that:
1) The proposed allocations, together with the Financial Implications set out in Appendix A, are approved and included in the Capital Programme.
2) Authority is delegated to the Head of Service for Highways and Transportation in conjunction with the Cabinet Member for Environment to prioritise, finalise and allocate funding to those schemes not specifically referred to in this report.
Report Author: Bob Fenwick / Stuart Davies
Finance Officer: Jayne James
Legal Officer: Debbie Smith
Access to Services Officer: Ann Williams
1. Introduction
1.1At its meeting of 6th March 2018, Council approved the Revenue and Capital Budget for 2018/19. The Capital budget included an allocation of £3.375m for highway and infrastructure assets. 1.2 An additional allocation of £1m for 2018/19 has been made for Invest to Save schemes, by undertaking repairs to reduce the level of third party claims against the Authority.
1.3An allocation of £1.4m has been received to help tackle the backlog of highway maintenance based on the evidence in the commissioning report.
1.4In addition to internal funding the Welsh Government has allocated £1,785,804 as a Capital Grant to assist with the backlog of outstanding highway works allocated to 17/18. As the expenditure has to be committed this financial year, this will result in the council substituting completed schemes and “flipping” the funding into 18/19 to carry out a list of projects
2. Main Body of Report
2.1The City and County of Swansea’s infrastructure is in need of significant investment and there is a significant backlog of works. The Authority is continuing to develop programmes of work to the principals agreed at the all Wales Asset Management Project. This will ensure spending is targeted based on a whole life cost approach which will minimise financial and service demands.
2.2The Authority looks at different methods of repair and uses assessment methods agreed across Wales to evaluate the effect on network condition based on a mix of preventative, reactive and planned maintenance works. The highway capital programme 2015-20 was developed with these principals.
2.3Scheme Selection Process The prioritisation for additional schemes will be based on the same asset management approach used to produce the forward works programme. Schemes will be selected based on a review of factors such as network importance, condition, network use and likely deterioration. A score for each assessed road will be calculated and the highest scoring schemes will be programmed. This prioritisation will be balanced by the need to give cost effective packages of work of similar types (for instance surface dressing requires a minimum quantity of work to be cost effective when considering site set up costs). Where schemes are not specifically named due to the need to continue the prioritisation process delegated authority is sort for the Head of service, in conjunction with the cabinet member for environment to finalise the details of the schemes
3. Key Proposals
3.1Investment this year is approximately £7.5m. This includes the £3.375m annual allocation, the additional £1m invest to save allocation and an additional £1.4m internal funding and £1.785m Welsh Government Grant funding in response to the identified backlog of repairs required on Swansea’s roads. It is critical to ensure that investment in the highway network is sustained in future years to minimise future deterioration.
3.2£3.375m Infrastructure allocation.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.