More Homes Development Programme Update.

Noted Executive 2 papers

Cabinet noted this item on Thursday 23 January 2020. Below is the council's own wording, with the papers it was decided on.

Item133

Resolved

Resolved that: 1) The Council sets a target to deliver 1,000 new Council homes via the Housing Revenue Account (HRA), and a further 4,000 affordable homes as part of its ambition to deliver more than 5,000 new affordable homes over the period from 2021 to 2031; 2) In line with Welsh Government grant funding requirements, a 3 year rolling programme of development schemes be produced setting out where the homes will be delivered and it is noted that any changes in the financial assumptions presented in this report will result in an increase or decrease in the number of units that the Council can afford to deliver; 3) Any further decisions relating to the process above will be delegated to the Director of Place and the Cabinet Member for Homes, Energy and Service Transformation, and future development schemes are detailed and approved via the annual HRA Capital Budget report.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Homes, Energy & Service Transformation

Special Cabinet - 23 January 2020

More Homes Development Programme Update Purpose: To set out the Council’s ambition to deliver new affordable homes over 10 years.

Policy Framework: More Homes Strategy, Local Housing Strategy.

Consultation: Access to Services, Finance, Legal.

Recommendation(s): It is recommended that:

1. The Council sets a target to deliver 1000 new Council homes via the Housing Revenue Account (HRA), and a further 4000 affordable homes as part of its ambition to deliver more than 5000 new affordable homes over the period from 2021 to 2031.

2. In line with WG grant funding requirements, a 3 year rolling programme of development schemes is produced setting out where the homes will be delivered and is it noted that any changes in the financial assumptions presented in this report will result in an increase or decrease in the number of units that the Council can afford to deliver.

3. Any further decisions relating to the process above will be delegated to the Director of Place and the Cabinet Members for Homes, Energy and Transformation, and future development schemes are detailed and approved via the annual HRA Capital Budget report.

Report Author: Carol Morgan / Paul Lilley

Finance Officer: Ben Smith

Legal Officer: Lyndsay Thomas

Access to Services Officer: Rhian Millar 1. Introduction

As well as investing just under £500m in improving its existing housing stock to ensure that homes meet the Welsh Housing Quality Standard, 1.1 the Council also has a clear ambition to deliver more affordable housing in Swansea. The More Homes Development Plan, which was agreed by Cabinet in February 2019, sets out short term plans to build 142 new council houses up to 2023. Beyond this, the current Housing Revenue Account (HRA) Business Plan includes an indicative £5m per year from April 2023 which has been set aside to fund new homes.

1.2The Welsh Government (WG) has set a target of delivering 20,000 more affordable homes across Wales during this term. To support this, WG have removed the HRA borrowing cap as additional borrowing is seen as a key factor in achieving their ambition. The removal of cap provides the opportunity to consider increasing borrowing to fund further new Council housing.

1.3In wider terms, there are various mechanisms in place to increase the supply of much needed affordable housing in Swansea. The LDP sets out the provision to deliver a minimum of 3,310 affordable homes over the period of the plan. This is achieved through a variety of mechanisms as follows;  On-site provision of affordable housing to be delivered as part of new developments via Section 106 agreements.  Through Local Needs Housing Exception Sites or Rural Exceptions sites which will deliver over 50% or 100% of affordable housing on these sites.  Bringing empty homes back into use  Acquiring properties to bring back into use as council housing.

1.4Another major delivery route for affordable housing supply is via Registered Social Landlords (RSLs) who are zoned to develop in Swansea. There are 4 RSLs currently operating in Swansea and between them they project to deliver over 4000 new homes over the next 10 years.

1.5Various scenarios have been modelled and it has been concluded that it is feasible to increase the Council housing stock by an additional 1000 properties in the 10 years from April 2021, making a significant contribution to the overall ambition to deliver 5000 new homes. This report sets out the various factors that need to be considered.

2. Affordability within the HRA Business Plan

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
10 (2 of 2): Appendix 1 EIA_screening_form HRA More Homes Development Programme updateAppendix 412 KB Download
PDF
More Homes Development Programme Update.Report 173 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 25 attended
AP
Alyson PughCommittee Member, present
MC
Mark ChildCommittee Member, apologies
JD
Jeffrey DongOfficer, expected
HE
Huw EvansOfficer, present
PF
Patrick FletcherOfficer, expected
RF
Robert Francis-DaviesCommittee Member, present
AL
Andrea LewisCommittee Member, present
AH
Adam HillOfficer, present
DH
David HopkinsCommittee Member, present
DH
David HowesOfficer, expected
KJ
Kate JonesOfficer, expected
RJ
Rhodri JonesOfficer, expected

All 25 on the meeting page

On this subject at Swansea

Search all
  1. More Homes Development Programme Update.This decision
  2. Scrutiny of Cabinet Member Portfolio Responsibilities: More Homes Delivery - Councillor Andrea Lewis, Cabinet Member for Service Transformation.Decided
  3. More Homes Delivery Programme.Noted
  4. More Homes Strategy and Decarbonisation of Existing Housing Stock.Noted
  5. More Homes Parc Yr Helyg Site Options Appraisal.Noted
  6. Pre-decision Scrutiny: More Homes Parc Yr Helyg Site Options Appraisal Report.Decided

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open
16 Sep 2026 Quarter 1 2026/27 Performance Monitoring Report.Resolved that: 1) The Council’s performance in delivering its well-being objectives during Quarter 1 of 2026/27 be no... Noted Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies