Resolved that: 1) The additional capital allocation of £1m for the financial year 2026/2027 to the Changing Rooms Programme be approved as outlined in the report. 2) The additional capital allocation of £1m for the financial year 2025/2026 to the Community Investment Fund Programme be approved as outlined in the report. 3) The continued delegation of authority to the Cabinet Member for Economy, Finance & Strategy, the Cabinet Member for Investment, Regeneration, Events & Tourism and the Director of Place to determine eligibility for each Community Investment Project. In the event of a scheme being submitted in one of the wards of those Cabinet members with delegated authority, the decision would be made instead by the Deputy Leader of the Council and Cabinet Member for Corporate Services and Performance in conjunction with the Director of Place. 4) The £1.835m of previously approved £2m Capital Equalisation Reserve funding for Changing Rooms and Community Investment Fund be carried forward to 2025/2026. With £228k then reprofiled into 2026/2027 for Community Investment Fund. 5) The delegation of authority to the Director of Place or his nominees to progress the schemes as approved in recommendation 3 be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Economy, Finance & Strategy and the Cabinet Member for Investment, Regeneration, Events & Tourism
Cabinet – 15 May 2025
Financial Procedural Rule 7 - Additional Community Investment Capital 2025-2026 and 2026-2027 Purpose: 1. To approve additional capital allocation to the Changing Rooms Programme and the Community Investment Fund Programme.
2. To confirm and delegate authority to Officers to progress approved schemes.
Policy Framework: Community Budget and Council Constitution - Financial Procedure Rule 7.3
Consultation: Access to Services, Finance, Legal.
Recommendation(s): It is recommended that Cabinet:
1) Approves the additional capital allocation of £1m for the financial year 26/27 to the Changing Rooms Programme as outlined in the report.
2) Approves the additional capital allocation of £1m for the financial year 25/26 to the Community Investment Fund Programme as outlined in the report.
3) Approves the continued delegation of authority to the Cabinet Member for Economy, Finance & Strategy, the Cabinet Member for Investment, Regeneration, Events & Tourism and the Director of Place to determine eligibility for each Community Investment Project. In the event of a scheme being submitted in one of the wards of those Cabinet members with delegated authority, the decision would be made instead by the Deputy Leader and Cabinet Member for Corporate Services and Performance in conjunction with the Director of Place.
4) Approves £1.835m of previously approved £2m Capital Equalisation Reserve funding for Changing Rooms and Community Investment Fund is carried forward to 2025/26. With £228k then reprofiled into 2026/27 for Community Investment Fund. 5) Approves the delegation of authority to the Director of Place or his nominees to progress the schemes as approved in recommendation 3.
Report Author: Geoff Bacon Finance Officer: Ben Smith Legal Officer: Debbie Smith Access to Services Officer: Rhian Millar
1. Introduction
1.1In March 2025 the Council Leader confirmed that additional Welsh Government monies be invested into Capital Programmes. This will allow for further budget to be allocated to the existing fund pot of £4m, taking it to £6m in total, this excludes Skate Parks £1m which currently sits with Cultural Services. This report seeks to put into effect sums already approved by Council on 6th March 2025.
March 2024: • £1m Community Investment Fund • £1m Changing Rooms • {£1m Skate Parks (this budget sits in Cultural Services)}
September 2024: • £1m Community Investment Fund • £1m Skate Parks
March 2025: • £1m Community Investment Fund • £1m Changing Rooms
1.2Following the 23/24 ERF monies of £1m which sit with Cultural Services for a Skate and Wheeled Sports facility and in conjunction with the Project Consultants, Curve Studio, a wider Masterplan was created which included options for additional facility improvements and developments across the city.
1.3The revised masterplan, provides options for a multi-layered network of skate and wheeled sports facilities across Swansea, creating a stage for inspirational riding and making it easy for anyone to take up wheeled sports in their community. A further specific capital allocation of £1m from the Contingency Fund to form part of the overall scheme was proposed and approved in September 2024 and sits with Property Services.
*Additional funding to support the programme includes Grants from Active Travel, Community Donations, Councillors Budget and Community investment Fund. Once this funding becomes available for each project it will enable up to an additional £900k to be added to the capital programme, further reports to be submitted to Cabinet in line with grant approval and FPR7 procedures. This brings the total investment to: Investment Amount (£’000) ERF 1,000 RCCO Contingency Fund 1,000 Additional Support* 900 TOTAL 2,900
2. Changing Rooms Programme – Capital Value £1m
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.