Financial Procedural Rule 7 - Additional Capital Allocation to Highway Infrastructure Assets 2026-27.
ApprovedExecutive3 papers
AI summarySwansea Cabinet approves extra capital funding for highways in 2026-27 and delegates allocation to the Head of Highways and Transportation, lifting the highways budget to £14,548k.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedDelegated allocation to Head of Highways and Transportation
Money£14,548k total highways budgetIncludes £2m Welsh Government grant for new schemes
What happens nextHead of Service to finalise allocationsWith Cabinet Member for Environment and Infrastructure agreement
Who it affectsHighways and related infrastructure assetsAcross the 2026-27 and 2027-28 financial years
What was decided
Cabinet approved the indicative allocations and financial implications in Appendix A for inclusion in the Capital Programme. Report P3
Cabinet delegated authority to the Head of Highways and Transportation, with the Cabinet Member for Environment and Infrastructure, to prioritise, finalise and allocate the funding.
Why
The investment helps the Council meet its statutory duty to maintain the highway under Section 41 of the Highways Act 1980. Report P6
It also supports the duty under Section 130 of the same Act to protect the public's right to use and enjoy the highway. Report P6
Additional Welsh Government capital funding has been made available to expand the programme. Report P2
What happens next
The Head of Highways and Transportation will prioritise and allocate funding to schemes using the approach in the report.
Procurement and contracts for the schemes must follow UK legislation and the Council's Contract Procedure Rules. Report P6
Future maintenance costs will be met from the relevant Revenue Service budgets. Report P4
The money
£14,548k Total proposed budget on Highways and other related assets for 2026-27 Report P1
£2m Welsh Government General Capital Grant for additional highways schemes Report P2
£686k Further Welsh Government General Capital Grant, split across two years Report P2
£230k Share of the £686k allocated to 2026-27 Report P2
£456k Share of the £686k allocated to 2027-28 Report P2
Implications
Legal: Helps the Council discharge statutory duties under Sections 41 and 130 of the Highways Act 1980. Report P6
Financial: Future maintenance of the funded schemes will fall to existing Revenue Service budgets. Report P4
Other: Procurement activity must comply with current UK legislation and the Council's Contract Procedure Rules. Report P6
Equalities: An Integrated Impact Assessment Screening Form is provided as Appendix B. Report P7
Who and where
Highway users and the general public, who rely on the Council to maintain the network Report P6
Swansea Council as the local highway authority Report P6
The Highways and Transportation service, which will deliver and maintain the schemes Report P1, P4
Timeline
2026-27: Additional capital programme applied to highways and related assets, taking the total budget to £14,548k Report P1
2026-27: £230k of the £686k Welsh Government grant is drawn down Report P2
2027-28: £456k of the £686k Welsh Government grant is drawn down Report P2
Plain English for the jargon
Financial Procedural Rule 7: The Council's standing rule that governs how additional capital allocations are approved.
Welsh Government General Capital Grant: Capital funding provided by the Welsh Government to the Council for use on eligible schemes.
Highways Act 1980: The Act that sets the Council's duties as a highway authority, including maintaining the highway and protecting public rights of use.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item31
Resolved
Resolved that: 1) The proposed indicative allocations, together with the Financial Implications set out in Appendix A of the report, be approved and included in the Capital Programme. 2) Authority be delegated to the Head of Service for Highways and Transportation with the agreement of the Cabinet Member for Environment and Infrastructure to prioritise, finalise and allocate funding to the appropriate schemes in line with the prioritisation approach detailed in this report.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
Report of the Cabinet Member for Environment and Infrastructure
Cabinet – 25 June 2026
Financial Procedural Rule 7 - Additional Capital Allocation to Highway Infrastructure Assets 2026-27
Executive Summary Purpose of Report: To confirm the additional Capital Work Programme for highway infrastructure assets.
Recommendation(s). It is recommended that: 1) The proposed indicative allocations, together with the Financial Implications set out in Appendix A, are approved and included in the Capital Programme. 2) Authority is delegated to the Head of Service for Highways and Transportation with the agreement of the Cabinet Member for Environment and Infrastructure to prioritise, finalise and allocate funding to the appropriate schemes in line with the prioritisation approach detailed in this report.
Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why Specify the exact paragraphs from the Council Constitution.
Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☐ Tackling Poverty & Enabling Communities ☒ Economy & Infrastructure ☐ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☐ All ☐ Safeguarding ☐ Not Applicable
Relevance to Corporate Plan Wellbeing Objectives: Programme of works to maintain council assets, to defend reputation and meet statutory responsibilities. Reviewed and approved by: Access to Services, Finance, Legal, Cabinet Member.
Report Author & Job Title: Bob Fenwick, Group Leader Highways Maintenance
1. Introduction
At its meeting of 5th March 2026, Council approved the Highways Capital Programme for 2026-27 and investment of £3.468m for highway and infrastructure assets.
2. Additional Capital funding of £3m was approved in 2025-26. This was detailed in a separate FPR7 report but the additional funding is also included below and in the financial summary for completeness.
3. Additional Capital funding of £3m was approved in 2026-27 from the Economic Growth Fund, subject to the 2025-26 outturn position.
4. In addition, the Welsh Government will provide the Council with additional resource funding to enable self-financed borrowing of £7.1m to assist with the backlog of outstanding highway works. Funding to be spent over 2025-27.
5. Approval is sought to allocate a further £2m to extend the Highways resurfacing programme for 2026-27.
6. Approval is also sought for funding to provide a 15% match to a Welsh Government FCERM Grant for the construction of a flood prevention scheme. At total of £686k Is sought over 2026 – 28.
7. Capital Programme
8. The City and County of Swansea’s infrastructure is in need of significant investment and there is a significant backlog of works. The Authority is continuing to develop programmes of work based on the principles agreed as part of the all-Wales Asset Management Project. This will ensure spending is targeted based on a whole life cost approach which will minimise financial and service demands. Works are centred around a 3-year forward works programme (2025-28), with each major asset having a separate published programme. The additional £2m will allow further schemes to be added to the programme and the £686k will unlock £3.874m of grants.
9. Overview
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.