Resolved
Noted.
Governance & Audit Committee noted this item on Wednesday 11 June 2025. Below is the council's own wording, with the papers it was decided on.
Resolved
Noted.
Report of the Director of Corporate Services
Governance and Audit Committee- 11 June 2025
Corporate Risk Overview - Quarter 4 2024-25 Executive Summary Purpose of Report: To present an overview of the status of the Council’s strategic risks and issues at 31 March 2025 to provide assurance to the committee that they are being managed in accordance with the Council’s risk management framework. The report confirms continued effective application of the Council’s Risk Management Framework.
Recommendation. It is recommended that Committee: 1) Notes the status of the Council’s strategic risks and issues at the end of quarter 4 2024-25.
Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☐ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☒ Not Applicable. Information Only Specify the exact paragraphs from the Council Constitution.
Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☐ Tackling Poverty & Enabling Communities ☐ Economy & Infrastructure ☐ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☒ All ☐ Safeguarding ☐ Not Applicable
Relevance to Corporate Plan Wellbeing Objectives:
Managing strategic risks is integral to delivering the Council’s Corporate Plan 2023–2028 and achieving its Well-being Objectives. The risks in this report reflect key challenges across all objectives, including education, poverty, economy, climate, transformation, and safeguarding.
Through the Corporate Risk Management Framework, these risks are identified, monitored, and managed to support informed decision-making, protect service delivery, and contribute to long-term outcomes for residents and communities. Reviewed and approved by: Access to Services Finance Legal
Report Author & Job Title: Suzy Richards, Sustainable Policy Officer
1. Introduction
2. This report provides an overview of the status of the Council’s strategic risks and issues as at 31 March 2025 to give assurance that these are being managed effectively in line with the council’s framework and policy.
3. Advice
4. Risk and Issue Management Process
5. The Council’s Corporate Risk Management Framework sets out how risks and issues are identified, assessed, and managed to support delivery of corporate objectives.
6. Risks are potential events that could impact the Council’s priorities. They are assessed for likelihood and impact, with control measures applied to reduce exposure. Each risk has an inherent score (before controls), a residual score (after controls), and a target score aligned to the Council’s risk appetite. Risks are classified as Strategic, Operational, or Project level and are reviewed regularly at Directorate and Corporate levels.
7. Issues are events that are already happening or are imminent, requiring active resolution. Strategic Issues are prioritised based on urgency and impact, with action plans assigned, tracked, and monitored by the Corporate Management Team. Operational Issues are managed within services.
8. Both risks and issues are monitored through established governance processes, ensuring they are addressed promptly and in line with Council priorities.
9. Risk and Issue status at the end of Q4 2024/25
10. The Council’s Risk and Issue Registers recorded a total of 103 entries as at 31 March 2025 (95 Risks and 8 issues). This includes 18 Strategic Risks and 7 Strategic Issues.
11. The current status of these Strategic Risks and Issues is summarised in this report, with detailed records presented in Appendix A. Two Strategic Risks are exempt from publication and are summarised in a separate report for the Committee.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
13 (2 of 3): Appendix A: Risk Report Q4 2024-25 v5Appendix | 16 MB | Download |
PDF |
13 (3 of 3): Appendix B: IIAAppendix | 187 KB | Download |
PDF |
Corporate Risk Overview: Quarter 4 2024/25.Report | 151 KB | DownloadRead as text |
Follow Governance & Audit Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. | Decided | Open |
| 2 Sep 2026 | Minutes.Approved. | Approved | Open |
| 2 Sep 2026 | Internal Audit Monitoring Report – Q1 2026/27.Noted. | Noted | Open |
| 2 Sep 2026 | Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. | Decided | Open |
| 2 Sep 2026 | Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.