Resolved
Noted.
AI summarySwansea Council's Governance and Audit Committee noted the Quarter 4 2025-26 corporate risk overview, which lists strategic risks and issues in an appendix.
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Resolved
Noted.
Report of the Director of Corporate Services
Governance and Audit Committee – 3rd June 2026
Corporate Risk Overview – Quarter 4 2025-26 Executive Summary Purpose of Report: To present an overview of the status of the Council’s strategic risks and issues of 31 March 2026 to provide assurance to the committee that they are being managed in accordance with the Council’s risk management framework. The report confirms continued effective application of the Council’s Risk Management Framework.
Recommendation(s). It is recommended that: 1) Notes the status of the Council’s strategic risks and issues as of the end of quarter 4 2025-26
Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☐ Financial Procedure Rules ☒ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why
Constitution Part 3.1
Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☐ Tackling Poverty & Enabling Communities ☐ Economy & Infrastructure ☐ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☒ All ☐ Safeguarding ☐ Not Applicable
Relevance to Corporate Plan Wellbeing Objectives: Managing strategic risks is integral to delivering the Council’s Corporate Plan 2023-2028 and achieving its Well-being Objectives. The risks in this report reflect key challenges across all objectives, including education, poverty, economy, climate, transformation, and safeguarding. Through the Corporate Risk Management Framework, these risks are identified, monitored, and managed to support informed decision-making, protect service delivery, and contribute to long- term outcomes for residents and communities. Reviewed and approved by: Access to Services, Finance, Legal, Cabinet Member
Report Author & Job Title: Rhian Millar, Strategy Development Team Leader
1. Introduction
2. This report provides an overview of the status of the Council’s Strategic Risks and Issues as of 31 March 2026, to provide assurance that these are being managed in line with the Council’s Risk Management Framework and policy.
3. Advice
4. Risk and Issue Management Process
5. The Council’s Corporate Risk Management Framework outlines how risks and issues are identified, assessed, and managed to support delivery of corporate objectives.
6. Risks are potential future events that may adversely affect the Council’s ability to deliver its priorities. They are assessed for likelihood and impact, with control measures applied to reduce exposure. Each risk is assigned an inherent score (before controls), a residual score (after controls), and a target score aligned to the Council’s risk appetite. Risks are categorised as:
a. Strategic Risks – those that could affect the whole Council or prevent achievement of corporate objectives or legal obligations. b. Operational Risks – those that may disrupt individual services or functions but do not threaten the Council’s overall objectives. c. Project Risks – those specific to the delivery of defined projects or programmes.
7. Issues, by contrast, are events that are already occurring or are imminent and require active resolution. Strategic Issues are prioritised based on urgency and impact and are managed through the Issue and Risk Register, which is tracked and regularly monitored. Operational Issues are managed locally by Heads of Service as part of day-to-day service delivery.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
13 (2 of 2): Appendix A Strategic Risks and Issues Q4 2025-26: Open sessionAppendix | 783 KB | Download |
PDF |
Corporate Risk Overview: Quarter 4 2025-26.Report | 155 KB | DownloadRead as text |
Follow Governance & Audit Committee at Swansea and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 2 Sep 2026 | Disclosures of Personal and Prejudicial Interests.Councillors M White & P Bentu declared personal interests in item 9. | Decided | Open |
| 2 Sep 2026 | Minutes.Approved. | Approved | Open |
| 2 Sep 2026 | Internal Audit Monitoring Report – Q1 2026/27.Noted. | Noted | Open |
| 2 Sep 2026 | Governance & Audit Committee - Self-Assessment of Good Practice 2025-2026.Withdrawn. | Decided | Open |
| 2 Sep 2026 | Successful and Sustainable Swansea Corporate Transformation Plan Annual Report 2025-26.For information. | Decided | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.