Capital Allocation to Highway Infrastructure Assets 2026-27.

Approved Executive 3 papers

AI summarySwansea Council Cabinet approves indicative allocations of up to £12.318m for 2026/27 highway infrastructure works, with delegated authority to finalise scheme priorities.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAuthority delegated to prioritise and allocate funding
Moneyup to £12.318mEstimated cost of 2026/27 highways programme
What happens nextHead of Service to finalise allocationsWith Cabinet Member for Environment and Infrastructure agreement
Who it affectsHighway users and the CouncilAs highway authority, across the 2026/27 programme

What was decided

The proposed indicative allocations and Financial Implications in Appendix A were approved and included in the Capital Programme.

Authority was delegated to the Head of Service for Highways and Transportation, with the Cabinet Member for Environment and Infrastructure's agreement, to prioritise, finalise and allocate funding to schemes.

Why

The investment helps the Council meet its statutory duty to maintain the highway under Section 41 of the Highways Act 1980 and its duty to protect public rights under Section 130. Report P8

The programme is funded from Welsh Government General Capital Grant, prior-approved insurance reserve funding, Welsh Government LGBI funding, and a requested sum from the Economic Growth Fund. Report P2, P3, P4, P5

All procurement and contracts must comply with current UK Legislation and the Council's Contract Procedure Rules. Report P8

What happens next

Future maintenance expenditure will be met from respective Revenue Service budgets. Report P6

An additional sum of up to £3m for 2026-27 is requested from the Economic Growth Fund, subject to funds being available and dependent on 2025-26 outturn. Report P5

Schemes will be prioritised and finalised by the Head of Service under delegated authority, in line with the approach set out in the report.

The money

  • up to £12.318m Estimated total cost of the 2026/27 Highways and Other Infrastructure works programme Report P1
  • £3.468m Welsh Government General Capital Grant Report P3
  • £3m Prior approved additional funding from the insurance reserve (RCCO) Report P3
  • £7.1m Welsh Government LGBI Funding, split £4.250m in 2025/26 and £2.850m in 2026/27 Report P4
  • up to £3m Requested from the Economic Growth Fund for 2026-27, subject to availability and 2025-26 outturn Report P5

Implications

  • Legal: Investment supports the Council's statutory duties under Sections 41 and 130 of the Highways Act 1980 as a highway authority. Report P8
  • Legal: Procurement and contracts must comply with current UK Legislation and the Council's Contract Procedure Rules. Report P8
  • Financial: Future revenue maintenance will be met from respective Revenue Service budgets. Report P6
  • Financial: Up to £3m from the Economic Growth Fund for 2026-27 is subject to funds being available and dependent on 2025-26 outturn. Report P5

Who and where

  • Highway users across the Council's road network Report P8
  • The Council as highway authority Report P8

Timeline

  • 2026/27: Main programme of Highways and Other Infrastructure works to be delivered Report P1
  • 2025/26: Welsh Government LGBI funding of £4.250m allocated in this year Report P4
  • 2026/27: Welsh Government LGBI funding of £2.850m allocated in this year Report P4
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item155

Resolved

Resolved that: 1) The proposed indicative allocations, together with the Financial Implications set out in Appendix A, be approved and included in the Capital Programme. 2) Authority be delegated to the Head of Service for Highways and Transportation with the agreement of the Cabinet Member for Environment and Infrastructure to prioritise, finalise and allocate funding to the appropriate schemes in line with the prioritisation approach detailed in this report.
Word for word from the decision Swansea published for this meeting. Source: democracy.swansea.gov.uk

Follow this further

Built from Swansea's papers

What the report saysPro

Report to Cabinet

Report of the Cabinet Member for Environment and Infrastructure

Cabinet - 19 March 2026

Capital Allocation to Highway Infrastructure Assets 2026-27 Executive Summary Purpose of Report: To confirm the Capital Work Programme for highway infrastructure assets.

Recommendation(s). It is recommended that: 1) The proposed indicative allocations, together with the Financial Implications set out in Appendix A, are approved and included in the Capital Programme. 2) Authority is delegated to the Head of Service for Highways and Transportation with the agreement of the Cabinet Member for Environment and Infrastructure to prioritise, finalise and allocate funding to the appropriate schemes in line with the prioritisation approach detailed in this report.

Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why Specify the exact paragraphs from the Council Constitution.

Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☐ Tackling Poverty & Enabling Communities ☒ Economy & Infrastructure ☐ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☐ All ☐ Safeguarding ☐ Not Applicable

Relevance to Corporate Plan Wellbeing Objectives: Programme of works to maintain council assets, to defend reputation and meet statutory responsibilities.

Reviewed and approved by: Access to Services, Finance, Legal & Cabinet Member. Report Author & Job Title: Bob Fenwick Group Leader Highways Maintenance

1. Introduction

At its meeting of 5th March 2026, Council will consider the Revenue and Capital Budget for 2026/27. The Capital budget in this report assumes that the report is approved and the core allocation remains the same as 2025/26, an allocation of £3.468m for highway and infrastructure assets.

2. It should be noted that additional Capital funding of £3m was approved in 2025/26 (to be programmed over 2 years). This was detailed in a separate FPR7 report but the additional funding is also included below and in the financial summary for completeness.

3. In addition, this report is seeking to request up to a further £3m allocation for 2026-27 from the Economic Growth Fund, which is subject to the 2025-26 outturn position.

4. In addition, the Welsh Government will provide the Council with additional resource funding to enable self-financed borrowing of £7.1m to assist with the backlog of outstanding highway works. Funding to be spent over 2025 to 2027.

5. Retrospective approval is also sought for a £300k Capital funding (RCCO) for 2025/26 end of year emergency carriageways works programme

6. Capital Programme

The City and County of Swansea’s infrastructure is in need of significant investment and there is a significant backlog of works. The Authority is continuing to develop programmes of work based on the principles agreed as part of the all-Wales Asset Management Project. This will ensure spending is targeted based on a whole life cost approach which will minimise financial and service demands. Works are centred around a 3-year forward works programme (2025-28), with each major asset having a separate published programme.

7. Funding will be split between the different asset groups based in the main on total asset values, together with factors such as liability and exceptional demand. Carriageways will receive the largest allocation due to the value but also the risk of liability for claims and managing reputational impact.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
11: Appendix A: Highways Capital Report FPR 7 AMMENDEDAppendix 96 KB Download
PDF
11: Appendix B: IIA: FPR7 Highways CapitalAppendix 133 KB Download
PDF
Capital Allocation to Highway Infrastructure Assets 2026-27.Report 164 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

16 of 28 attended
CA
Cyril AndersonCommittee Member, present, as expected, virtual
AA
Alyson AnthonyCommittee Member, apologies
JD
Jeffrey DongOfficer, expected
HE
Huw EvansOfficer, present
PF
Patrick FletcherOfficer, expected
RF
Rebecca FogartyCommittee Member, present, as expected, virtual
LG
Louise GibbardCommittee Member, present
HG
Hayley GwilliamCommittee Member, present, as expected, virtual
AH
Andrea HarringtonCommittee Member, present
DH
David HopkinsCommittee Member, present
DH
David HowesOfficer, expected
RJ
Rhodri JonesOfficer, expected

All 28 on the meeting page

On this subject at Swansea

Search all
  1. Capital Allocation to Highway Infrastructure Assets 2026-27.This decision
  2. Financial Procedural Rule 7 - Additional Capital Allocation to Highway Infrastructure Assets 2026-27.Approved
  3. Financial Procedure Rule 7 – Capital Allocation to Highway Infrastructure Assets 2025-26.Approved
  4. Financial Procedure Rule 7 - Additional Capital Allocation to Highway Infrastructure Assets 2024-25.Approved
  5. Additional Capital Allocation to Highway Infrastructure Assets 2024-25.Approved
  6. Capital Allocation to Highway Infrastructure Assets 2024-25.Approved

More from Swansea Cabinet

All decisions
MeetingDecisionOutcome
16 Sep 2026 Minutes.Resolved that the Minutes of the meeting(s) listed below be approved and signed as a correct record: 1) Cabinet held ... Approved Open
16 Sep 2026 Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new... Approved Open
16 Sep 2026 Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ... Approved Open
16 Sep 2026 Revenue and Capital Budget Monitoring 1st Quarter 2026/27.Resolved that: 1) The comments and variations, including the heightened material uncertainties, set out in the report... Noted Open