FPR7 Redevelopment of 277-278 Oxford Street - Y Storfa.
ApprovedExecutive2 papers
AI summarySwansea Cabinet approved final funding for the Y Storfa redevelopment on Oxford Street, releasing an £811,000 underspend to the capital programme contingency.
Written from the decision and the officer reportPDF Pro
OutcomeApprovedFinal accounts and reallocation agreed for Y Storfa
Money£2m, £3.081m and £811,000Extra grant and contingency reallocation
What happens nextUnderspend to capital contingency£811,000 returned for other priority schemes
Who it affectsY Storfa, Oxford StreetFinal accounts closed; Council capital programme
What was decided
Cabinet approved an extra £2 million from the Welsh Government Transforming Towns programme for the Y Storfa project. Report P3
Cabinet approved the allocation of £3.081 million from the UK Government Shared Prosperity Fund to replace existing capital budget provision. Report P4
Cabinet approved returning the £811,000 underspend on Y Storfa to the Capital Programme Contingency, subject to residual funding terms. Report P11
Why
The total project cost of £28,219,000 has been fully delivered within the approved funding envelope, with total finance of £29,030,000. Report P8, P10
Construction costs rose to a final account of up to £21,742,378, £3,139,701 above the value-engineered sum, but the increase was offset by earlier value engineering savings and additional external grants. Report P7
The scheme has been funded through a blended model of external grants, Council capital, prudential borrowing and a partner contribution, with 38.74% from external grants. Report P12
What happens next
Final payments including Kier's retention and remaining fit-out costs will be settled, with £100,000 retained within the budget for any residual design costs. Report P11
The £811,000 underspend will be reallocated to the Capital Programme Contingency to support existing or future priority schemes. Report P11
The money
£2,000,000 Additional Welsh Government Transforming Towns grant Report P3
£3,081,000 UK Government Shared Prosperity Fund allocation Report P4
£811,000 Underspend reintroduced to Capital Programme Contingency Report P11
£26,400,000 Total scheme budget originally approved by Cabinet in July 2023 Report P1
£28,219,000 Total project cost for Y Storfa Report P10
£21,742,378 Maximum final account for construction works Report P7
£18,602,677 Value-engineered construction contract sum Report P7
£7,500,000 Total Welsh Government Transforming Towns contribution Report P3, P10
£6,000,000 Welsh Government Town Centre Loan (CCS Borrowing) Report P5, P10
£346,000 Welsh Government Y Storfa Relocation Grant (including £35k RCCO match funding) Report P10
£311,000 Welsh Government Library Transformation Programme grant Report P5
£295,000 Capital receipt from Housing Options Office disposal (originally estimated £200,000) Report P6, P10
£4,626,000 USB (Usable capital receipts) funding Report P10
£27,521,949.57 Amount recorded on the project ledger to date Report P11
£911,000 Current forecast underspend on Y Storfa Report P11
Options considered
Chosen: Allocate the £2m additional Welsh Government Transforming Towns grant to Y Storfa. Increase total Welsh Government contribution to £7.5m and help mitigate construction cost escalation Report P3
Chosen: Use £3.081m UK Shared Prosperity Fund to offset and replace existing capital budget. Reflect approved funding substitution and reallocation with the Bascule Bridge project Report P4
Chosen: Return the £811,000 underspend to the Capital Programme Contingency. To support existing or future priority capital schemes, subject to residual funding terms Report P11
Implications
Financial: Y Storfa scheme has been delivered within its total approved funding envelope of £28,219,000, with £811,000 freed up for the wider capital programme. Report P8, P10, P11
Financial: The Council's exposure to construction cost rises was mitigated through value engineering and securing additional external grants rather than extra Council borrowing. Report P2, P7
Legal: Officers report no legal or governance implications arising from this report other than those identified within it. Report P14
Who and where
Y Storfa building and users on Oxford Street, Swansea Report P1, P6
Swansea Council's Capital Programme, including future priority schemes drawing on the contingency Report P11
Welsh Government (Transforming Towns, Town Centre Loan, Library Transformation) and UK Government (Shared Prosperity Fund) as funders Report P3, P4, P5
External delivery partner (Kier) in respect of retention payments Report P11
Timeline
July 2023: Cabinet approved the original £26.4 million total scheme budget for Y Storfa. Report P1
2025/26 financial year: Additional £2 million Welsh Government Transforming Towns grant secured. Report P3
16 October 2025: Previous Cabinet reports FPR7 considered the Transforming Towns grant and the Shared Prosperity Fund reallocation including the Bascule Bridge project. Report P3, P4
16 July 2026: Current Cabinet decision: approves the £2m, £3.081m and £811,000 reallocations and closes the scheme's final accounts.
Plain English for the jargon
Y Storfa: The redeveloped building at 277-278 Oxford Street delivering Council services including the relocated Housing Options and library functions.
Transforming Towns Programme: A Welsh Government grant programme supporting town centre regeneration.
Shared Prosperity Fund: A UK Government capital funding programme replacing earlier EU structural funds.
RCCO: Revenue Contributions to Capital Outlay, Council revenue funding transferred to support capital spend.
USB: Usable capital receipts, Council receipts from asset sales available to fund capital projects.
CCS Borrowing (Town Centre Loan): Welsh Government loan to the City and County of Swansea for town centre investment, treated as prudential borrowing in the accounts.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item40
Resolved
Resolved that: 1) The allocation of a further £2 million in grant funding secured through the Welsh Government Transforming Towns programme, as set out in the Cabinet Report FPR7 for the WG Transforming Towns Programme on 16 October 2025 be approved. 2) The allocation of £3.081 million in grant funding, secured through the UK Government’s Shared Prosperity Fund, as detailed in the Cabinet Report FPR7 for the Shared Prosperity Fund Capital Projects on 16 October 2026, to offset and replace the existing capital budget provision be approved. 3) The reintroduction of the identified underspend of £811,000 into the Capital Programme Contingency, to support ongoing and future project delivery, subject to the terms and conditions of residual funding be approved.
Word for word from the decision Swansea published for this meeting.Source: democracy.swansea.gov.uk
FPR7 Redevelopment of 277-278 Oxford Street – Y Storfa
Executive Summary Purpose of Report:
To ensure compliance with Financial Procedure Rule No. 7 (Capital Programming and Appraisals) by providing Cabinet with a formal update on the final position and completion of the Y Storfa project.
Recommendation(s). It is recommended that Cabinet: 1) Approve the allocation of a further £2 million in grant funding secured through the Welsh Government Transforming Towns programme, as set out in the Cabinet Report FPR7 for the WG Transforming Towns Programme on 16th October 2025.
2) Approve the allocation of £3.081 million in grant funding, secured through the UK Government’s Shared Prosperity Fund, as detailed in the Cabinet Report FPR7 for the Shared Prosperity Fund Capital Projects on 16th October 2026, to offset and replace the existing capital budget provision.
3) Approve the reintroduction of the identified underspend of £811,000 into the Capital Programme Contingency, to support ongoing and future project delivery, subject to the terms and conditions of residual funding.
Decision-Making Authority www.swansea.gov.uk/constitution: Select from the list the constitutional basis www.swansea.gov.uk/constitution on which a decision is being sought (Please tick all that apply): ☐ Article 4 “The Council Meeting” ☒ Financial Procedure Rules ☐ Scheme of Delegation ☐ Land Transaction Procedure Rules ☐ Terms of Reference ☐ Other “Please Specify” ☐ Contract Procedure Rules ☐ Not Applicable. Explain Why Specify the exact paragraphs from the Council Constitution.
Corporate Plan Wellbeing Objectives: Select which Wellbeing Objectives are relevant to this report (Please tick all that apply): https://www.swansea.gov.uk/corporateimprovementplan ☐ Education & Skills ☐ Tackling Poverty & Enabling Communities ☐ Economy & Infrastructure ☐ Transformation & Financial Resilience ☐ Nature Recovery & Climate Change ☐ All ☐ Safeguarding ☒ Not Applicable Relevance to Corporate Plan Wellbeing Objectives:
This report does not introduce any new proposals or decisions that directly impact the delivery of Corporate Plan Wellbeing Objectives. Instead, it provides an update on the completion of an existing approved project, the outcomes of which have already contributed to the Council’s wellbeing objectives as set out in previous reports.
Reviewed and approved by: Access to Services, Finance, Legal & Cabinet Member.
Report Author & Job Title: Geoff Bacon – Head of Property & Regeneration
1. Introduction
2. The Y Storfa project was initially presented to Cabinet in December 2020, at which time approval was granted for the acquisition of 277–278 Oxford Street (formerly the BHS building), alongside the proposed redevelopment of the site and its associated financial implications. A further report was presented to Cabinet in December 2021 seeking approval for the acquisition of 279 Oxford Street (formerly the [name removed] building) to be incorporated into the scheme, together with revised financial implications and an update on project progress.
3. The most recent report to Cabinet, in July 2023, provided a comprehensive update on the project background and highlighted the challenges encountered in delivering a complex retrofit scheme, including cost escalation and programme delays.
4. In light of the detailed update previously provided, this report does not seek to repeat earlier information. Instead, it provides an update on the final position following completion of the scheme, including the successful opening of the building in December 2025.
5. A summary of headline project milestones is provided below for context:
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Public Space Protection Order Scheme. *Resolved that: 1) The findings of the Public Spaces Protection Order Review be approved. 2) The introduction of a new...
Local Authority Governor Appointments.Resolved that: 1) The following nominations recommended by the Director of Education in conjunction with the Cabinet ...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.