Cabinet, Wednesday 5 September 2012

Capital Programme Monitoring - 1st Quarter 2012/13

Noted Executive 3 papers

Cabinet noted this item on Wednesday 5 September 2012. Below is the council's own wording, with the papers it was decided on.

Item38

Resolved

Resolved – (1) That the projected Capital Out-turn position of the Capital Programme for 2012/13, as set out in the joint report, be noted. (2) That the changes to Capital Programme schemes, as set out in paragraphs 4.2 to 4.8 of the joint report, be approved. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: GP)
Word for word from the decision Swindon published for this meeting. Source: ww5.swindon.gov.uk

Follow this further

Built from Swindon's papers

What the report saysPro

Report to Cabinet, 6 pages

Capital Programme Monitoring 1st Quarter 12/13

Cabinet Date: 5th September 2012

Author: Cabinet Member for Finance Board Director of Finance, Revenues, Benefits and Property Wards: All Locality Affected: All Parishes Affected: All

1. Purpose and Reasons 1.1 This report sets out the 2012/13 Capital Programme position as at the end of June 2012. 2. Recommendations Cabinet is recommended to: 2.1 Note the 2012/13 Capital Programme position 2.2 Approve the changes to the Capital Programme detailed at paragraph 4.2 – 4.8 3. Detail Capital Programme 2012/13 3.1 Table 1 below provides a summary of the forecast out-turn position by group compared with the approved total scheme budgets as at the end of July 2012. 3.2 Table 2 provides a summary of current spend against each budget forecast, providing expenditure in 12/13 (April 12 to June 12) as well as previous years spend to provide a total spend to date figure over all years. Appendix 1 provides a full scheme by scheme breakdown of these figures. 3.3 This is a change in the format of the data provided to Cabinet previously in that the Approved Budget column represents the Total Scheme Budget rather than focusing solely on the element of the budget expected to be spent in year. 3.4 Projects have been grouped within the headings previously reported as whilst they do not reflect the new Stronger Together structure, it appears to be the most meaningful presentation.

Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 1st Quarter 12/13

Cabinet Date: 5th September 2012

Table 1 – Budget Forecasts and variances

Approved Budget Group Budget Forecast Variance £’000’s £’000’s £’000’s Adult Social Care 3,798 3,798 - Business Transformation 50,315 50,264 (51) Children’s Services 27,139 27,139 - Environment & Regeneration & 67,028 66,819 (209) Communities (E,R&C) Housing Revenue Account (HRA) 15,312 15,312 - Leisure Libraries & Culture 1,691 1,691 - S106 funded schemes 18,563 18,605 42 Service Totals 183,846 183,628 (218)

Table 2 – Expenditure to date

Total Budget Spend to 12/13 Spend to Group Forecast 31.3.12 Spend June 12 £’000’s £’000’s £’000’s £’000’s Adult Social Care 3,798 2,785 (59) 2,726 Business Transformation 50,264 36,389 508 36,897 27,139 7,814 345 8,159 Children’s Services Environment & Regeneration & 66,819 21,875 (1,709) 20,166 Communities (E,R&C) Housing Revenue Account (HRA) 15,312 0 92 92 Leisure Libraries & Culture 1,691 209 1 210 S106 funded schemes 18,605 3,394 164 3,558 Service Totals 183,628 72,466 (658) 71,808

3.5The underspend shown against Business Transformation in table 1 relates to the buildings element of the Localities project. 3.6 The net ER&C budget forecast underspend of £209k relates to a combination of: 3.6.1 forecast overspends totalling £99k on the following projects:

Further information on the subject of this report can be obtained from Paul Smith on Direct Dial No.463976, or Email [email protected]. Capital Programme Monitoring 1st Quarter 12/13

Cabinet Date: 5th September 2012

• £21k overspend on the CCTV Recreation sites project • £56k overspend relating to ITSO bus migration grant • £22k relating to Pinetrees Community Centre 3.6.2 and forecast underspends totalling £308k on the following projects:

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Capital Programme Scheme DetailAppendix 1 7 pages Download
PDF
ContingenciesAppendix 2 1 pages Download
PDF
Capital Programme Monitoring: 1st Quarter 2012/13Report 6 pages DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 12 attended
RB
Councillor Roderick Bluh Leader of the Council, Chair of CabinetChair, present
DR
Councillor David Renard Deputy Leader, Vice-Chair and Cabinet Member for Children's ServicesVice-Chair, present
ME
Councillor Mark Edwards Cabinet Member for FinanceMember, apologies
FF
Councillor Fionuala Foley CLMember, present
DH
Councillor Dale Heenan Cabinet Member for Strategic Planning and SustainabilityMember, present
RH
Councillor Russell Holland Cabinet Member for One Swindon, Localities and HousingMember, present
BM
Councillor Brian Mattock Cabinet Member for Health and Adult Social CareMember, present
GP
Councillor Garry Perkins Cabinet Member for Regeneration and CultureMember, present
VT
Councillor Vera Tomlinson Cabinet Member for a Safer, Stronger BoroughMember, present
KW
Councillor Keith Williams Cabinet Member for Leisure and Strategic TransportMember, present
JG
Councillor Jim GrantCabinet Member attendee, in attendance
SW
Councillor Steve WakefieldCabinet Member attendee, in attendance

On this subject at Swindon

Search all
  1. Capital Programme Monitoring - 1st Quarter 2012/13This decision
  2. Capital Programme 2026/2027 (Minute for Confirmation)Approved
  3. Capital Programme 2025-2026Approved
  4. Capital Programme 2024/2025 (Minute for Confirmation)Approved
  5. Capital programme 2023-24 (Minute for Confirmation)Approved
  6. Capital Programme to 2026/27 (Minute for Confirmation)Approved

More from Swindon Cabinet

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Management UpdateNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the Council’s ... Noted Open
8 Oct 2026 Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend... Noted Open
8 Oct 2026 Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a... Approved Open
8 Oct 2026 CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad... Noted Open
8 Oct 2026 Housing Policy ReviewNon-Key Decision Following consideration of the report and its appendices, Cabinet resolved that the nine housing pol... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies