Resolved – (1) That the key findings resulting from research and analysis undertaken over the previous 6 months into the implications of the creation of a “Swindon Partnership Framework Agreement” for tendering non-housing related building construction and refurbishment projects, be noted. (2) That the Head of Commercial Services, in consultation with the Cabinet Member for Finance, the Director of Law and Democratic Services, and the Head of Design and Architecture, be authorised to continue tendering for the delivery of non-housing related building construction and refurbishment projects on the basis as set out in paragraph 3.6 of the joint report. The reasons for the decision and alternative options are as set out in the report to the meeting. (CM: FF)
Word for word from the decision Swindon published for this meeting.Source: ww5.swindon.gov.uk
Capital Building Projects – Partnership Framework Agreements Cabinet Date: 5th September 2012
Author: Cabinet Member for Regeneration and Culture; Cabinet Member for Finance Board Director Commissioning Wards: All Locality Affected: All Parishes Affected: All
1. Purpose and Reasons 1.1 To seek the Cabinet’s approval to review the decision to create a ‘Swindon Partnership’ framework agreement for tendering non-housing related building construction and refurbishment projects, as referred to in the Strategic Commissioning Review report presented to Cabinet on 19th October 2011 (Minute .53, 2011/12 refers). 1.2 The October 2011 report set out the process recommended to be undertaken when tendering non-housing related building construction and refurbishment projects below the EU threshold of £4.3M to best achieve the Cabinet’s ambitions to; i. Stimulate and support a vibrant Local economy ii. Create opportunities for employment iii. Open up ‘non – housing’ related construction projects to market competition 2. Recommendations Cabinet is recommended to: 2.1 Note the key findings resulting from research and analysis undertaken over the previous 6 months. 2.2 Authorise the Head of Commercial Services, in consultation with the Cabinet Member for Finance, the Director of Law and Democratic Services, and the Head of Design and Architecture, to continue tendering for the delivery of non-housing related building construction and refurbishment projects on the basis as set out in paragraph 3.6.
Further information on the subject of this report can be obtained from Sue Mendham, [phone removed], [email protected]. Capital Building Projects – Partnership Framework Agreements Cabinet Date: 5th September 2012
3. Detail 3.1 The recommendation to review the creation of a framework agreement for non- housing related building construction and refurbishment projects at this time is based upon a number of factors set out below. 3.2 Officers are actively exploring opportunities for how social value and the wellbeing of an area can be considered and developed when tendering as a result of the Public Services (Social Value) Act 2012 and the Localism Act 2011. 3.3 The capital works programme for non-housing related building construction and refurbishment projects has significantly reduced and there is currently little synergy to be gained through aggregation in single frameworks. 3.4 Current economic conditions are having a significant effect on the supply market and will impact upon the viability and stability of a Framework at this time. 3.5 A significant number of projects on the Capital programme for 2012/13 are of a specialist/diverse nature and therefore does not necessarily lend itself well to maximising value for money from a generic framework agreement. 3.6 Since the last report in October 2011, the Council has tendered a significant number of projects applying a combination of the criteria headings (relevant to the scheme to be tendered) set out below and this has proved successful in stimulating the supply base and improving value for money:
• Market research –To ensure we have a good understanding of the supply market before tendering.
• Expressions of Interest – When suppliers express an interest into a specific project leading to an increase in competition.
• Experience, track record, capability and capacity – Ensuring suppliers have the necessary experience and can demonstrate a successful track record of delivery.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Capital Monitoring – Quarter 1 2026/2027Key Decision Following consideration of the report and its appendices, Cabinet resolved : (1) That the 2026/27 expend...
Consultation and Engagement PolicyKey Decision Following consideration of the report and its appendix, Cabinet resolved that the updated Consultation a...
CSC Ofsted Monitoring Visit UpdateNon-key Decision Following consideration of the report and its appendix, Cabinet resolved : (1) That the progress mad...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.