Resolved That permission be granted subject to conditions addressing the following matters, the precise number and form of which shall be delegated to the Head of Development Management: 1. Standard three year time limit for commencement 2. Development to proceed in accordance with the approved drawings 3. Any works in association with or construction of the atrium extension shall not commence until a phasing plan for the development has been submitted to and approved in writing by the Local Planning Authority. The development to proceed only in accordance with the agreed phasing approach. The phased approach must secure the restoration of the single theatre/auditorium prior to or alongside the construction of the atrium-style southern extension. 4. Demolition to take place by hand (to protect the listed building) 5. Scheme for protection of existing listed building features during works 6. Proposed internal elevation drawings 7. Detailed stage extension drawings 8. Retention and repair of the balcony structure 9. Details of rooflights and requirement to lie flush as indicated on elevation drawings 10. Slate sample 11. Eaves details and rain water goods specifications 12. External new windows and doors specifications 13. Brick plinth sample 14. Programme of works to increase public understanding of Frank Matcham , prominent theatre architect from Newton Abbot. Details of which to be submitted to and approved in writing by the Local Planning Authority and thereafter implemented.
Word for word from the decision Teignbridge published for this meeting.Source: democracy.teignbridge.gov.uk
Consent be granted subject to conditions addressing the following matters, the precise number and form of which shall be delegated to the Head of Development Management:
1. Standard three year time limit for commencement
2. Development to proceed in accordance with the approved drawings
3. Any works in association with or construction of the atrium extension shall not commence until a phasing plan for the development has been submitted to and approved in writing by the Local Planning Authority. The development to proceed only in accordance with the agreed phasing approach. The phased approach must secure the restoration of the single theatre/auditorium prior to or alongside the construction of the atrium-style southern extension.
4. Demolition to take place by hand (to protect the listed building)
5. Scheme for protection of existing listed building features during works
6. Proposed internal elevation drawings
7. Detailed stage extension drawings
8. Retention and repair of the balcony structure
9. Details of rooflights and requirement to lie flush as indicated on elevation drawings
10. Slate sample
11. Eaves details and rain water goods specifications
12. External new windows and doors specifications
13. Brick plinth sample
14. Programme of works to increase public understanding of Frank Matcham, prominent theatre architect from Newton Abbot. Details of which to be submitted to and approved in writing by the Local Planning Authority and thereafter implemented.
3. SUMMARY OF UPDATES FOLLOWING COMMITTEE DEFERRAL 3.1. Members will recall that these two linked planning and listed building consent applications were deferred from March 2024’s Planning Committee owing to the submission of late business case information by the applicant.
3.2Following the Committee, further business case information has also been submitted (dated April 2024) as well as revised drawings, which removed the northern loading bay that was proposed. As a result of the additional information, the recommended reason for refusal previously put to Members which related to the lack of public benefit justification for the heritage harm deriving from the proposed design is no longer considered necessary. The recommendation is therefore, now one of approval subject to conditions.
3.3Upon examination the business case information submitted just prior to March’s Committee did not relate directly to the proposed development scheme. It related to an alternative scheme which would not entail the restoration of the theatre but instead involved the retention of the dual-screen cinema ‘as is’. The Case Officer identified to the applicant the difficulty of using this business case information to assess the proposed application (which is specifically for the theatre restoration), and invited the submission of revised business case information, which has been received and is dated April 2024.
3.4A summary of the latest April 2024 Business Case is as follows:
• Two development and operational models are presented as ‘Plan A’ and ‘Plan B’
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.