ASHBURTON - 25/01752/FUL - Land at Goodstone

Approved Planning 1 paper

AI summaryTeignbridge Planning Committee approved a 279sq.m agricultural building at Goodstone, Ashburton, for a horticultural cut-flower business, with conditions on drainage, lighting, biodiversity, and solar panels. No CIL is payable.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedAgricultural building on agricultural land
MoneyCIL liability NilNo Community Infrastructure Levy payable
What happens nextConditions to discharge before useDrainage design within 3 months; BGP before start
Who it affectsApplicant and rural Goodstone siteHorticultural business with 3 FTE staff

What was decided

Planning permission approved for a 279sq.m agricultural (horticultural) building, subject to seven conditions covering plans, biodiversity, construction hours, surface and foul drainage, use restriction, solar PV and swift boxes. Report P1, 3.9

The building must be used for agricultural purposes only, excluding café, shop, workshop or educational uses. Report P15

At least 140sq.m of solar PV panels must be installed on the roof within three months of first use, and three integrated swift nesting boxes must be fitted to the north western elevation. Report P17

Why

A new agricultural building on agricultural land is acceptable in principle under Local Plan policies GP3 and CC4 and NPPF policy S5, with the applicant having justified the building size for the horticultural operation. Report 3.15

Surface water can be managed by a soakaway (the site is suitable) and foul water by a septic tank and drainage field, both to be secured by conditions, so flood risk and pollution will not increase. Report 3.19, 3.20, 3.21, 3.22

The Council's Biodiversity Officer raised no objection and a 10% Biodiversity Net Gain will be delivered on site; the Landscape Connectivity Zone position is addressed by lighting and construction-hour conditions. Report 3.5, 3.23, P80, P81

What happens next

A detailed surface water drainage design and maintenance plan must be submitted for written approval within three months of the planning approval. Report P11

A Biodiversity Gain Plan must be submitted to and approved by the Local Planning Authority before development commences. Report P5, P6, P94

The Planning Authority is separately progressing enforcement to require a further application to regularise wider unauthorised works at the site beyond the red line. Report 3.8, 3.17, 3.31

Options considered

  • Chosen: Approve subject to conditions (officer recommendation). Agricultural use acceptable in principle, drainage and biodiversity concerns addressed by conditions, use restriction overcomes mixed-use concern Report P1, 3.15, 3.17, 3.29
  • Rejected: Refuse due to potential mixed or non-agricultural use at the site. Condition 6 limits the building to agricultural use only, resolving the concern; NPPF policy DM3 supports working positively with applicants Report 3.16, 3.17

Implications

  • Environment and climate: Biodiversity Net Gain of at least 10% required via a Biodiversity Gain Plan before commencement; landscape enhancements already underway in the southern part of the field. Report 3.5, 3.13, P5, P94
  • Environment and climate: Construction restricted to daylight hours (30 minutes after sunrise to 30 minutes before sunset) from April to October, with no overnight lighting, to protect greater horseshoe bats linked to the South Hams SAC. Report P9, P10, 3.23
  • Environment and climate: Permanent external lighting on the new building is tightly controlled: low-lumen, LED, PIR-activated, downward-shielded, 2,700K or less, 550nm or more, to safeguard light-averse bats. Report P19, P20
  • Risk: Surface water flooding risk managed by a soakaway in a Critical Drainage Area, with detailed design to be approved in writing before installation. Report 3.19, 3.20, 3.21, P11
  • Risk: Foul drainage to be a septic tank and drainage field, installed before first use, to prevent wastewater pollution. Report P13, 3.22
  • Legal: Unauthorised works beyond the red line (including shipping containers, additional access, glasshouse use, signage for the Bloomin' Lovely Flower Farm café) are being handled under the Council's planning enforcement policy, not this application. Report 3.6, 3.7, 3.8, 3.31
  • Other: Devon County Council Minerals and the Devon Stone Federation raised no objection; the mineral resource beneath the field is treated as already sterilised by nearby dwellings. Report 3.28, P82, P83

Who and where

  • The applicant, operating a cut flower business (branded Bloomin' Lovely Flower Farm) with three full-time equivalent staff Report 3.11
  • The Council's Planning Authority, which is separately progressing enforcement for wider unauthorised works at the site Report 3.8, 3.17, 3.31
  • Greater horseshoe bats associated with the South Hams Special Area of Conservation, due to the site's Landscape Connectivity Zone position Report 3.4, 3.23

Timeline

  • 24 Oct 2025: Location plan, proposed floor plan, elevations and Small Sites Metric received Report P3, P6
  • 30 Oct 2025: BNG Statement received Report P6
  • 12 Nov 2025: First site visit; site recorded as undeveloped Report 3.1
  • 27 Apr 2026: Revised layout plan (TM58c.P1b+BNG2a V4) received with BRE 365 Soak-Away Test report Report P3
  • 2 Jul 2026: Second site visit; unauthorised works and a business operating as 'Bloomin' Lovely Flower Farm: Nursery and Café' discovered beyond the red line Report 3.6
  • Within 3 months of approval: Detailed surface water drainage design and maintenance arrangements to be submitted for approval Report P11
  • Before commencement: Biodiversity Gain Plan to be submitted to and approved by the Local Planning Authority Report P5, P94
  • Before first use: Septic tank and drainage field, swift boxes and surface water drainage system to be installed; foul drainage available for use Report P11, P13
  • Within 3 months of first use: At least 140sq.m of solar PV panels to be installed on the roof Report P17

Plain English for the jargon

  • BNG: Biodiversity Net Gain, a legal requirement for most planning permissions to deliver at least a 10% increase in biodiversity compared with the site baseline
  • BGP: Biodiversity Gain Plan, the document setting out how the required biodiversity net gain will be achieved and maintained
  • SAC: Special Area of Conservation, a European protected site for habitats and species; here, the South Hams SAC for greater horseshoe bats
  • Landscape Connectivity Zone: Land around a SAC used by greater horseshoe bats to travel and forage, where lighting and development can affect the protected population
  • Critical Drainage Area: An area identified by the Environment Agency as having known surface water flooding problems, requiring careful drainage design
  • CIL: Community Infrastructure Levy, a charge on new development to fund local infrastructure; here set at Nil for this agricultural use
  • PIR: Passive Infra-Red motion sensor, used to activate lights only when triggered by movement
  • Horticultural: Relating to the growing of plants, classed as a form of agriculture in planning terms
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item6a

Resolved

RESOLVED Planning permission be approved subject to the following conditions: 1. The development hereby permitted shall be carried out in accordance with the following approved plans/documents: Date Received Drawing/reference number Description 24 Oct 2025 TM58C.A1 Location Plan (1:12500) 24 Oct 2025 TM58C.P2 Proposed Floor Plan, Elevations & Roof Plan of SW Building 27 Apr 2026 TM58c.P1b+BNG2a V4 Appendix 1 Layout Plan within the BRE 365 Soak-Away Test report (numbered S26-29/365) REASON: In order to ensure compliance with the approved drawings. 2. Construction work shall only commence at least 30 minutes after sunrise and cease at least 30 minutes before sunset each day during the active season of bats (i.e., from April to October inclusive). No lighting shall be left on over-night during the construction phase. REASON: To protect light-averse bats during the construction period, in light of the site's location within the Landscape Connectivity Zone of the South Hams SAC. 3. No later than three months following approval of this application, the detailed design and maintenance arrangements of the proposed permanent surface water drainage management system shall be submitted to the Local Planning Authority for approval in writing. The design of this permanent surface water drainage management system shall comply with the site layout drawing ref. TM58c.P1b+BNG2a V4. Once approved, the surface water drainage management system shall be installed prior to first use of the hereby permitted new building and thereafter maintained in accordance with the approved arrangements. REASON: To ensure that surface water runoff from the development is managed in accordance with the principles of sustainable drainage systems, to prevent an increase in flood risk elsewhere, in accordance with Policy EN6 of the adopted Teignbridge Local Plan 2040 and Policies F7 and F8 of the National Planning Policy Framework 2026. 4. Three integrated swift nesting boxes shall be incorporated into the fabric of the building on its north western elevation, immediately under the eaves of the roof. The swift nesting boxes shall be installed prior to first use of the building and thereafter retained and maintained. REASON: To meet the requirement at Policy N2 of the NPPF 2026 for the incorporation of integrated nesting boxes. 5. Prior to first use of the hereby permitted new building, the foul water drainage septic tank and drainage field shall have been installed, made available for use and once installed shall be thereafter maintained. REASON: To prevent wastewater pollution arising from the development in accordance with Policy EN6 of the adopted Teignbridge Local Plan 2040 and P3 of the National Planning Policy Framework 2026. 6. The building hereby approved shall be used for agricultural purposes only and for no other use, including as a café, shop, for workshops or for educational purposes. REASON: To prevent uses which do not require a countryside location and have not otherwise been shown to require this location, in accordance with Policies GP3 and CC4 of the adopted Teignbridge Local Plan 2040 and S5 of the National Planning Policy Framework 2026. 7. No later than 3 months following first ...
Word for word from the decision Teignbridge published for this meeting. Source: democracy.teignbridge.gov.uk

Follow this further

Built from Teignbridge's papers

What the report saysPro

Report to Planning Committee

Recommendation

Planning permission be approved subject to the following conditions:

1. The development hereby permitted shall be carried out in accordance with the following approved plans/documents:

Drawing/reference Date Received Description number 24 Oct 2025 TM58C.A1 Location Plan (1:12500) Proposed Floor Plan, 24 Oct 2025 TM58C.P2 Elevations & Roof Plan of SW Building Appendix 1 Layout Plan within 27 Apr 2026 TM58c.P1b+BNG2a V4 the BRE 365 Soak-Away Test report (numbered S26-29/365)

REASON: In order to ensure compliance with the approved drawings.

2. The development hereby permitted shall be carried out strictly in accordance with the Biodiversity Gain Plan (BGP) approved under the General Condition relating to Biodiversity Gain.

The BGP shall be prepared in accordance with the BNG Statement submitted with the application and received on 30th October 2025 and the Small Sites Metric received 24th October 2025. The development hereby permitted shall be carried out strictly in accordance with the approved Biodiversity Gain Plan.

REASON: To ensure the development delivers biodiversity net gain in accordance with Schedule 7A of the Town and Country Planning Act 1990.

INFORMATIVE: The DEFRA Biodiversity Gain Plan Template should be used for the production of the BGP.

3. Construction work shall only commence at least 30 minutes after sunrise and cease at least 30 minutes before sunset each day during the active season of bats (i.e., from April to October inclusive). No lighting shall be left on over-night during the construction phase.

REASON: To protect light-averse bats during the construction period, in light of the site's location within the Landscape Connectivity Zone of the South Hams SAC.

4. No later than three months following approval of this application, the detailed design and maintenance arrangements of the proposed permanent surface water drainage management system shall be submitted to the Local Planning Authority for approval in writing. The design of this permanent surface water drainage management system shall comply with the site layout drawing ref. TM58c.P1b+BNG2a V4. Once approved, the surface water drainage management system shall be installed prior to first use of the hereby permitted new building and thereafter maintained in accordance with the approved arrangements.

REASON: To ensure that surface water runoff from the development is managed in accordance with the principles of sustainable drainage systems, to prevent an increase in flood risk elsewhere, in accordance with Policy EN6 of the adopted Teignbridge Local Plan 2040 and Policies F7 and F8 of the National Planning Policy Framework 2026.

5. Prior to first use of the hereby permitted new building, the foul water drainage septic tank and drainage field shall have been installed, made available for use and once installed shall be thereafter maintained.

REASON: To prevent wastewater pollution arising from the development in accordance with Policy EN6 of the adopted Teignbridge Local Plan 2040 and P3 of the National Planning Policy Framework 2026.

6. The building hereby approved shall be used for agricultural purposes only and for no other use, including as a café, shop, for workshops or for educational purposes.

REASON: To prevent uses which do not require a countryside location and have not otherwise been shown to require this location, in accordance with Policies GP3 and CC4 of the adopted Teignbridge Local Plan 2040 and S5 of the National Planning Policy Framework 2026.

7. No later than 3 months following first use of the building, solar PV panels covering at least 140sq.m shall be installed on the roof structure of the building and thereafter retained and maintained.

REASON: To meet the requirement for carbon/climate mitigation in accordance with Policy CC2 of the adopted Teignbridge Local Plan 2040.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
ASHBURTON: 25/01752/FUL: Land at GoodstoneReport 1.4 MB DownloadRead as text

At this meeting

Whole meeting

Who was there

9 of 21 attended
TC
Trish CornsOfficer, in attendance
PW
Councillor Peter WilliamsCommittee Member, present
LG
Councillor Linda Goodman-BradburyVice-Chair, in the Chair, present
DC
Councillor David CoxCommittee Member, apologies
JB
Councillor Janet BradfordCommittee Member, present
PB
Councillor Phil BullivantCommittee Member, present
AH
Councillor Alex HallCommittee Member, present
SH
Councillor Stephen HornerCommittee Member, present
PP
Councillor Paul ParkerCommittee Member, apologies
DP
Councillor David PalethorpeCommittee Member, present
SS
Councillor Suzanne SandersCommittee Member, apologies
KS
Councillor Kevin SmithCommittee Member, present

All 21 on the meeting page

On this subject at Teignbridge

Search all
  1. ASHBURTON - 25/01752/FUL - Land at GoodstoneThis decision
  2. 20/00400/FUL Ashburton - Higher Mead FarmApproved
  3. 22/02342/FUL - 128 Ashburton Rd - Newton AbbotApproved
  4. 21/00802/FUL - Higher Mead Farm, Alston Cross, AshburtonApproved

More from Teignbridge Planning Committee

All decisions
MeetingDecisionOutcome
22 Sep 2026 MinutesThe of the meeting held on 21 July 2026 were approved as a correct record and signed by the Chair. Approved Open
22 Sep 2026 BICKINGTON - 26/00876/MAJ - Land at Chipley MillRESOLVED a) The application be referred to the Secretary of State in accordance with the Town and Country Planning (C... Approved Open
21 Jul 2026 Kerswell-with-Combe - 25/01844/MAJ - Land at East of Buckland Road25/01844/MAJ - Land to the East of Buckland Road Newton Abbot Outline application for up to 50 dwellings, public open... Approved Open
12 May 2026 Woodland - 26/00353/HOU - Sunset Cottage House CrossRESOLVED Planning Permission be granted subject to the following conditions: 1. The development hereby permitted shal... Approved Open
12 May 2026 Teignmouth - 26/00275/HOU - 9 Woodland AvenueRESOLVED Planning permission be granted subject to the following conditions: 1. The development hereby permitted shal... Approved Open