Ipplepen - 25/00172/ENF - Siting of residential caravans
RefusedPlanning1 paper
AI summaryTeignbridge Planning Committee backed enforcement action against unauthorised residential caravans at Ipplepen, giving the applicant until 12 June 2026 to submit a valid planning application or face removal orders.
Written from the decision and the officer reportPDF Pro
OutcomeRefusedSubject to no valid planning application by 12 June 2026
MoneyNot stated
What happens nextOne month to submit valid applicationValidated by 12 June 2026
Who it affectsLand at IpplepenSite of unauthorised residential caravans
What was decided
Allow one month for a valid planning application to be submitted and validated by 12 June 2026, or issue an Enforcement Notice under Section 172 of the Town and Country Planning Act 1990.
The Notice, if issued, would require ceasing residential caravan use, removing the caravans, removing the unauthorised hardstanding, reinstating the land to grass, and removing all structures including two day rooms and a kennel. Report P2
If the Notice is not complied with within six months, the Solicitor is authorised to take further action under Section 179 of the Act. The Committee voted 7 in favour and 1 against. Report P3, P4
Why
The officer recommendation was to issue an Enforcement Notice under Section 172 of the Town and Country Planning Act 1990, with a six-month compliance period and Solicitor authority under Section 179 for non-compliance. Report P1, P2, P3, P4
The case was assessed against the Human Rights Act, including Article 1 of the First Protocol and Article 8, balancing the applicant's reasonable development rights and expectations against wider community interests, the Development Plan and Central Government Guidance. Report P5
The recommendation was made by the Head of Development Management. Report P6, P7
What happens next
The applicant has until 12 June 2026 to submit and have validated a valid planning application.
If no valid application is made, or any application is refused, the Enforcement Notice will be issued.
Once issued, the compliance period is six months, after which the Solicitor may act under Section 179 if the Notice is not complied with. Report P3, P4
Options considered
Rejected: Issue an Enforcement Notice immediately under Section 172 (officer recommendation). Modified to allow a one-month window for a valid planning application, with the deadline set at 12 June 2026 Report P1, P2
Chosen: Allow one month for a valid planning application, then issue an Enforcement Notice if none is submitted or it is refused. Decided by the Committee with 7 votes in favour and 1 against
Implications
Legal: Action grounded in Section 172 (issue of Enforcement Notice) and Section 179 (further action for non-compliance) of the Town and Country Planning Act 1990. Report P1, P4
Legal: Human Rights Act considered, including Article 1 of the First Protocol and Article 8, balancing the applicant's rights against wider community interests, the Development Plan and Central Government Guidance. Report P5
Risk: If the applicant submits a valid planning application by 12 June 2026, the Enforcement Notice will not be issued and the matter will proceed through the planning application route.
Who and where
The applicant, whose reasonable development rights and expectations were balanced against wider community interests Report P5
The owner and any occupiers of the land at Ipplepen where the residential caravans are sited Report P2
The local community at Ipplepen, whose interests were weighed in the balance Report P5
Timeline
2026-05-12: Planning Committee meeting; decision taken (7 votes for, 1 against)
12 June 2026: Deadline for a valid planning application to be submitted and validated
Six months (from issue of the Notice): Compliance period for the Enforcement Notice, if issued Report P3
Plain English for the jargon
Section 172, Town and Country Planning Act 1990: The legal power for a local planning authority to issue an Enforcement Notice where there has been a breach of planning control.
Section 179, Town and Country Planning Act 1990: The legal power covering further action, including prosecution, where an Enforcement Notice is not complied with.
Enforcement Notice: A formal notice served by a local planning authority requiring steps to be taken to remedy a breach of planning control.
Article 8, Human Rights Act: The right to respect for private and family life, home and correspondence, considered in the balance of interests.
Article 1 of the First Protocol, Human Rights Act: Protection of property, considered alongside the applicant's reasonable development rights and expectations.
What was decided, why, and what happens next
Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.
Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item159a
Resolved
RESOLVED To allow one month for a valid planning application to be submitted. If no planning application is submitted and validated by 12 June 2026, or any subsequent planning application is refused, an Enforcement Notice be issued under Section 172 of the Town and Country Planning Act 1990 to: i) Cease using the land for the siting of caravans for residential purposes. ii) Remove the caravans and any other items associated with the unauthorised residential use from the land. iii) Remove the unauthorised hardstanding and reinstate the land to grass. iv) Remove all structures that have been constructed on the land, including two day rooms and a kennel. In the event of the Notice not being complied with, within six months the Solicitor be authorised to take further action as necessary under Section 179 of the Act. (7 votes for and 1 against)
Word for word from the decision Teignbridge published for this meeting.Source: democracy.teignbridge.gov.uk
25/00172/ENF 1. REASON FOR COMMITTEE CONSIDERATION
Unauthorised change of use of the land from an agricultural to the siting of residential mobile homes.
2. THE ALLEGED BREACH OF PLANNING CONTROL AND ENFORCEMENT INVESTIGATION FINDINGS
2.1The land is located at the far end of the road leading through Dainton, Ipplepen. The site is situated next to the railway line. The permitted use of the land is for agriculture. The key facts in this case are as follows:
There were around 6 caravans sited on the land when viewed on 22 January 2026 that appear to be being used for residential purposes.
No planning permission has been granted for the change of use of the land to site residential caravans.
In order to remedy the planning breach formal enforcement action is required.
3. BACKGROUND AND CONTEXT
3.1In May 2025 the Council received a complaint that works were being carried out to lay areas of hardstanding and the land was being used to site a number of caravans that were being used for residential purposes. From an initial investigation it was noted that the land in question had recently been sold. To assess what works were being carried out the Council contacted the new owner and a response was received from an agent who had been appointed to act on their behalf.
3.2From discussions with the agent they confirmed that the owner proposed to submit a planning application for a change of use of the land to allow it to be used as a gypsy site. Following further discussions a planning application was subsequently submitted in October 2025 for the change in use of land to a gypsy caravan site for the parking of six single family caravans with the construction of three day rooms and the resurfacing of parking and turning areas. However, due to insufficient information being submitted the application was never validated and eventually it was returned in January 2026.
3.3Following further complaints about activities occurring on the land a site visit was carried out on 22 January 2026 to assess the situation. From the visit it was noted that there were 6 touring caravans sited on the land that appeared to be being used for residential purposes. In addition it was clear that the majority of the site had been covered in hardstanding. Although it was claimed the area of hardstanding was being extended it appeared that the more recent works were to repair areas that had previously been covered. 3.4 As it was clear from the visit that the unauthorised residential use was continuing, and extensive groundworks have been carried out that would have required planning permission, the Council need to consider enforcement action to remedy the planning breach. Furthermore, the Council are continuing to receive complaints about activities occurring on the land.
3.5Although the owner and agent have been contacted and a new planning application was to be submitted to date no application has been received.
4. PLANNING CONSIDERATIONS FOR ENFORCEMENT ACTION
4.1Although the caravans have been sited on the land for about a year, there appears to be no evidence that they have been sited on the land and said land used for residential purposes for the necessary ten years to be established.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.