Resolved
Recommendation made that: 12.1 Cabinet notes the outturn position for 2008/09 12.2 Cabinet notes the position in relation to the possible EDRF reclaim 12.3 Cabinet approves the revised General Fund Capital Programme
Cabinet approved this item on Thursday 9 April 2009. Below is the council's own wording, with the papers it was decided on.
Resolved
Recommendation made that: 12.1 Cabinet notes the outturn position for 2008/09 12.2 Cabinet notes the position in relation to the possible EDRF reclaim 12.3 Cabinet approves the revised General Fund Capital Programme
BUDGET MONITORING REPORT 2008/09
To: Cabinet – 9 April 2009
Main Portfolio Area: Corporate
By: Financial Services Manager
Classification: Unrestricted
Ward: All
Summary: To inform Cabinet of projected General Fund, HRA and Capital budget variances for the financial year 2008/09.
For Decision
1.0Introduction
1.1This report enables Cabinet to take an informed view of the likely financial out-turn on the General Fund, HRA and Capital Programme for 2008/09.
2.0Summary Outturn Position 2008/09
2.1The latest budget monitoring information shows an anticipated overspend of £116k for the General Fund for 2008/09. The Council’s financial position has inevitably been affected by the global credit crunch and the unsettled banking environment. This has impacted upon the Council’s expenditure levels, investment income receipts as well as other income streams both due to reduced demand as well as potentially increased defaults on debts. There has been a dramatic uptake in concessionary fare passes; investment income has fallen due to the reduced interest rates; planning fees and land charge income have fallen due to the decline in the housing market; and the number of housing benefit claimants has risen significantly. These have all been on an unprecedented scale. However, the Council has reacted quickly by controlling discretionary spend and containing overspends wherever possible within existing budgets.
2.2The Housing Revenue Account (HRA) is currently reporting an underspend of £136k.
2.3The General Fund Capital Programme has been revised to reflect slippage on some schemes to 2009/10. The revised programme is shown at Annex 3 to this report. There are no changes to report to the HRA Capital Programme.
3.0General Fund Outturn 2008/08
3.1The following table shows the projected outturn as at 28 February 2009 for the General Fund Revenue Budget 2008/09: February Monitoring Variance in projected outturn from Director returns: £’000
CE, CMT and Executive Support Unit -5.0
Commercial and Operational -228.0
Development Services 408.0
Customer Services -63.0
Improvement & Performance -17.0
Legal 0.0
Housing & Community 48.0
Resources -135.0
Maritime 108.0
Projected outturn for 2008/09 116.0
The main reasons for this overspend are detailed below:
4.0Detailed General Fund Outturn
4.1Due to the work needed to align budgets with the new departmental structure, the budgets will not be presented in the new format for monitoring purposes until the new financial year.
4.2Commercial and Operational – An underspend of £228k is forecast. This is mainly due to reduced expenditure on the Parks and Waste DLOs (£264k) as well as substantial reductions in expenditure across the service (£108k), all of which are offset by a projected loss of income on off street car parking (£144k). It is also anticipated that future maintenance costs of the refuse vehicles will increase as they come to the end of their warranties. A sum of £150k is estimated as being needed to be set aside in an earmarked reserve to meet future costs of refurbishing these vehicles. In addition a sum of £100k is required as a contribution to capital towards replacement bins in 2009/10. Neither of these have been reflected in the reported monitoring position nor in the budget build report, but will be reviewed as the financial year draws to a close and the final outturn figures for Commercial and Operational Services are confirmed. They will also be assessed alongside other competing priorities.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Budget MonitoringReport | 118 KB | DownloadRead as text |
Follow Cabinet at Thanet and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 30 Apr 2026 | 26/013 - Pride in Place Impact FundDecision Making Panel to include the MP’s representing the district and relevant Cabinet members; 5. To recommend to ... | Agreed | Open |
| 19 Mar 2026 | 26/015 - Thanet Regeneration Programme - updateAGREED: To note the progress achieved in the delivery of the approved Thanet regeneration program projects in the rep... | Agreed | Open |
| 18 Dec 2025 | Asset Management Disposal of Surplus PropertyIt was agreed that converting these underperforming assets into capital could allow for direct reinvestment in the cr... | Agreed | Open |
| 10 Aug 2023 | Birchington Draft Neighbourhood PlanDecision Statement that the plan should proceed to a referendum. Councillor Kup spoke under Council Procedure Rule 20... | Agreed | Open |
| 17 Jun 2021 | Coastal Lifts Current PositionIt was agreed that maintenance work on the lift at Viking Bay would be undertaken and be completed by the beginning o... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.