26/015 - Thanet Regeneration Programme - update

Agreed Executive 4 papers

AI summaryThanet District Council Cabinet noted progress on the Thanet Regeneration Programme covering 16 projects in Margate and Ramsgate, with around £18m of capitalised expenditure at risk if projects are cancelled. The report goes to the Overview and Scrutiny Panel.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeAgreedCabinet noted programme progress and referred report to Overview and Scrutiny Panel
Money£18m capitalised, £1.6m interestCapitalised spend across portfolio; interest earned on grant balances since April 2021
What happens nextReferral to Overview and ScrutinyPanel will consider the report and Cabinet will then consider its recommendations
Who it affectsMargate and Ramsgate wardsMargate Central, Cliftonville West, Central Harbour, East Cliff, Newington

What was decided

Cabinet agreed to note the progress achieved in delivery of the approved Thanet Regeneration Programme projects set out in the report. Report P10

Cabinet agreed to refer the report to the Overview and Scrutiny Panel and to consider any recommendations the panel makes. Report P11

Why

The report is the programme-wide update following the previous Cabinet update on 27 November 2025, providing a project by project delivery and finance update on the council's government funded regeneration programme. Report P8, P14, P59

Projects are complex, involving property, construction, planning, service delivery and partnership issues, and Cabinet needs to track progress and emerging budget pressures. Report P15, P16

What happens next

The Overview and Scrutiny Panel will consider the report and Cabinet will subsequently consider any recommendations the panel makes. Report P11

The council is due to start going out to the market to identify operators for several sites, beginning with the Theatre Royal and the cafe next to the Clock House, and Newington is to be handed over to the Newington Community Centre Association. Report P19

A comprehensive assessment of the ongoing revenue impact of all projects is being finalised, and no project will be allowed to proceed to final delivery until the Section 151 Officer is satisfied it does not worsen the council's critically low reserve position. Report P41, P43, P45

The money

  • approximately £1.6m Interest earned on grant balances held since April 2021 for the Pathfinder schemes, benefitting the General Fund Report P29
  • approximately £18m Expenditure capitalised across the whole regeneration portfolio Report P30
  • £1.25m Capitalised expenditure to date on individual schemes within the portfolio Report P30
  • approximately 20% Share of the council's total forecast reserves and balances that a single abortive cost of this scale would represent Report P31
  • 20-30% Range of significant inflationary increases flagged as a programme-wide risk Report P51

Options considered

  • Rejected: Borrow to bridge funding gaps for projects that become unviable within current grant allocation. Considered a last resort because prudential borrowing would create long-term revenue costs in interest and Minimum Revenue Provision and add permanent pressure to the General Fund and MTFS Report P34
  • Chosen: Note the report only. Recommended course: note progress and refer to Overview and Scrutiny Panel for further consideration Report P9, P10, P11

Implications

  • Financial: Projects are currently forecast to be delivered within overall approved budgetary envelopes, but any deviation from the delivery plan presents a direct risk to the council's General Fund. Report P27
  • Financial: Under the CIPFA Code, if a project is cancelled or fails to deliver, capitalised costs must be written back to revenue as abortive costs, and the General Fund has no capacity to absorb such a charge. Report P28, P31
  • Risk: Programme-wide risks include budget pressures, 20 to 30 percent inflation, core service capacity, contractor failure, condition survey surprises and scope increase after initial cost estimates. Report P51
  • Legal: There are no legal implications from this noting report, but specialist legal advice will be sought on State Aid or Subsidy Control, Procurement, Property and Contracts for individual projects. Report P47
  • Equalities: There are no direct equalities implications, but the funding supports regeneration in Margate and Ramsgate and aims to improve employment opportunities for residents including those from lower socio-economic groups. Report 7.1, P56
  • Climate: There are no direct climate change and biodiversity implications from the report, but design processes aim to minimise carbon emissions through efficient design, materials and energy efficient services. Report P53
  • Staffing: Capacity of council core services to support delivery of significant programme spend is a risk, with the project team reviewing use of extra external resources and procurement routes. Report P51

Who and where

  • Residents of Margate Central, Cliftonville West, Central Harbour, East Cliff and Newington wards Report P7
  • Margate and Ramsgate communities, including people from lower socio-economic groups Report P56
  • Newington Community Centre Association, taking on the near-complete Newington Community Centre Report P19
  • EKC Group, which has opened the Margate Digital Campus to students Report P19
  • The local fishing fleet, with engagement due to recommence on fishing facilities Report P19

Timeline

  • April 2021: Council began holding Pathfinder scheme grant balances that have since earned around £1.6m in interest Report P29
  • 2024/25: Council experienced an overspend that left reserves at a critically low level Report P31
  • 2025/26: Council faced significant revenue pressure from the cessation of the Highways and Port schemes Report P29
  • 27 November 2025: Previous Cabinet update on the Thanet Regeneration Programme Report P59
  • End of February 2026: Cut-off for the actuals reported in Annex 2 Report P20
  • 19 March 2026: Cabinet considered this update and referred it to Overview and Scrutiny Report P2

Plain English for the jargon

  • CIPFA: Chartered Institute of Public Finance and Accountancy, the body that sets local authority accounting and prudential codes
  • MRP: Minimum Revenue Provision, the annual revenue charge a council must set aside to repay capital debt
  • MTFS: Medium-Term Financial Strategy, the council's multi-year financial planning document
  • RIBA Stage 3: Royal Institute of British Architects design stage at which a change control process is applied to manage scope changes
  • MHCLG: Ministry of Housing, Communities and Local Government, to which programme-wide risks for the central government funded projects are reported quarterly
  • EKC Group: East Kent Colleges Group, the further education provider that has opened the Margate Digital Campus to students
  • Pathfinder schemes: The council's earlier government funded regeneration projects whose grant balances have been held since April 2021
  • Section 151 Officer: The council officer with statutory responsibility for financial administration, who must be satisfied on the financial sustainability of projects
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
Item246

Resolved

AGREED: To note the progress achieved in the delivery of the approved Thanet regeneration program projects in the report; To refer this report to the Overview and Scrutiny Panel and subsequently consider any recommendations made by the panel.
Word for word from the decision Thanet published for this meeting. Source: democracy.thanet.gov.uk

Follow this further

Built from Thanet's papers

What the report saysPro

Report to Cabinet

26/015 Thanet Regeneration Programme update

Cabinet​ 19 March 2026

By​ Louise Askew, Head of Regeneration and Growth

Cabinet Portfolio Member​ Cllr Rick Everitt, Leader of the Council and Cllr Ruth Duckworth, Regeneration and Property Portfolio Holder

Key Decision​ No

Decision classification​ Unrestricted ​ Call in status​ Can be called in

Ward:​ Margate Central, Cliftonville West, Central Harbour, East Cliff, Newington.

Purpose of the Report This report provides an update to Cabinet on the projects within the Thanet Regeneration Programme. The report includes a project by project delivery and finance update for the programme.

Recommendation(s): It is recommended that Cabinet:

●​ Note the progress achieved in the delivery of the approved Thanet Regeneration Programme projects in this report.

●​ Refer this report to the Overview and Scrutiny Panel and subsequently consider any recommendations made by the panel.

1.​ Summary of Reasons

1.1​ The report includes a project by project update on the Thanet Regeneration Programme, including high-level timeline and financial information. The report, and the information held within it are correct at the time of publishing, some of the information may change as we move through the project development stages, and gaining further approvals. 2.​ Background

2.1​ This report provides Cabinet with an update on the progress of the council’s government funded Thanet Regeneration programme. This follows a programme wide update to Cabinet on 27 November 2025.

2.2​ The report provides a project by project update, highlighting where there has been positive progress and where issues have emerged that need to be resolved. The nature of the council’s regeneration programme is highly complex and diverse. All the projects are complex, involving a range of property, construction, planning, service delivery and partnership issues requiring significant time from the delivery teams, and key decisions to be taken by the Cabinet on a number of milestones through each project timeline. A number of these decisions have already been made and this report sets out any future decisions that will be required over the coming months.

2.3​ Where there are individual projects with particular budget pressures or risks, these are highlighted in this report. And although this report doesn't recommend any budget virements, there have been budget virements within the programme to enable delivery of the projects.

3.​ Relevant Issues

3.1​ Appendix 1 provides a project by project overview of the Thanet Regeneration Programme. The programme includes the following projects: ●​ Margate Digital ●​ Margate Creative Land Trust ●​ Margate Theatre Royal ●​ Access Walpole Bay ●​ Testing New Uses Walpole Bay beach facilities ●​ Testing New Uses participation and skills programme ●​ Skatepark ●​ Active Movement and Connections ●​ Margate Winter Gardens ●​ Creative Workspace and Access to Opportunities ●​ Broad Street ●​ Green Campus ●​ Clock House ●​ Pier Yard ●​ Fishing Facility ●​ Newington Community Centre

3.2​ Newington is near final completion and ready to hand over to the Newington Community Centre Association, EKC Group has opened the doors to students in the Margate Digital Campus - an amazing space for the young people of Thanet, engagement with the fishing fleet is due to recommence for the fishing facilities and the council are due to start going out to the market to identify operators for a number of sites and opportunities within the regeneration programme, starting with the Theatre Royal and the cafe next to the Clock House.

3.3​ Appendix 2 includes a financial update for the programme. This includes the budget position for each project, spend to date and information on the type of spend to date. The figures outlined in Annex 2 are actuals up to the end of February 2026.

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
20260319 Annex 1: Thanet Regeneration Programme Update: project information (1)Appendix 540 KB Download
PDF
20260319 Annex 2: Thanet Regeneration Programme Update: financial informationAppendix 48 KB Download
PDF
20260319 Annex 3: Thanet Regeneration Programme Update: financial information %Appendix 112 KB Download
PDF
26/015: Thanet Regeneration Programme: updateReport 220 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 11 attended
RE
Councillor Rick EverittChair, present
HW
Councillor Helen WhiteheadCommittee Member, present
SA
Councillor Steve AlbonCommittee Member, present
KB
Councillor Kristian BrightCommittee Member, present
RD
Councillor Ruth DuckworthCommittee Member, present
HK
Councillor Heather KeenCommittee Member, present
JB
Councillor Jill BayfordGuest, in attendance
JD
Councillor John DavisGuest, in attendance
BR
Councillor Brenda RogersGuest, in attendance
GR
Councillor George RusieckiGuest, in attendance
LW
Councillor Linda WrightGuest, in attendance

On this subject at Thanet

Search all
  1. 26/015 - Thanet Regeneration Programme - updateThis decision
  2. 26/012 - Thanet Regeneration Programme - procurement decisionDecided
  3. Thanet Regeneration Programme - Theatre Royal Project DecisionsApproved

More from Thanet Cabinet

All decisions
MeetingDecisionOutcome
30 Apr 2026 26/013 - Pride in Place Impact FundDecision Making Panel to include the MP’s representing the district and relevant Cabinet members; 5. To recommend to ... Agreed Open
18 Dec 2025 Asset Management Disposal of Surplus PropertyIt was agreed that converting these underperforming assets into capital could allow for direct reinvestment in the cr... Agreed Open
10 Aug 2023 Birchington Draft Neighbourhood PlanDecision Statement that the plan should proceed to a referendum. Councillor Kup spoke under Council Procedure Rule 20... Agreed Open
17 Jun 2021 Coastal Lifts Current PositionIt was agreed that maintenance work on the lift at Viking Bay would be undertaken and be completed by the beginning o... Agreed Open