Highway Works Programme 2010/11
A report by the Director of Kent Highway Services to the Thanet Joint Transportation Board on 24 March 2011
Introduction
1. This report summarises the identified schemes that have been programmed for construction by Kent Highway Services in 2010/11. Each County Council Directorate is expected to ensure that the cash limits for next year are adhered to. Any within-year Directorate pressures must therefore be met from these cash limits and budgets/work programmes would have to be adjusted accordingly.
Road Surface Treatments
2. Grip Fibre –see ANNEX A1 Thin Surfacing – see ANNEX A2
Highway Maintenance Schemes
3. Carriageway Schemes - see ANNEX B1 Footway Schemes - see ANNEX B2 Street Lighting Schemes - see ANNEX B3 Drainage Maintenance Works – see ANNEX B4 Weather Damage Repairs – see ANNEX B5
4. Indicated below are those schemes identified for the Thanet district for constructing 2010 / 11 funded through the Local Transport Plan.
Local Transport Plan Funded Schemes - see ANNEX C1 Public Rights of Way (LTP Funded) – see ANNEX C2 Developer Funded Schemes (Delivered by KHS) - see ANNEX C3
Other Works
5. Bridge Works - see ANNEX D1 District Council Funded Schemes - see ANNEX D2 County Members Highway Fund Works - see ANNEX D3 Major Capital Projects - see ANNEX D4
Conclusion
5. This report is for Members’ information
Contact Officers:
Dennis Button Community Delivery Manager 08458 247800 Gary Peak Local Transport Schemes Team Leader 08458 247800
Background documents: None ANNEX A – ROAD SURFACE TREATMENTS
ANNEX A1 – GRIPFIBRE: 5 - 15mm depth
Location Description Budget Status St James Terrace, Whole length £3,450 Work complete Birchington
ANNEX A2 – THIN SURFACING: 15 – 24mm depth
Location Description Budget Status Fairfield Road, Bromstone Road - Broadstairs £89,425 Work complete Broadstairs Road August 2010 King Street / Dane Hawley Street – Wilderness Hill £88,920 Work complete Road, Margate October 2010 High Street, Minster Monckton Road – Church Street £55,825 Work complete October 2010 Tothill Street, Minster From War Memorial – Monkton £106,785 Suspended due Road to emergency Drainage works. Surfacing to be carried out once work complete ANNEX B – HIGHWAY MAINTENANCE SCHEMES
ANNEX B1 – CARRIAGEWAY SCHEMES
Location Description Budget Status
None
ANNEX B2 – FOOTWAY SCHEMES
Location Description Budget Status Salisbury Avenue, Phase 4 Footway reconstruction £145,000 Completed October Broadstairs 2010 Westcliffe Road, Footway reconstruction £44,550 Deferred as not Ramsgate Operations priority site Westover Gardens, Footway reconstruction £41,900 Works completed Broadstairs August 2010 Park Crescent, Margate Footway reconstruction £78,750 Works completed October 2010
ANNEX B3 – STREET LIGHTING SCHEMES
There are no Street Lighting schemes planned for 2011/12. Inventory data collection is complete and will be followed by electrical and structural testing from which future programming of work will be developed.
ANNEX B4 – DRAINAGE MAINTENANCE WORKS
Gulley cleansing schedule We now have 12 machines working throughout Kent on a roughly District- based schedule of routes to complete gulley cleansing on a roughly 2 year cycle. Whilst cleansing, the operatives are gathering asset data on the gullies to determine how full they are. This will then be fed into an optimisation programme to determine the most effective return period for that road – gullies that do not fill up very often will be visited less frequently, and conversely those that are always full will be visited more often.
To deal with one-off gullies, we have 2 small “van packs” which are portable machines that can visit the more difficult sites to ensure they are cleansed. The schedules are being looked at to be able to publish these on a monthly basis to show where we will be visiting on a Parish basis. This is being developed at present.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
Highway Works Programme 2010/2011Report | 71 KB | DownloadRead as text |
Follow Joint Transportation Board at Thanet and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 10 Sep 2026 | Highways Forward Works ProgrammeIt was agreed that officers would investigate this report. · A request was made to ensure contractors collect warning... | Agreed | Open |
| 5 Jun 2025 | KCC Highways Works Programme: 2024/25 and 2025/26RESOLVED to note the report. | Noted | Open |
| 5 Jun 2025 | Parking and Waiting Review - Thanet VariousRESOLVED to note the report. | Noted | Open |
| 5 Jun 2025 | Civil Enforcement UpdateRESOLVED to note the report. | Noted | Open |
| 12 Jun 2014 | Minutes of Previous MeetingIt was AGREED, on the proposal of Councillor K Gregory, seconded by Councillor D Saunders, that, subject to that amen... | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.