CouncilMonitor
194 principal councils 228,996 meetings since 2000 2.8 million official papers archived Straight from each council's own publication system
Thanet District Council
Cabinet, Thursday 31 July 2014 at 7.00pm

Budget Outturn

Approved Executive 4 papers

Cabinet approved this item on Thursday 31 July 2014. Below is the council's own wording, with the papers it was decided on.

Item189

Resolved

THAT Cabinet notes the General Fund, HRA and capital outturn position for 2013/14; 2. THAT Cabinet approves the proposed movements to earmarked reserves as outlined in paragraphs 2.4 and 3.3 of the report.
Word for word from the decision Thanet published for this meeting. Source: democracy.thanet.gov.uk

Follow this further

Built from Thanet's papers

What the report saysPro

Report to Cabinet

BUDGET OUTTURN REPORT 2013/14

To: Cabinet – 31 July 2014

Main Portfolio Area: Finance

By: Interim Director of Corporate Resources

Classification: Unrestricted

Ward: All Wards

Summary: To inform Cabinet of the outturn position against the General Fund and Housing Revenue Account budgets and against the 2013/14 Capital Programme.

For Information

1.0Introduction and Background

1.1In February 2013 Council agreed the General Fund, Housing Revenue Account and Capital budgets for 2013/14. The purpose of this report is to advise on the outturn position against these budgets. Members should note that the figures within this report are subject to audit and are therefore draft at this stage.

2.0General Fund

2.1The Council has faced significant cuts in funding over the last four years which has resulted in a cut in the net revenue budget of 18% from 2010/11 to 2013/14 with further cuts in funding anticipated over the next few years. The figures for 2014/15 have been confirmed but the figures for 2015/16 are still provisional. Further cuts of 10% have been assumed for both 2016/17 and 2017/18. For 2013/14 management continued to try to deliver maximum savings to help ease some of the budget pressures moving forward, thus helping to ensure that the Council’s balances and reserves are sufficient to meet the needs of the Council over the medium term.

2.2Budget monitoring to Cabinet in year reflected a balanced budget position and this was despite the fact that when the budget was set in February 2013, it was still expected that Transeuropa would continue in business. The budgetary impact for 2013/14 as a result of them ceasing business was a shortfall of circa £836k. This was after terminating contracts at the Port wherever possible and cutting back on the running costs at both the Port and Harbour. Strict controls were continued with regard to recruitment. Managers were not allowed to recruit immediately as a post became vacant but instead took the opportunity to review the needs of the service, with ultimately all decisions with regard to whether a vacancy should be filled being taken by the Workforce Forum. Managers also worked diligently to make efficiency savings wherever possible and reduce discretionary spend. 2.3 As a result of the measures highlighted in paragraph 2.2 above and after various Reserve movements as detailed in 2.7 below, a General Fund breakeven position has been achieved in 2013/14. The following table shows the final position by Service:

Service Outturn Reason for Variance £’000s Chief Executive & 8 Miscellaneous minor overspends S151 The majority of this overspend reflects the write off of the Ferry operator debt as well as the provision for the pending Animal Exports Legal case, these are Operational Services 4,636 both offset within Corporate Services by the appropriate provisions as well as by additional Vacant Post savings and other minor underspends. Increased Planning income associated with Major Applications, savings on Community Services sports & leisure, contributions to (165) voluntary organisations and events, as well as various other minor underspends. Predominantly due the write off of Ferry Operator income and the use of New Corporate Services & (4,479) Homes Bonus to fund Animal Export Transformation provision, as well as additional Vacant Post savings and other minor variances. Total 0

2.4The movements to and from earmarked reserves as indicated at 2.3 above that have facilitated a breakeven position are proposed as per the table overleaf and include any movement on the HRA to ensure that this agrees to the Explanatory Forward and the Movement in Reserves statements within the Financial Statements. Movement in Reserves £000's

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Appendix 1Appendix 1 78 KB Download
PDF
Appendix 2Appendix 2 73 KB Download
PDF
Appendix 3Appendix 3 81 KB Download
PDF
Budget OutturnReport 100 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

6 of 26 attended
MI
Councillor Mrs Iris JohnstonChair, present
RN
Councillor Richard NicholsonCommittee Member, present
RE
Councillor Rick EverittCommittee Member, present
DG
Councillor David GreenCommittee Member, present
EG
Councillor Elizabeth GreenCommittee Member, present
MJ
Councillor Mike J HarrisonCommittee Member, present
SA
Councillor Steve AlexandrouGuest, in attendance
RW
Councillor Robert W BayfordGuest, in attendance
JC
Councillor Jack CohenGuest, in attendance
MK
Councillor Mrs Kay A DarkGuest, in attendance
RD
Councillor Rozanne DuncanGuest, in attendance
JE
Councillor John EdwardsGuest, in attendance

All 26 on the meeting page

On this subject at Thanet

Search all
  1. Budget OutturnThis decision
  2. Budget Outturn Report - 2011/12Approved

More from Thanet Cabinet

All decisions
MeetingDecisionOutcome
30 Apr 2026 26/013 - Pride in Place Impact FundDecision Making Panel to include the MP’s representing the district and relevant Cabinet members; 5. To recommend to ... Agreed Open
19 Mar 2026 26/015 - Thanet Regeneration Programme - updateAGREED: To note the progress achieved in the delivery of the approved Thanet regeneration program projects in the rep... Agreed Open
18 Dec 2025 Asset Management Disposal of Surplus PropertyIt was agreed that converting these underperforming assets into capital could allow for direct reinvestment in the cr... Agreed Open
10 Aug 2023 Birchington Draft Neighbourhood PlanDecision Statement that the plan should proceed to a referendum. Councillor Kup spoke under Council Procedure Rule 20... Agreed Open
17 Jun 2021 Coastal Lifts Current PositionIt was agreed that maintenance work on the lift at Viking Bay would be undertaken and be completed by the beginning o... Agreed Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies