RESOLVED to endorse the recommendations to Cabinet as outlined in the report: 1) That a previous decision to progress a plan for a Multi Purpose Hybrid model of operation for the Port, made by Cabinet on 2 March 2023, will not be implemented. This also means that the previously planned concession port operator model, supported by a grant from Pathfinder funding, will not be implemented. This recommendation does not however change the overarching objective to deliver a sustainable solution for the port in the long term; and, 2) That Cabinet grants approval to officers to develop a schedule of high level strategic options for the future of the Port (as described in section 3.9 of ... view the full minutes text for item 129.
Word for word from the decision Thanet published for this meeting.Source: democracy.thanet.gov.uk
Purpose of the Report To update the Overview and Scrutiny Panel on the Future Delivery Project which is focussed upon the long term sustainability of the Port of Ramsgate. This includes the concession operator procurement process which started in August 2024 and was formally abandoned in January 2025.
This report describes a proposed recommendation that will be made to Cabinet on 26 June 2025 to formally end previous approved plans to implement a concession port operator model, supported by a grant from Pathfinder funding. However this proposal does not change the overarching objectives for the port, which include ending the revenue deficit position and delivering a sustainable solution for the port in the long term. The report describes the rationale for reallocating £7.6m of Ramsgate Pathfinder funding away from the Port Future Delivery Project due to the deadline for spending that funding. That recommendation is set out in a separate report to Cabinet on 26 June 2025 but is now essential in order to retain that funding and deliver valuable local outputs via other existing projects.
None of the above changes the fundamental position or objectives for the port. There remains a strong strategic case for the Port of Ramsgate. The port’s strengths include its geographical location and excellent connectivity along with the short sea capacity and freight resilience it can offer. This strategic case has been recognised by successive council administrations who have made decisions in support of efforts to attract new operators. Civil servants have also been clear in recent discussions that they appreciate the strategic advantages offered by the Port of Ramsgate. Of particular significance is that as set out in paragraph 3.5.9 of this report (and as per Appendix 2) the Port of Dover has stated the strong advantage that Ramsgate can offer in efficient shipping connections and the potential that may exist for future collaboration.
The proposed reallocation of Pathfinder Funding has resulted in the recommendation to step away from the concession model. However there remains strong evidence of the potential that the port continues to offer and this report recommends that further options be scoped to deliver a sustainable long term solution for the port. Recommendations: Recommendation 1 That the Overview and Scrutiny Panel note and scrutinise the report and consider any representations to Cabinet in advance of its meeting on 26 June 2025;
Recommendation 2 That the Overview and Scrutiny Panel note and comment on the recommendation that Cabinet agrees that a previous decision to progress a plan for a Multi Purpose Hybrid model of operation for the Port, made by Cabinet on 2 March 2023, will not be implemented. This also means that the previously planned concession port operator model, supported by a grant from Pathfinder funding, will not be implemented. This recommendation does not however change the overarching objective to deliver a sustainable solution for the port in the long term.
Recommendation 3 That the Overview and Scrutiny Panel note and comment on the recommendation that Cabinet grants approval to officers to develop a schedule of high level strategic options for the future of the Port (as described in section 3.9 of this report) and bring those options back to Cabinet in the autumn (2025) for decision.
1. Summary of Reasons
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
25/014 - Health in All PoliciesRESOLVED to endorse the recommendations to Cabinet: To approve the adoption and implementation of the Health in All P...
26/008 - Draft 2026/27 HRA BudgetRESOLVED to endorse the recommendations as outlined in the report to Council as follows: The HRA budget for 2026/27 w...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.