Resolved
To approve CIL funding for the following scheme detailed in Table 1 of the report.
Full Council approved this item on Tuesday 9 July 2024. Below is the council's own wording, with the papers it was decided on.
Resolved
To approve CIL funding for the following scheme detailed in Table 1 of the report.
1.1This report seeks to allocate a total of £1,504,534 of CIL funding for four infrastructure projects from the first application process in 2024 to support growth in Three Rivers.
1.2These 4 applications for funding are:
£817,231 - To replace the bridge due to its structural deterioration at Rickmansworth Aquadrome (submitted by Three Rivers Leisure)
£45,000 - For purchase and installation of Beryl Bike as part of Croxley Green Bikeshare Extension (submitted Regional Operations Manager Smidsy LTD T/A Beryl) Page 1 of 16 £456,400 - For Batchworth Depot Groundworks and Drainage (submitted by Three Rivers Director for Customer and Community)
£185,903 - For Chorleywood Common Youth Football Club (submitted by Chorleywood Common Youth Football Club (CCYFC)) for refurbishment of Pavilion.
2 Details
2.1Three Rivers became a Community Infrastructure Charging Authority on 1 April 2015. CIL is the main way in which the Council now collects contributions from developers for infrastructure provision to support development in the area.
2.2The Council has the responsibility for spending the CIL on infrastructure needed to support the development of the area, it is primarily a tool to support capital infrastructure. The Council has the opportunity to choose what infrastructure is prioritised in order to support development.
2.3Since the introduction of the CIL Charging Schedule in April 2015 a total of £12,715,050 has been collected.
2.4The CIL monies collected are divided into three pots – Main CIL Pot (80%) Neighborhood Pot (15%) and the remaining 5% set aside for the administration and the Exacom software costs to support the CIL in line with the CIL Regulations.
2.5This report relates only to the Main CIL Pot which, as of 6 April 2024 amounts to £6,904,829 (excludes previously agreed spend).
2.6Whilst this is a substantial amount, CIL does not generate enough funds to cover the whole cost of infrastructure needed to support planned development, as such there will be competing demands on the Main Pot from infrastructure providers who used to rely on S106 developer contributions (such as Hertfordshire County Council, NHS and TRDC etc.) going forward.
2.7What can CIL be spent on?
2.8Regulation 59 of the CIL Regulations states:
(1) A charging authority must apply CIL to funding the provision, improvement, replacement, operation or maintenance of infrastructure to support the development of its area, and
(2) A charging authority may apply CIL to funding the provision, improvement, replacement, operation or maintenance of infrastructure outside its area where to do so would support the development of its area.
2.9The definition of infrastructure in relation to CIL is set out in section 216(2) of the Planning Act 2008 (as amended by regulation 63 of the Community Infrastructure Levy Regulations);
a) roads and other transport facilities, b) flood defences, c) schools and other educational facilities,
Page 2 of 16 d) medical facilities, e) sporting and recreational facilities, and f) open spaces
2.10The Infrastructure List1 sets out the types of infrastructure that the Council intends will be, or may be, wholly or partly funded by CIL.
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
PDF |
CIL Spending Requests 2024/2025Report | 447 KB | DownloadRead as text |
PDF |
Enc. 1 for CIL Spending Requests 2024/2025Report | 351 KB | Download |
PDF |
Enc. 2 for CIL Spending Requests 2024/2025Report | 178 KB | Download |
PDF |
Enc. 3 for CIL Spending Requests 2024/2025Report | 212 KB | Download |
PDF |
Enc. 4 for CIL Spending Requests 2024/2025Report | 1.7 MB | Download |
Follow Full Council at Three Rivers and we tell you when its next papers are published, before the meeting rather than after it.
| Meeting | Decision | Outcome | |
|---|---|---|---|
| 20 Oct 2026 | Building safety levyThat: · Hertfordshire Building Control limited be authorised to undertake the role of centralised collecting agent fo... | Agreed | Open |
| 20 Oct 2026 | Aquadrome project - match funding requestThat: · £165,000 of capital funds be allocated to be used as match funding towards the Aquadrome Project as detailed ... | Decided | Open |
| 20 Oct 2026 | Budget monitoring report to 30 june 2026That: · The revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4.1.4 be approved and inc... | Noted | Open |
| 14 Jul 2026 | Appointment to CommitteesThat the appointments to committees and named substitutes be approved as amended. | Approved | Open |
| 14 Jul 2026 | Minor Amendments to Chorleywood Neighbourhood PlanThat Council agrees the minor amendments and adopts the update Chorleywood Neighbourhood Plan in Appendix 2. | Agreed | Open |
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Keeps you signed in and runs your free-paper allowance. Always on.
Counts visits and which pages are used. First-party only, no advertising, never shared.