CIL SPENDING APPLICATIONS – JANUARY 2026 APPLICATIONS

Approved Committee 6 papers

AI summaryThree Rivers Policy and Resources Committee approves £457,348 of CIL funding for three community sport and leisure infrastructure projects in 2026/27.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedBowl club, football pavilion, YMCA sports hub
Money£457,348 totalFrom Main CIL Pot in 2026/27
What happens nextFinance Director determines final fundingWith Lead Members for Resources and Planning
Who it affectsCroxley Bowls, CCYFC, One YMCAPlus Three Rivers district residents

What was decided

Approved £47,298 of CIL funding for Croxley Guild Bowls Club for clubhouse improvements, access to the green and a shelter. Report P7, P9

Approved £363,000 of CIL funding for Chorleywood Common Youth Football Club for refurbishment of the existing pavilion. Report P7, P10, P11

Approved £47,050 of CIL funding for One YMCA for refurbishment of the MUGA and 3G pitch at Woodlands Community Hub in Leavesden Country Park. Report P7, P12, P13

Why

All three applications were assessed as CIL eligible and scored sufficiently against the agreed eligibility criteria. Report P57

Officers consider the projects support local leisure facilities, align with Council Plan 2026 to 2029 objectives, and are deliverable with match funding. Report P70, P86, P104

CIL is the main way the council collects developer contributions for infrastructure to support development of the area. Report 3.1, 3.2

What happens next

A legal agreement will be put in place between Three Rivers District Council and each infrastructure provider to govern how the CIL money is spent. Report 4.3

Infrastructure providers must report on progress until the scheme is completed and all CIL funding has been spent, with an annual report required. Report 4.3

If CIL money is not spent within five years of receipt or is not spent as agreed, the council may require the applicant to repay some or all of the funds. Report 4.4

The money

  • £457,348 Total CIL allocation for the 3 approved projects Report 1.1
  • £47,298 CIL for Croxley Guild Bowls Club clubhouse and access works Report P3, P9
  • £363,000 CIL for Chorleywood Common Youth Football Club pavilion refurbishment Report P4, P10
  • £47,050 CIL for One YMCA MUGA and 3G pitch refurbishment Report P5, P12
  • £62,298 Total Croxley Bowls Club project cost, excluding VAT Report P53, P59
  • £417,754 Total CCYFC pavilion project cost, excluding VAT Report P54, P72
  • £54,550 Total One YMCA project cost, excluding VAT Report P55, P88
  • £15,013,037 Total CIL collected since the April 2015 charging schedule Report 3.3
  • £6,070,165 CIL funds previously committed by the council Report 9.1
  • £107,144 Christ Church Playground CIL bid, rejected as not eligible Report P41
  • £151,821 Watford and Three Rivers Trust Dig Deep CIL bid, not progressed Report P46

Options considered

  • Chosen: Approve all three CIL applications as recommended. Applications assessed as CIL eligible, deliverable, with match funding and aligned to Council Plan objectives Report P7, P57, P70, P86, P104
  • Rejected: Approve with alternative or reduced funding amounts. Officers proposed the full CIL request for each project as the funded works are CIL compliant Report 6.2, P70, P86, P104
  • Rejected: Christ Church Playground, Chorleywood C of E School, £107,144. Not considered strategic infrastructure, planning permission not yet sought, and benefit considered limited to the school community Report P41, P42, P43, P44, P45
  • Rejected: Watford and Three Rivers Trust, Dig Deep garden project, £151,821. Planning permission required for proposed structures and no current lease in place for the site Report P46, P47, P48, P49

Implications

  • Financial: Delegation allows the Director of Finance to consider reasonable changes to CIL funding to enable projects to proceed despite potential cost pressures. Report 9.2, P126
  • Legal: Legal agreements will govern the use of CIL funds, repayment of unspent monies, and ongoing reporting by the infrastructure providers. Report 4.3, 4.4, 10.1
  • Risk: Risks include failure to manage CIL income and expenditure, and projects not being delivered or paid on completion, both entered on the risk register. Report 11.2, P131, P132
  • Other: Officers identify no specific equalities, staffing, environmental, community safety, public health, customer services, communications or health and safety implications. Report 8.1, P122

Who and where

  • Croxley Guild Bowls Club members and visiting community groups including West Herts Beekeepers, Croxley Bridge and Cribbage Clubs, and Croxley Green Community Choir Report P61, P62, P63
  • Chorleywood Common Youth Football Club, with 47 teams including 10 girls' sides and male and female adult teams Report P78
  • Users of the Woodlands Community Hub MUGA and 3G pitch in Leavesden Country Park, including people with disabilities, youth programmes, and local sports clubs Report P96, P97, P98
  • Three Rivers District Council taxpayers and residents benefiting from improved community leisure infrastructure Report 3.2, P68, P69

Timeline

  • November 2024: Planning permission 24/0813/FUL approved for CCYFC pavilion extension and refurbishment Report P81
  • Within 5 years of receipt: Deadline by which CIL must be spent or risk repayment to the council Report 4.4
  • 31 December each year: Annual Infrastructure Funding Statement published under CIL Regulation 121A Report 4.5, P38
  • 1 January 2026: First CIL funding application period of 2026 opened, for 6 weeks Report 4.1
  • 31 March 2026: Main CIL Pot balance stood at just under £6 million Report 3.5
  • 2026/2027: Financial year in which all three CIL grants are required Report P53, P54, P55

Plain English for the jargon

  • CIL: Community Infrastructure Levy, a charge on new development collected by the council to fund infrastructure
  • Main CIL Pot: 80 per cent of CIL receipts retained by the council for strategic infrastructure, separate from the 15 per cent Neighbourhood Pot and 5 per cent administration share
  • MUGA: Multi-Use Games Area, a fenced outdoor court marked for sports such as tennis, netball and basketball
  • 3G pitch: Third generation artificial football pitch surface
  • S106: Section 106 planning obligations, developer contributions used alongside CIL for infrastructure
  • TRDC: Three Rivers District Council
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPR724

Resolved

· That Members approve CIL funding for the following schemes detailed in Table 1 of this report and summarized in the table below for 2026/27: Applicant & Project Name Infrastructure CIL Amount Croxley Guild Bowls Club, Croxley Guild of Sport, The Green, Croxley Green, Rickmansworth, WD3 3HT Improvements to clubhouse and access to Bowling Green and provision of a shelter £47,298 Chorleywood Common Youth Football (CCYFC) Lady Ela Drive, Chorleywood, WD3 5SL Refurbishment of Current Pavilion £363,000 One YMCA Woodlands Community Hub in Leavesden Country Park College Road, Abbots Langley Hertfordshire WD5 0GU MUGA and 3G Pitch Refurbishment £47,050 · The final funding and implementation of the 3 agreed projects is delegated to the Director of Finance, in consultation with the Lead Members for Resources and Planning Policy and Infrastructure, to determine to enable the agreed projects to be progressed and implemented.
Word for word from the decision Three Rivers published for this meeting. Source: moderngov.threerivers.gov.uk

Follow this further

Built from Three Rivers's papers

What the report saysPro

Report to Policy and Resources Committee

Summary

1.1This report seeks to allocate a total of £457,348 for 3 infrastructure projects from the CIL application process (January - June 2026) to support growth in Three Rivers.

1.2The 3 applications received for funding are:

 £47,298 for Croxley Guild of Sports and Social Club Croxley Bowls Club - Improvements to Clubhouse, access to Bowling Green and provision of a shelter.

 £363,000 for Chorleywood Common Youth Football Club (CCYFC) - Refurbishment of Current Pavilion.

 £47,050 for One YMCA - MUGA and 3G Pitch Refurbishment.

1.3In addition, 2 further CIL funding requests received were not considered eligible for CIL funding. Further details are below at paragraph 3.4.

Recommendation

 That Members approve CIL funding for the following schemes detailed in Table 1 of this report and summarised in the table below for 2026/2027:

Applicant & Project Infrastructure CIL Amount Name

Croxley Guild Bowls Improvements to Clubhouse and access to £47,298 Club, Croxley Guild Bowling Green and provision of a shelter of Sport, The Green, Croxley Green, Rickmansworth. WD3 3HT

Chorleywood Refurbishment of Current Pavilion £363,000 Common Youth Football Club (CCYFC)

Lady Ela Drive, Chorleywood, WD3 5SL

2 One YMCA MUGA and 3G Pitch Refurbishment £47,050 Woodlands Community Hub in Leavesden Country Park

College Road Abbots Langley Hertfordshire WD5 0GU

 The final funding and implementation of the 3 agreed projects is delegated to the Director of Finance, in consultation with the Lead Members for Resources and Planning Policy and Infrastructure, to determine to enable the agreed projects to be progressed and implemented.

3 Details

3.1Three Rivers became a Community Infrastructure Charging Authority on 1 April 2015. CIL is the main way in which the Council now collects contributions from developers for infrastructure provision to support development in the area.

3.2The Council has the responsibility for spending the CIL on infrastructure needed to support the development of the area, it is primarily a tool to support capital infrastructure. The Council has the opportunity to choose infrastructure to prioritise in order to support development.

3.3Since the introduction of the CIL Charging Schedule in April 2015 a total of £15,013,037 has been collected.

3.4The CIL monies collected are divided into three pots – Main CIL Pot (80%) Neighbourhood Pot (15%) and the remaining 5% is set aside for the administration and the Exacom software costs to support the CIL in line with the CIL Regulations.

3.5This report relates only to the Main CIL Pot which, as of 31 March 2026, amounts to a balance just under £6 million for infrastructure projects going forward.

3.6Whilst this is a substantial amount, CIL does not generate enough funds to cover the whole cost of infrastructure needed to support planned development, as such there will be competing demands on the Main Pot from infrastructure providers who previously relied on S106 developer contributions (such as Hertfordshire County Council, NHS and TRDC etc.) going forward.

3.7What can CIL be spent on?

3.8Regulation 59 of the CIL Regulations states:

(1) A charging authority must apply CIL to funding the provision, improvement, replacement, operation or maintenance of infrastructure to support the development of its area, and

3 (2) A charging authority may apply CIL to funding the provision, improvement, replacement, operation or maintenance of infrastructure outside its area where to do so would support the development of its area.

3.9The definition of infrastructure in relation to CIL is set out in section 216(2) of the Planning Act 2008 (as amended by regulation 63 of the Community Infrastructure Levy Regulations);

a) roads and other transport facilities, b) flood defences, c) schools and other educational facilities, d) medical facilities, e) sporting and recreational facilities, and f) open spaces

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Approved Infrastructure ProjectsAppendix 1 429 KB Download
PDF
CCYFC Spending Request FormAppendix 2 1.6 MB Download
PDF
CCYFC Equality Assessment FormsAppendix 3 160 KB Download
PDF
CCYFC Climate and Sustainability Assessment formAppendix 4 55 KB Download
PDF
Croxley Bowls Club Spending Request FormAppendix 5 407 KB Download
PDF
CIL SPENDING APPLICATIONS: JANUARY 2026 APPLICATIONSReport 552 KB DownloadRead as text

At this meeting

Whole meeting

Who was there

12 of 18 attended
SG
Councillor Stephen Giles-Medhurst OBEChair, present
LP
Councillor Louise PriceVice-Chair, present
CA
Councillor Christopher AlleyCommittee Member, apologies
AB
Councillor Aidan BentleyCommittee Member, present
OC
Councillor Oliver CooperCommittee Member, present
SC
Councillor Stephen CoxCommittee Member, present
SD
Councillor Steve DruryCommittee Member, present
VE
Councillor Vicky EdwardsCommittee Member, present
AF
Councillor Andrea FraserCommittee Member, present
CL
Councillor Chris LloydCommittee Member, present
PR
Councillor Paul RainbowCommittee Member, present
NS
Councillor Narinder SianCommittee Member, present

All 18 on the meeting page

On this subject at Three Rivers

Search all
  1. CIL SPENDING APPLICATIONS – JANUARY 2026 APPLICATIONSThis decision
  2. Cil spending applications – january 2026 applicationsApproved
  3. CIL Spending Applications – June 2025Approved
  4. CIL Spending Requests 2024/2025Approved
  5. CIL Spending Requests July 2024Approved
  6. CIL Spending Requests July 2024Agreed

More from Three Rivers Policy and Resources Committee

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Monitoring Report to 30 June 2026· That the revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4. 1. 4 be approved and in... Noted Open
8 Oct 2026 Planning Committees and the National Scheme of Delegation of Planning FunctionsThat Policy and Resources recommend to Council: · To agree the process and procedure detailed in Appendix 4, with min... Agreed Open
8 Oct 2026 Business Solar Panel GrantThat: · Policy and Resources Committee approve the revised terms of the Solar PV and Battery Grant Scheme: o Increasi... Approved Open
8 Oct 2026 Aquadrome Project - Match Funding RequestThat: · The Policy and Resources Committee recommends to Full Council that £165,000 of capital funds be allocated to ... Decided Open
8 Oct 2026 Cemetery Rules and RegulationsThat: · The Committee approves the revised attached at Appendix A. · The Committee authorises officers to implement t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies