Corporate Peer Challenge Action Plan

Approved Committee 5 papers

AI summaryThree Rivers Policy and Resources Committee has approved the Corporate Peer Challenge Action Plan with meeting amendments, including a note that a Ministerial Direction has superseded one recommendation and that actions cover only the Minister's seven additional sites.

AI summaryIn plain English

Written from the decision and the officer reportPDF Pro
OutcomeApprovedSubject to changes agreed at the meeting
MoneyNo new moneyAll actions within existing budgets
What happens nextPublish by July 2026Follow-up peer visit in February 2027
Who it affectsCouncil operations and staffIncludes staffing capacity work linked to LGR

What was decided

The Committee approved the Corporate Peer Challenge Action Plan, subject to amendments agreed at the meeting, including retaining the peer review's original wording, noting that a Ministerial Direction has superseded a recommendation, and making clear that actions relate only to the Minister's seven additional sites. Report P5

Public access to the decision was made immediate. Report P6

Why

An LGA Corporate Peer Challenge team visited the council from 10 to February 2026 and produced findings and recommendations; the council is expected to publish a clear action plan responding to all of them. Report 1.2, 1.3, 3.1

Under the Best Value duty, government expects all local authorities to have an LGA Corporate Peer Challenge at least every five years. Report 3.1

What happens next

The action plan should be agreed and published by July 2026, with delivery during the current financial year. Report 4.1, P15

A follow-up visit by peers is scheduled for February 2027 to check progress against the actions. Report P15

Options considered

  • Chosen: Agree the Corporate Peer Challenge Action Plan as set out (with meeting amendments). Responds to all peer challenge recommendations and supports sector-led improvement Report 4.1, 1.1, 1.3
  • Chosen in part: Suggest amendments that can be agreed. Committee added amendments at the meeting covering the Ministerial Direction and the seven additional sites Report 4.1
  • Rejected: Not implement the action plan. Would risk failing to achieve the recommendations in the Corporate Peer Challenge; risk rated 4 by impact and 4 by likelihood Report P41

Implications

  • Financial: No financial implications arising; all actions are within existing budgets. Report 6.1, 5.1
  • Legal: No legal implications arising. Report 7.1
  • Equalities: Equality Impact Assessment completed; no negative impact expected for protected groups, with some positive impacts identified. Report 8.1, P24, P25, P27
  • Climate: No environmental implications; a Sustainability Impact Assessment has been completed. Report P30
  • Risk: Risk of not implementing the plan is rated 4 (Very Likely) by likelihood and 4 (Catastrophic) by impact; officers classify it as an operational risk, reviewed annually by the Audit Committee. Report P41, 16.2, 16.4
  • Staffing: Actions will be delivered within existing staffing; one action on staffing capacity linked to LGR will be resourced within the 2026/27 budget. Report P29
  • Other: Communications on individual projects or actions will take place when appropriate, and the plan will be published on the council's website. Report P38

Who and where

  • Three Rivers District Council as a whole, through its service plans and risk register Report 16.2
  • Council staff delivering the actions within existing arrangements Report P29
  • Residents and community, assessed as facing no negative equalities impact Report P27

Timeline

  • 10 to February 2026: LGA Corporate Peer Challenge delivered at Three Rivers Report 1.2
  • 24 February 2026: Council Plan agreed (the relevant policy) Report 5.1
  • 2026-06-29: Policy and Resources Committee approved the Action Plan with amendments
  • by July 2026: Action plan to be agreed and published Report 4.1
  • February 2027: Follow-up visit by peer challenge team to check progress Report P15

Plain English for the jargon

  • CPC: Corporate Peer Challenge, an LGA improvement and assurance tool for councils.
  • LGA: Local Government Association, the body that runs the peer challenge.
  • LGR: Used in the report in the phrase 'LGR' alongside 'staffing capacity'; not defined in the supplied papers.
What was decided, why, and what happens next

Pro reads every officer report for you and explains each decision in plain English: the money, the options, the risks, the timeline, each with the paragraph it came from.

Written by AI from the council's published papers. AI can get things wrong: the council's own wording below is the record.Report a problem
ItemPR524

Resolved

That the be approved, subject to the amendments agreed at the meeting, and that public access to the decision be immediate. The original wording from the peer review be included. A note added that the recommendation had been superseded by the Ministerial Direction. The actions should explicitly reflect that work related only to the Minister’s seven additional sites.
Word for word from the decision Three Rivers published for this meeting. Source: moderngov.threerivers.gov.uk

Follow this further

Built from Three Rivers's papers

What the report saysPro

Report to Policy and Resources Committee

Summary

1.1The Local Government Association Corporate Peer Challenge (CPC) is a valued improvement and assurance tool the LGA offers to councils which is built on the principles of sector-led improvement.

1.2A team of local government peers, led by the Local Government Association (LGA) delivered a Corporate Peer Challenge (CPC) of Three Rivers District Council (TRDC) from 10-13 February 2026. This was the council’s second peer challenge, the first was in March 2019.

1.3The agreed CPC report attached at Appendix A provides TRDC with feedback on the peer team’s findings. It provides the council with a set of high-level recommendations alongside further recommendations under each of the CPC’s core areas. There is an expectation the council will publish a clear action plan to respond to all the recommendations highlighted. The proposed action plan is attached at Appendix B.

Recommendation

2.1That:

Policy and Resources Committee agree the Corporate Peer Challenge Action Plan.

That public access to the report be immediate. Report prepared by: Rebecca Young, Head of Strategy and Partnerships. Katie Stacey, Corporate Services Manager. 3 Details

3.1Local authorities are responsible for their own performance and improvement and are primarily accountable locally for this, through their local democratic mandates. Under the statutory Best Value duty, Government expects all local authorities to have a Local Government Association Corporate Peer Challenge (CPC) at least every five years.

3.2CPC is a tried and trusted method of improvement; it provides councils with a robust and effective improvement tool which is owned and delivered by the sector, for the sector.

3.3The CPC covered the following five core areas:

 Local priorities and outcomes

 Organisational and place leadership

2  Governance and culture

 Financial planning and management

 Capacity for improvement

3.3.1 Recommendations from the report and actions TRDC has developed cover these five areas. The actions will be delivered during this financial year and a follow up visit by the peers will take place in February 2027 to check on progress against the actions.

4 Options and Reasons for Recommendations

4.1The recommendation is to agree the Corporate Peer Challenge Action plan or make suggested amendments that can be agreed. The action plan should be agreed and published by July 2026.

5 Policy/Budget Reference and Implications

5.1The recommendations in this report are within the Council’s agreed policy and budgets. The relevant policy is entitled Council Plan and was agreed on 24 February 2026.

Financial implications

6.1None arising, all actions are within existing budgets.

7.1None arising.

8 Equal Opportunities Implications

8.1Relevance Test

Has a relevance test been completed for Equality Impact? Yes

Did the relevance test conclude a full impact assessment was No required?

8.2Impact Assessment

An Equality Impact Assessment (EIA) is contained within the appendices for this report. It is not anticipated that the updated Policy will have any negative impact on the groups with protected characteristics, with positive impacts on some groups listed. 9 Staffing Implications

10 Actions will be delivered within existing staffing arrangements. One action relates specifically to staffing capacity in connection with LGR and will be resourced in line with the approved 2026/27 budget.

3 11 Environmental Implications

None Arising – a Sustainability Impact Assessment has been completed and can be viewed in the appendix.

12 Community Safety Implications

None Arising

13 Public Health implications

None Arising

14 Customer Services Centre Implications

None Arising

15 Communications and Website Implications

The Action plan will be published on the website and communications on individual projects or actions will take place when appropriate. 16 Risk and Health & Safety Implications

Read every report as text, not just the decision

Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.

Papers for this item

Kept in our archive, download once signed in
PDF
Corporate Peer Challenge Action PlanReport 355 KB DownloadRead as text
PDF
Corporate Peer Challenge Action Plan Short_Equality_Impact_and_Outcome_Assessment_templateReport 328 KB Download
PDF
Corporate Peer Challenge Action PlanClimate and Sustainability Impact Assessment Internal V2Report 159 KB Download
PDF
Enc. 1 for Corporate Peer Challenge ReportReport 754 KB Download
PDF
Enc. 2 for Corporate Peer Challenge Action PlanReport 323 KB Download

At this meeting

Whole meeting

Who was there

12 of 18 attended
SG
Councillor Stephen Giles-Medhurst OBEChair, present
LP
Councillor Louise PriceVice-Chair, present
CA
Councillor Christopher AlleyCommittee Member, apologies
AB
Councillor Aidan BentleyCommittee Member, present
OC
Councillor Oliver CooperCommittee Member, present
SC
Councillor Stephen CoxCommittee Member, present
SD
Councillor Steve DruryCommittee Member, present
VE
Councillor Vicky EdwardsCommittee Member, present
AF
Councillor Andrea FraserCommittee Member, present
CL
Councillor Chris LloydCommittee Member, present
PR
Councillor Paul RainbowCommittee Member, present
NS
Councillor Narinder SianCommittee Member, present

All 18 on the meeting page

On this subject at Three Rivers

Search all
  1. Corporate Peer Challenge Action PlanThis decision
  2. Corporate Peer Review ReportAgreed

More from Three Rivers Policy and Resources Committee

All decisions
MeetingDecisionOutcome
8 Oct 2026 Budget Monitoring Report to 30 June 2026· That the revenue budget virements as set out in Appendices 1 to 3 and noted in paragraph 4. 1. 4 be approved and in... Noted Open
8 Oct 2026 Planning Committees and the National Scheme of Delegation of Planning FunctionsThat Policy and Resources recommend to Council: · To agree the process and procedure detailed in Appendix 4, with min... Agreed Open
8 Oct 2026 Business Solar Panel GrantThat: · Policy and Resources Committee approve the revised terms of the Solar PV and Battery Grant Scheme: o Increasi... Approved Open
8 Oct 2026 Aquadrome Project - Match Funding RequestThat: · The Policy and Resources Committee recommends to Full Council that £165,000 of capital funds be allocated to ... Decided Open
8 Oct 2026 Cemetery Rules and RegulationsThat: · The Committee approves the revised attached at Appendix A. · The Committee authorises officers to implement t... Approved Open

We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies