That the Head of Asset Management be authorised to; · Continue the existing contracts with suppliers on the Crown Commercial Service (CCS) framework · Enter into new supply contracts under any new CCS framework, subject to compliance with relevant procurement rules in order to secure the continued purchase of electricity for a further period of three years until the end of September 2018. Reason for Decision - as stated in the report This decision is not subject to call-in, (Chapter 4, Part 3, paragraph 10.14 (d)).
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
This report provides context on the Council’s current means of electricity purchase through framework contracts. The internal authority for the contracts will expire at the end of September 2015. If the contracts are to be terminated at the end of September 2015, notice of termination must be given by 31 March 2015.
This report, also, seeks authority for a strategy which will enable the Council to continue, for a further 3 years, to use flexible procurement frameworks managed by the Crown Commercial Service (CCS) in order to ensure continuity of supply of bulk purchased electricity until the end of September 2018, subject to new frameworks being put into place by CCS when the, existing, frameworks expire.
The Customer Access Agreement with CCS will continue to be available until the Council decides to terminate it.
Recommendations
1.1That the Head of Asset Management be authorised to; • Continue the existing contracts with suppliers on the Crown Commercial Service (CCS) framework
• Enter into new supply contracts under any new CCS framework, subject to compliance with relevant procurement rules
in order to secure the continued purchase of electricity for a further period of three years until the end of September 2018. 2. Introduction and Background
2.1Thurrock Council presently purchases electricity for its own operational buildings, e.g. offices, public buildings and libraries, and on behalf of Schools.
2.2The Council’s electricity contract spend is approximately £2.3m per year. The existing flexible procurement arrangements using CCS have allowed energy to be secured in advance, in a volatile energy market, thus enabling the Council to enjoy below market price electricity over the previous three years contract.
2.3The existing, internal, authority for procuring electricity will expire at the end of September 2015. This report sets out a future strategy for electricity procurement to achieve best value for the Council.
2.4Currently corporate buildings represent £1,059k (46%) of the annual electricity spend; Un-metered supply for street lighting represents £836k (36%), with schools accounting for £428k (18%) annually. The future take-up will only be known after individual schools have decided whether to continue participating.
2.5The procurement of energy in public sector organisations has been reviewed by the Office of Government Commerce’s Pan Government Energy Project. Due to the specialist nature of procuring energy and the inherent risks of procuring energy directly from spot markets a number of recommendations were made for public bodies. The key recommendation was that public sector organisations should purchase energy through an aggregated, flexible, risk- managed framework – effectively via a Central Purchasing Body which has the capacity to be expert in the electricity market and to achieve discounts by bulk purchasing.
2.6The existing Crown Commercial Services (CCS) electricity framework access agreement will continue to be available until the Council decide to terminate it. This allows for a seamless continuation of the framework contracts subject to member’s approval.
2.7This continuous process avoids the risk of out of contract rates being incurred by the Council and simplifies future migration between any new framework suppliers appointed by CCS.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.