That the updated Transforming Homes programme, based on principles approved by Cabinet in January 2013 as detailed in Appendix 1, be agreed. 2. Agree the Planned and Cyclical Maintenance Programme for 2015/16 as detailed in Appendix 2 and delegate the authority to the Director of Housing in consultation with the Portfolio Holder for Housing to commence a competitive tendering process and subsequently enter into any agreements pursuant to the Programme. 3. That it be agreed to proceed to tender for specialist contract management resource as detailed in Appendix 3. 4. That authority be delegated to the Director of Housing, in consultation with the relevant Portfolio Holder, to award the contract for specialist resource. Reason for Decision - as stated in the report This decision is subject to call-in
Word for word from the decision Thurrock published for this meeting.Source: democracy.thurrock.gov.uk
The purpose of this report is to seek approval on a range of areas within the Housing’s Investment and Maintenance Programmes with specific regards to Planned and Cyclical Maintenance for 2015/16 and a revised outline for Transforming Homes in accordance with principles for the programme approved by Cabinet in Feb 13. The revisions will ensure the Council is able to maximise outcomes from the proposed Housing Estate Regeneration programme. The report also provides an update on social value outcomes that have been achieved, along with an outline of future targets designed to ensure we continue to make the most of the commissioning leverage associated with contracts linked with these programmes.
1. Recommendation(s)
1.1That the updated Transforming Homes programme, based on principles approved by Cabinet in January 2013 as detailed in Appendix 1, be agreed. 1.2 Agree the Planned and Cyclical Maintenance Programme for 2015/16 as detailed in Appendix 2 and delegate the authority to the Director of Housing in consultation with the Portfolio Holder for Housing to commence a competitive tendering process and subsequently enter into any agreements pursuant to the Programme. 1.3 That it be agreed to proceed to tender for specialist contract management resource as detailed in Appendix 3. 1.4 That authority be delegated to the Director of Housing, in consultation with the relevant Portfolio Holder, to award the contract for specialist resource.
2. Introduction and Background
Integrated Approach to Delivering Housing Investment Programmes
2.1The Council has taken a strategic and integrated approach to delivering the different programmes across housing and development. The capital investment programme integrates delivery of major capital improvement works, with planned, cyclical and responsive repairs where relevant and appropriate. The principles driving investment across the different strands of housing examine the scope of works, synergies across programmes and the broader strategic objectives of the Council such as leveraging large contracts to deliver local economic investment.
2.2In 2013, the Council commenced the planning and delivering of its Transforming Homes programme, terminated a failing repairs service and implemented a revised framework and delivery structure for delivery of an improved repairs service through an Interim Contract. This was followed in 2014 with establishing a new set of principles for and setting up of a Planned Maintenance programme. Integral to all these programmes has been taking a strategic approach to the planning, procurement and delivery and ensuring that this process is informed by residents and also delivers added value in line with the Council strategic objectives and corporate frameworks.
2.3Over the last two years in the process of establishing and delivering these programmes, a number of changes have taken place these include, changes to external funding obligations, emerging estate regeneration proposals (the impacts of which are explored in more detail under issues options and analysis). In addition, in this time, the Council established a social value framework, and a strategic partnership with job centre plus.
Read every report as text, not just the decision
Pro opens the officer report behind each decision, searchable and quotable, across every council we cover.
Thurrock Transport Strategy Adoption2.1 Cabinet approved the Thurrock Transport Strategy given in Appendix 1 to be progressed to Full Council for adoptio...
We use a cookie to keep you signed in and run your free-paper allowance, and an optional one to count visits. You can accept all, or choose. Privacy & cookies
Necessary
Keeps you signed in and runs your free-paper allowance. Always on.
Always on
Analytics
Counts visits and which pages are used. First-party only, no advertising, never shared.